Morrismarina
July 14th, 2008, 08:59 PM
Did somebody forget to order the cladding ?? :lol:

pinnacle1
July 14th, 2008, 11:08 PM
Hi,
Dispite Tiger giving me a bank account no: If you check R.E.R.A. website under Tiger, they are listed as an approved contractor, but it also says Marina Pinnacle, TRUST ACCOUNT NOT APPLICABLE, BANK ACCOUNT NOT APPLICABLE. This stinks. I am also trying to sell all mine now, but Tiger will not talk to any agents and are being really obtrusive. Completion dates are also being stated as December 2010. What a shower of shit these people are. I am writing to R.E.R.A. tomorrow, but I think they will give little resolution to the problems we are having.

pinnacle1
July 14th, 2008, 11:21 PM
For what it is worth. Has anyone got any up to date pics. You never know that might have put a few more blocks in.

Stephan23
July 16th, 2008, 06:24 PM
16.07.2008

Pic from MisterMark :okay:

http://i35.tinypic.com/156y4vn.jpg

pinnacle1
July 16th, 2008, 10:20 PM
Since January Tiger have built 17 floors. That one every 11days. I know that is poor for Dubai, but against British building that is not bad going.
I am not defending them, I still think they are a but of lying b******

pinnacle1
July 17th, 2008, 09:04 PM
Has anyone paid money into Tigers new Escrow account?

bylowsellhi81
July 17th, 2008, 10:31 PM
I just drove by the site and noticed one sheet of glass on the marinna side. I dont know if they are just testing the glass that will be used for the building or glasswork has started, any ideas?

scoot68
July 20th, 2008, 04:46 PM
http://i34.tinypic.com/24c8rd1.jpg

WhatIfTheWatersRise?
July 31st, 2008, 04:13 PM
You just have to laugh
http://www.arabianbusiness.com/11569-doka-ske50-makes-tiger-roar-on-71-storey-marina-pinnacle

Stephan23
July 31st, 2008, 08:09 PM
"Sharjah-based contractor Tiger International has opted for Doka's self-climbing formwork SKE50 system to work on the 71-storey Marina Pinnacle in Dubai Marina.

According to the company, the move is to help meet fast construction cycles and a tight deadline.

Although an established user of Doka formwork systems, Tiger International is using the self-climbing formwork system for the first time."


---------------------------

71 floors??? For real??!!

pinnacle1
August 8th, 2008, 12:44 AM
I noticed my comments about Tiger and the prices they are now quoting, has been deleted. Is there any reason? Have I upset someone?

AltinD
August 8th, 2008, 12:15 PM
I noticed my comments about Tiger and the prices they are now quoting, has been deleted. Is there any reason? Have I upset someone?

There you go.

pinnacle1
August 8th, 2008, 01:19 PM
Sorry, I thought it was in the interest of Pinnacle purchasers as to what the current prices of the apartments were.

AltinD
August 8th, 2008, 01:25 PM
^^ Sure is, but it's also against the forum rules.

malec
August 8th, 2008, 01:42 PM
:ohno: not again.

Audi04
August 8th, 2008, 03:13 PM
Any news about the completion date. Is it as mentioned before pushed till end 2010?

pinnacle1
August 9th, 2008, 12:56 AM
2010 was quoted direct from Tiger.

Audi04
August 9th, 2008, 06:15 AM
Thanks. I sent an inquiry to Tiger-Hamdy- on the due date. I don't expect much except the run around as usual if he replies. I going to Dubai solely this time around for my investment with Tiger. I will knock every door whether legal or otherwise. I am getting really sick and tired of their lies. They do have a good amount of my money with them.

Audi04
August 9th, 2008, 02:41 PM
I did get an email from Tiger stating the date being 2010. I am taking my case with RERA and putting as much pressure on them as I can to see an end to this scam.

pinnacle1
August 9th, 2008, 05:44 PM
I have just sent a letter to Waleed Mohammed Mohammed, as he is the seller on my conytract. I am sure he is fully aware of what Tiger are doing, delays, ignoring e.mails, not notifying it's clients of delays. But just in case he isn't I will give him the chance to reply and give reasons. I have also asked what Tiger propose to do about compensation. Of course on any development you expect delays, but not 2 1/2 years late.
I will probably just be ignored, but I think Tiger know, there is jack shit we can do about it.
R.E.R.A. is probably the best bet, as if enough complaints are recieved, R.E.R.A. will surely look into Tigers devious methods.

pinnacle1
August 10th, 2008, 11:10 PM
Hi,
Just recieved August update from Tiger.
Almost identical to July.
So bugger all work going on.
They also sent loads of pictures, but they could be from any floor in the building, and the two external shots they took, you could not make out the top of the building, so impossible to count the floors. Crafty sods.


Project: Marina Pinnacle Tower
4B+G+4P+HC+3S+58 Residential floors
Bldg. on: Plot No. 392-206
Location: Marsa, Dubai

I. ACCOMPLISHMENT TO DATE (As of 31 JULY 2008)

1. Finished concreting of slab and columns up to 52nd floor.
2. Finished concreting of core wall up to 55th floor and about to finish steel works at 56th floor level.
3. Finished plastering works of internal wall of all flat units up to 41st floor using CEMENT PLASTER (ready for tiles setting and wall paints). In progress works at 42nd floor.
4. Finished concreting of core wall stair-1 up to 52nd floor and core wall stair-2 up to 48th floor and at 49th floor ready for casting concrete.
5. Finished casting of concrete at lift lobby up to 51st floor and about to finish steel works for 52nd floor.
6. Finished casting of concrete at electrical and garbage room from 37th up to 38th floor and at 49th floor ready for casting concrete.
7. Finished concreting of slab at machine room (P1, P2, P3, & P4) @ 50th floor.
8. 95% finished fixing fire stop (fire zone) thermal fiber between AAC blocks and slab at 6th to 42nd Floor. 65% finished @ 43rd to 44th floor.
9. Finished staircase railings at core wall from 4th basement to 26th floor and in progress installation up to 46th floor at stair 1& up to 31st floor at stair 2.
10. Finished block works up to 46th floor and in progress works at 47th floor.
11. 37% finished installation of G.I. pipes riser for LPG Gas pipe lines by BC Lootah Gas contractor.
12. 75% finished in repairing of plastering works for internal wall and ceiling @ 7th up to 15th floor and in progress up to 37th floor using NATIONAL PAINTS product.
13. In progress installation and fixing of Sprinkler pipes (partial) for fire fighting at 6th up to 36th floor. Pipe risers from 4th basement up to 15th floor by subcontractor JUMA AL MAJID EST. and AL WAHAB.
14. In progress fabrication, installation and fixing of AC duct exhaust at 9th up to 32nd floor and G.I pipes at 9th up to 44th floor by NASH Gulf Electronics and TIGCC contractor.
15. Finished application of waterproofing on slab of kitchen and T&B @ 11th to 13th floor.
16. Finished ceramic tiles setting on wall of all kitchen and bathroom from 6th to 28th
Floors and in progress at 29th to 31st floor and 85% on floor tiles at 7th to 10th floor.



NEXT ACTIVITY FOR THE MONTH OF AUGUST 2008



1. Installation and fixing of steel rebar, shuttering works and casting concrete for core wall from 56th to 59th floor.
2. Installation & fixing of rebars and casting of concrete on lift lobby from 52nd floor.
3. Installation & fixing of rebars and casting of concrete for core wall stair-1 from 53rd to 54th floor. Core wall stair-2 from 49th to 52nd floor.
4. Installation and fixing of rebar and concreting of slab at electrical and garbage room from 39th to 41st floor.
5. Installation and fixing of rebar and concreting of slab of machine rooms (P1, P2, P3, P4) @ 51st floor.
6. Continue wall plastering using Dubai plaster on Bedrooms, corridors, kitchen, T&B and stairs.
7. MEP builders work.
8. Continue installation and fixing of staircase railings at core wall.(2sets)
9. Continuous AAC and SOLID blocks laying for walls and partitions.
10. Continuous work for all surfaces to receive spray plastering.
11. Jack-up of 3 sets tower cranes.
12. Continue installation and fixing of G.I. pipes and exhaust for AC ducting by TIGER.
13. Continue JUMA AL MAJID EST. and AL WAHAB activities for fire fighting (rough-ins of main and branches pipe for sprinklers).
14. Continue repairing of wall plaster by National Paints contractor.
15. Continue elevator activities by KONE contractor.
16. Continue floor tiles setting of all flat units.
17. Continue tile works on all kitchen and bathroom walls.
18. Continue fixing and installation of LPG gas pipes by BC Lootah gas contractor.

JimDublin
August 18th, 2008, 06:13 PM
http://www.ameinfo.com/166230.html

This may be of interest to some Investors. I note the statement that they are moving on to the 51st floor after completing 50th floors on schedule - which schedule was that!.

GoDubai!
August 18th, 2008, 06:26 PM
Nothing but PR. Why does property development have to be such a dishonest business. Tsk, tsk...

pinnacle1
August 19th, 2008, 08:57 PM
Jim
It's called the Taha schedule----we pay all our money and he says ta ha

bylowsellhi81
August 20th, 2008, 09:42 AM
http://www.ameinfo.com/166230.html

This may be of interest to some Investors. I note the statement that they are moving on to the 51st floor after completing 50th floors on schedule - which schedule was that!.

This Taha guy is a JOKE!!! The only reason he is there is his brother is the Owner of Tiger. We would not have all these issues if we had a real CEO.

Imre
August 22nd, 2008, 10:51 AM
first crane (Marina 101 side) going down.

Stephan23
August 22nd, 2008, 12:10 PM
Means topped out??!! :eek:

pinnacle1
August 22nd, 2008, 01:01 PM
Imre.

Sorry bit thick on construction side of things. Does this mean anything.

ZZ-II
August 24th, 2008, 12:29 AM
Means topped out??!! :eek:

not at 260m but seems construction is nearing its end :cheers:

pinnacle1
August 27th, 2008, 05:49 PM
Has anyone heard about compensation on the Pinnacle. Mores the point has anyone heard anything about the Pinnacle. Not seen a photo in ages. Did someone say they were going to visit the Tiger offices.

bizzybonita
September 1st, 2008, 02:37 AM
C/U 31/08/08


http://i34.tinypic.com/20hws4j.jpg


http://i37.tinypic.com/15x21kl.jpg

JimDublin
September 4th, 2008, 01:48 AM
Has anyone managed to get any information from Tiger about proposals for dealing with delay. They are pressurising me to make payments on a revised payment schedule but my fear is that if I do so it will be viewed as my acceptance of new terms which could exclude any compensation for dealys. All they keep saying is that they will deal with the contract and they are unwilling to provide information as to how they propose to deal with the ongoing delays. Any information from others appreciated.

pinnacle1
September 4th, 2008, 07:35 PM
I was offered revised payment plan last year. When I asked about compensation, Tiger told me that was my compensation. Tiger are not adhering to their contract, otherwise we would be sitting in our apartments by now. My contract clearly states completion June 2008. Lying bunch of bar stewards.

pinnacle1
September 4th, 2008, 07:53 PM
Instead of everyone keep moaning about Tiger, it's about time something was done. I e.mail twice a week, I written to the owner of the Tiger, and all just get ignored. Tiger are rude, unprofessional and a disgrace.
Maybe someone can draft a letter of complaint to R.E.R.A. that can be copied by all Pinnacle owners to sign and send on.
If knowone can be bother to write to R.E.R.A or seek legal advise, then they have no reason to complain, they will just have to watch Tiger robbing them of their money and walking all over them.
I am trying to sell my apartments ( please knowone ask how much, I have already had a waste of space asking the ins and outs, who is probably a tall building anorak) My agent contacted me saying Tiger will not release any information. So basically we are stuffed, unless we take legal action.

pinnacle1
September 4th, 2008, 08:21 PM
This is a press release by Tiger on 31st August


The new structure will provide the flexibility that Tiger Group requires to deal with the ever-changing needs associated with its many expanding projects throughout the UAE and the Middle East.

It will also enable the Group to meet the requirements of the expansion plans it has set in place, and ensure continued excellent service to its clients.

As part of the reshuffle, a series of new appointments has been made at top management levels across Tiger Group in order to strengthen its core team.

New managers have come on board at some Tiger Group subsidiaries to undertake such tasks as supervising and executing the Group's existing and forthcoming projects, and setting up strategic plans for the future.

The Group's existing management team has been shifted into a new department - the Facilities Services Department - which will oversee all of the Group's projects and manage all project facilities.

One of the notable results of the organizational restructuring was the promotion of Mohammed Taha from Managing Director to CEO of Tiger Properties, one of the region's most renowned real estate developers and a Tiger Group subsidiary.

Taha's 14 years of experience in the regional real estate and construction sectors makes him eminently qualified to hold this position, and Tiger Group plans to draw on his comprehensive knowledge and understanding of regional property and contracting markets to further build Tiger Properties' already impressive reputation.

The organizational restructuring of Tiger Group came about as the result of the Board of Directors' decision to carefully manage the Group's substantial growth by putting in place a management team to oversee its expansion and to help it keep pace with the accelerating pace of its business development.

The appointment of numerous highly-qualified personnel who have experience in a number of different areas will serve to further enhance the Group's operation, preparing it for significant expansion and growth, and allowing it to retain its leading position across all levels.

Mohammed Taha, is the guy I met at his office, who first of all would not come out, and then gave me a load of b******s about completion September 2009. This guy could not organise a piss up in a brewery, though alone organise a development.
God help us.

WhatIfTheWatersRise?
September 4th, 2008, 08:49 PM
Does anyone have any idea who the curtain wall (windows and cladding) contractors are? No sign of anything happening there which is very worrying.
Mag18 has started its outer shell already.:ohno:

pinnacle1
September 8th, 2008, 10:54 PM
Recieved from Tiger today, also loads of photos, nice to see they have started aluminium cladding.



SEPTEMBER 03, 2008

MONTHLY REPORT TO TIGER PROPERTIES

Project: Marina Pinnacle Tower
4B+G+4P+HC+3S+58 Residential floors
Bldg. on: Plot No. 392-206
Location: Marsa, Dubai

I. ACCOMPLISHMENT TO DATE (As of 03 SEPTEMBER 2008)

1. Finished concreting of slab up to 55th floor and columns up to 56th floor.
2. Finished concreting of core wall up to 58th floor and at 59th floor level steel work is ongoing.
3. Finished plastering works of internal wall of all flat units up to 45th floor using CEMENT PLASTER (ready for tiles setting and wall paints). In progress works at 46th floor.
4. Finished concreting of core wall stair-1 up to 55th floor and core wall stair-2 up to 51st floor and at 52nd floor ready for casting concrete.
5. Finished casting of concrete at lift lobby up to 55th floor and steel work is on going for 56th floor lift lobby.
6. Finished casting of concrete at electrical and garbage room from 39th up to 40th floor and at 41st floor ready for casting concrete.
7. Finished concreting of slab at machine room (P1, P2, P3, & P4) @ 50th floor. KONE start their works at 50th floor lift machine room.
8. 95% finished fixing fire stop (fire zone) thermal fiber between AAC blocks and slab at 6th to 46th floor. Fire Stop Chemicals application is at 23rd floor level.
9. Finished staircase railings at core wall from 4th basement to 26th floor and in progress installation up to 51st floor at stair 1& up to 46th floor at stair 2.
10. Finished block works up to 46th floor and in progress works at 47th and 48th floors.
11. 40% finished installation of G.I. pipes riser for LPG Gas pipe lines by BC Lootah Gas contractor.
12. 75% finished in repairing of plastering works for internal wall and ceiling @ 7th up to 20th floor and in progress up to 46th floor using NATIONAL PAINTS product.
13. In progress installation and fixing of Sprinkler pipes (partial) for fire fighting at 6th up to 40th floor. Pipe risers from 4th basement up to 42nd floor by subcontractor JUMA AL MAJID EST. and AL WAHAB.
14. In progress fabrication, installation and fixing of AC duct exhaust at 6th up to 36th floor and G.I pipes at 9th up to 45th floor by TIGCC AC workers and subcontractor.
15. Finished application of waterproofing on slab of kitchen and T&B @ 14th to 18th floor.
16. Finished ceramic tiles setting on wall of all kitchen and bathroom from 6th to 37th
Floors and 85% on floor tiles at 7th to 12th floor and in progress at 13th &14th floor.
17. Finished installation of mock up sample for granite marble walls and floorings @ 10th floor lift lobby by AL AIN CEMENT & MARBLE PRODUCTS.
18. On going installation for Curtain wall and aluminum works @ two sides, Front and right side elevation. Mullions were installed up to 31st floor level and front side balconies up to 23rd floor level.
19. Received deliveries of FCU and Air handling units. FCU’s were installed at all flats @ 10th floor level at approved coordinated locations. Other FCU’s were distributed to different flats and different floor levels.
20. on going installation of elevator railings for P8, P1, P2, P3 & P4.

NEXT ACTIVITY FOR THE MONTH OF SEPTEMBER 2008

1. Installation and fixing of steel rebar, shuttering works and casting concrete for core wall from 58th to 61st floor.
2. Installation & fixing of rebars and casting of concrete on lift lobby from 56th to 58th floors.
3. Installation & fixing of rebars and casting of concrete for core wall stair-1 from 56th to 58th floor. Core wall stair-2 from 52nd to 54th floor.
4. Installation and fixing of rebar and concreting of slab at electrical and garbage room from 41st to 43rd floor.
5. Installation and fixing of machine for elevator (P1, P2, P3, P4) @ 51st floor.
6. Continue wall plastering using Dubai plaster on Bedrooms, corridors, kitchen, T&B and stairs.
7. MEP builders work.
8. Continue installation and fixing of staircase railings at core wall.(2sets)
9. Continuous AAC and SOLID blocks laying for walls and partitions.
10. Continuous work for all surfaces to receive spray plastering.
11. Jack-up of 2 sets tower cranes.
12. Continue installation and fixing of G.I. pipes and exhaust for AC ducting by TIGER.
13. Continue JUMA AL MAJID EST. and AL WAHAB activities for fire fighting (rough-ins of main and branches pipe for sprinklers).
14. Continue repairing of wall plaster by National Paints contractor.
15. Continue elevator activities by KONE contractor.
16. Continue floor tiles setting of all flat units.
17. Continue tile works on all kitchen and bathroom walls.
18. Continue fixing and installation of LPG gas pipes by BC Lootah gas contractor.

ramzy
September 9th, 2008, 12:46 AM
According to a friend of mine who lives in MH, they're certainly working on this - something like floor 55. The design of the floors has changed. The frames are being fixed for the glass...

I have some pictures he has taken, but not sure how to upload them. I am happy to email them to someone if they want to share them on the forum.

icemannapoli
September 9th, 2008, 11:17 AM
Thanks Pinnacle1....could you upload some picture? I'm really impatient for that! :-) What do you think about cladding...is it nice?

depassage298
September 15th, 2008, 12:15 PM
Do you know ifthe Completion Date is still expected on June 2010?

bylowsellhi81
September 15th, 2008, 03:31 PM
Tiger Properties unveils deluxe towers

Tiger Towers, a luxurious project on the Dubai Waterfront, is the latest development from real estate major Tiger Properties, a report said.

Located on the Madinat Al Arab portion of the Dubai Waterfront, the twin condominium towers will rise to 170 meters and 185 meters, respectively, said a Gulf News report.

The towers feature a four-storey podium building and 3,000 sq m of retail space, adding up to a built-up area of 121,500 sq m.

There will also be a 48th floor roof-top restaurant and landscaped areas on the ground level.

'With Tiger Towers, we will establish a new benchmark for buildings in the Waterfront district - one of Dubai's most successful new urban neighborhoods. Tiger Properties envisions this high-rise project as an icon in the city, becoming Dubai's most luxurious urban condominium building,' Taha Mohammad, CEO of Tiger Properties, was quoted as saying in the report.


Source: Trade Arabia News

pinnacle1
September 15th, 2008, 09:30 PM
This is not much help to the Pinnacle purchasers. Now R.E.R.A. has been introduced, all the funds collected on the new project will go to the new project. Unfortunatly all the funds collected on The Pinnacle, a percentage has gone on finishing over Tiger projects, which is why The Pinnacle has had so many delays.
I don't think companies like Tiger should be allowed permission to continue building new projects, when there is so much uncertainty and lack of professionalism in their current projects.

dirtyharry1
September 17th, 2008, 08:25 AM
pinnacle1, yes, I agree with you, but then the Marina would be nearly empty... because most of the local developers are crooks and bastards... what a nice imagination to have only 50% of the towers in the Marina...!!!!!

JimDublin
September 30th, 2008, 01:56 AM
Matters are gone very quiet. Has anyone got any updated photos? Hopefully work is proceeding. Its difficult to get any proposals from Tiger as to how it proposes to deal with delays, yet they continue to press for payments.

khalid298
October 2nd, 2008, 03:59 PM
Things are getting more quiet because there is no progress at all.
I went yesterday to see the Site and unfortunately it was the same as it was last month, no improvement at all.

If really they want to complete the work they can do it within 6 months time. But they said that the project will be completed in June 2010 to take it easy.

icemannapoli
October 6th, 2008, 03:50 PM
Time has gone since last photo update....Anyone has some picture? Thanks a lot

icemannapoli
October 7th, 2008, 11:17 AM
Marina Pinnacle seems to go ahead speedily....7 floors up on the last service floor....look at the picture in TT discussion!! Maybe there are only 3-4 apartment floors needed to completion....

icemannapoli
October 7th, 2008, 11:26 AM
http://i519.photobucket.com/albums/u359/bipinchhabra/P1010478.jpg

This is what i was talking about!!

High Times
October 7th, 2008, 11:30 AM
Marina Pinnacle seems to go ahead speedily....7 floors up on the last service floor....look at the picture in TT discussion!! Maybe there are only 3-4 apartment floors needed to completion....

Mmmmmmmm :ohno:

khalid298
October 7th, 2008, 04:32 PM
Marina Pinnacle seems to go ahead speedily....7 floors up on the last service floor....look at the picture in TT discussion!! Maybe there are only 3-4 apartment floors needed to completion....

Is it sarcastic?

icemannapoli
October 7th, 2008, 05:57 PM
No...if you look at the render, you can count 12 balconies (floors) from the last service floor....and compared to this picture there are just 5 floors less... I'm wrong??

let me know

pinnacle1
October 7th, 2008, 08:28 PM
Tiger properties will continue at a slow pace, as they are holding back on the sale of at least two hundred apartments. When other developments catch up, the value of Tigers apartments will have doubled if not tripled, therefore they sale of their two hundred existing, will be equivelent of selling 4-6 hundred at the old price. They do not want current buyers selling, which is why no mortgages are available and why Tiger are so uncooperative, as this would be detrimentel to their future sales.

icemannapoli
October 9th, 2008, 08:19 PM
Here you can see better the improvements.

Thx Joannides

http://i35.tinypic.com/34ywcj4.jpg

icemannapoli
October 9th, 2008, 08:38 PM
If you look at the rendering image here

http://www.emporis.com/en/il/im?id=344794

you can notice 2 things:

1. In the rendering, between 1° service floor and 2° service floor there are 14 floors, while in real picture there are 16.... why? maybe the rendering was wrong....
2. According to the project, the executive floors are 16. Actually they built 7 of them, so there are just 9 floors to complete the structure (or 7 if they changed something in the project, but i don't think so).

With a 1 floor per week rithm, MP needs 2 months more or less to top out!!

pinnacle1
October 9th, 2008, 08:48 PM
I have one bed apartment on 16th floor. When Tiger took me to see it, the 16th floor is 6 above the first service floor, which makes the first service floor level 10. According to Tigers last report they were supposed to be completing floor 61 in September, I dont think so, whatever way you count it.

pinnacle1
October 14th, 2008, 12:06 AM
More bad news, have learnt today, Tiger are now saying completion December 2010.
Probably next month it will be June 2011

malec
October 14th, 2008, 12:11 AM
Seems reasonable to expect.

However why is this so slow? And where's the cladding?

depassage298
October 14th, 2008, 07:20 AM
More bad news, have learnt today, Tiger are now saying completion December 2010.
Probably next month it will be June 2011

Ok! and what is the compensation that we can expect for the 6 months delay?

pinnacle1
October 14th, 2008, 03:42 PM
Depassage, keep up. The delay will be 2 1/2-3 years. Completion was supposed to be June 2008. Well according to my contracts, are yours dated later?

Stephan23
October 14th, 2008, 09:15 PM
:okay:


http://i35.tinypic.com/v4xg85.jpg

depassage298
October 15th, 2008, 06:56 AM
Depassage, keep up. The delay will be 2 1/2-3 years. Completion was supposed to be June 2008. Well according to my contracts, are yours dated later?

I bought a 1 BR later on and my Contract says Completion June 2010.

pinnacle1
October 15th, 2008, 10:16 PM
Well this goes to show what a lying crooked bunch of bar stewards they are.

icemannapoli
October 16th, 2008, 06:53 PM
Thanks to Bizzybonita

http://i34.tinypic.com/2pt74wm.jpg

Stephan23
October 19th, 2008, 08:12 PM
What a wall.....

today by Dubai Steve,

http://i37.tinypic.com/2hqrvp1.jpg

icemannapoli
October 20th, 2008, 03:41 PM
:cheers: WOW!!

It seems they are preparing cladding.....finally...

Morrismarina
October 21st, 2008, 01:03 AM
Yeah will be great to see some cladding going on here. Will give us some idea of the finished look. :banana:

Joannides
October 27th, 2008, 07:10 PM
http://i38.tinypic.com/wujibc.jpg


http://i34.tinypic.com/5meslu.jpg


http://i33.tinypic.com/21kcoyo.jpg

Stephan23
October 27th, 2008, 08:30 PM
^^Great shots man !! :eek:

pinnacle1
October 27th, 2008, 10:27 PM
Only 7 more residential floors to go.
I read on a sales site that someone has bought the whole of the 51st floor and is now selling for 29 million. Thats one serious purchase.

Stephan23
October 28th, 2008, 12:55 PM
It takes over three years to build 60 floors. :nuts: Unbelievable
Around 40 months for 60 floors. :doh:

icemannapoli
October 28th, 2008, 08:57 PM
Does anyone know if MP owners must pay the 1% tax to get Land Registration document? If yes, how can I do that?

ramzy
October 29th, 2008, 01:01 PM
thanks for the photos Jo.

bizzybonita
October 29th, 2008, 02:10 PM
Yeah will be great to see some cladding going on here. Will give us some idea of the finished look. :banana:

That's what iam looking for ....:banana:

Stephan23
November 1st, 2008, 08:15 PM
http://i38.tinypic.com/9gkkf5.jpg

Stephan23
November 2nd, 2008, 06:35 PM
http://img151.imageshack.us/img151/6315/helicoptertour01nov0807yt0.jpg (http://imageshack.us)
http://img151.imageshack.us/img151/helicoptertour01nov0807yt0.jpg/1/w1600.png (http://g.imageshack.us/img151/helicoptertour01nov0807yt0.jpg/1/)

H.Maleki
November 6th, 2008, 06:01 PM
According To Stephan23 Picture, Is Marina Pinnacle Behind Marina 101?, Cause Im Getting Confused By That Picture.

icemannapoli
November 6th, 2008, 06:34 PM
Yes you are right... Marina Pinnacle is that one! and it's going up very fast now...let's hope!!

H.Maleki
November 7th, 2008, 10:54 PM
It looks Nice, Cant Wait To Go And Live There :)
How Many More Floors To Go, Looks Nearly Completed, Then Just needs The Glass, Then Finnished :D

AltinD
November 8th, 2008, 12:58 AM
From thursday night

http://i35.tinypic.com/17ack3.jpg

icemannapoli
November 8th, 2008, 01:52 PM
What place is this? it seems nice!

ramzy
November 12th, 2008, 12:51 AM
Any picture updates?

Are there people actually working on the building?

Stephan23
November 15th, 2008, 03:04 AM
http://flickr.com/photos/persiabellini/3030121286/

JimDublin
November 19th, 2008, 04:22 PM
Can I ask if anyone has made any progress with Tiger in agreeing revised payament terms to reflect the lengthy delay in completion (Several years). I cant seem to make any progress. If preferred you can Private message me

bizzybonita
November 19th, 2008, 11:00 PM
Today

http://i37.tinypic.com/30k7mms.jpg

depassage298
November 20th, 2008, 06:59 AM
What is the official completion date? Is it June 2010 or December 2010?

Dubai Cisco
November 22nd, 2008, 03:38 PM
Can I ask if anyone has made any progress with Tiger in agreeing revised payament terms to reflect the lengthy delay in completion (Several years). I cant seem to make any progress. If preferred you can Private message me


I managed to change and revise my payment term as followings:
The total outstanding 300,000 Dhs.

I have agreed to pay another 100,000 Dhs in three installments every four months (January, May & December 2009).

After that the remaining dues +/- 200,000 Dhs to be paid on completion date

H.Maleki
November 24th, 2008, 08:58 PM
So i take it, it wont be finnishing in June 2009, if your going to pay every 4 months, Right?

JimDublin
November 26th, 2008, 05:10 PM
http://www.ameinfo.com/176997.html

Take alook at latest press release issued by Tiger

'The timely progression of construction works on the Marina Pinnacle tower is testament to Tiger's highly renowned principles of development that encompass the most stringent dedication to planned delivery schedules and the implementation of the highest international standards of quality.'

I am not sure what clock they are following but this must rank as the worst abuse of langauge whre they mention timely!!! Just three years late and counting.

H.Maleki
November 29th, 2008, 03:26 AM
I Dont Get It :|

It just talks about the apartment, we know what it has and doesn't have, it doesn't really explain about when it will finish or why it takes so long, what a useless statement to produce.

Stephan23
December 2nd, 2008, 09:13 PM
http://img145.imageshack.us/img145/2245/imresolt116nk4.jpg (http://imageshack.us)

Stephan23
December 2nd, 2008, 09:13 PM
Slowest tower ever :doh:

Core out of ground since 08.2005 :ohno:

Imre
December 7th, 2008, 06:08 PM
07/December/2008

Dubai Marina,tallest block

http://img156.imageshack.us/img156/5135/imresolt004qp8.jpg (http://imageshack.us)

http://img255.imageshack.us/img255/292/imresolt006lm2.jpg (http://imageshack.us)

http://img258.imageshack.us/img258/9408/imresolt007bh2.jpg (http://imageshack.us)

ramzy
December 8th, 2008, 12:19 PM
Hi Imre

Thanks for the photo updates. Would you be able to get some close up shots of the Marina Pinnacle. Am interested to see what progress is made on the cladding and the glass work. Pleasssse.

AltinD
December 9th, 2008, 02:08 AM
Dec 8th

http://i33.tinypic.com/69orbr.jpg

http://i35.tinypic.com/20j2t8o.jpg

ramzy
December 11th, 2008, 01:16 AM
Thanks for the update AltinD.

It seems they are making progress, but slowwwwllyyyyy. zzzzzzzzzzzz

Brizzy-Mike
December 11th, 2008, 04:50 AM
Rather large buildings there.

malec
December 11th, 2008, 02:26 PM
^^ Wait till some get twice as big as the tallest now.

Imre
December 17th, 2008, 06:01 PM
17/December/2008

Dubai Marina, tallest block

http://img168.imageshack.us/img168/4648/imresolt03hy6.jpg (http://imageshack.us)

http://img136.imageshack.us/img136/5830/imresolt04jq6.jpg (http://imageshack.us)

http://img95.imageshack.us/img95/8915/imresolt05aq1.jpg (http://imageshack.us)

http://img136.imageshack.us/img136/1659/imresolt06aj4.jpg (http://imageshack.us)

http://img150.imageshack.us/img150/574/imresolt14jg9.jpg (http://imageshack.us)

http://img301.imageshack.us/img301/4084/imresolt27ol8.jpg (http://imageshack.us)

JimDublin
December 18th, 2008, 03:12 AM
Great photos IMRE thanks a lot

pinnacle1
December 18th, 2008, 03:47 PM
One floor every 10 days, is better than nothing. At least it is going up, fingers crossed.

Imre
December 19th, 2008, 02:37 PM
19/December/2008

Marina Pinnacle

http://img186.imageshack.us/img186/3589/imresolt032ai3.jpg (http://imageshack.us)

http://img183.imageshack.us/img183/4458/imresolt059wr9.jpg (http://imageshack.us)

http://img156.imageshack.us/img156/7340/imresolt061rz8.jpg (http://imageshack.us)

THEPOINT
December 19th, 2008, 10:13 PM
^^ Wait till some get twice as big as the tallest now.Awesome -- cant wait but will have to for 2 years before PT topps out ?

Imre
December 20th, 2008, 03:19 PM
20/December/2008


http://img255.imageshack.us/img255/2917/imresolt002pa2.jpg (http://imageshack.us)

http://img168.imageshack.us/img168/6730/imresolt057fs6.jpg (http://imageshack.us)

http://img255.imageshack.us/img255/402/imresolt062sp1.jpg (http://imageshack.us)

icemannapoli
December 22nd, 2008, 12:07 PM
This is going to be very nice!!

Few floors to completion....now we have 10+16+16+13 residential levels=55+G+4B+3Service

Imre
December 27th, 2008, 11:15 AM
27/December/2008

Marina Pinnacle

http://img249.imageshack.us/img249/7152/imresolt20hp4.jpg (http://imageshack.us)

http://img68.imageshack.us/img68/3875/imresolt30jr0.jpg (http://imageshack.us)

http://img68.imageshack.us/img68/9262/imresolt59xf7.jpg (http://imageshack.us)

http://img68.imageshack.us/img68/2932/imresolt60yn5.jpg (http://imageshack.us)

Stephan23
January 4th, 2009, 02:37 PM
http://i44.tinypic.com/b7mniw.jpg


http://i39.tinypic.com/24zavxu.jpg

Imre
January 8th, 2009, 03:10 PM
08/January/2009

Marina Pinnacle

http://img241.imageshack.us/img241/1084/imresolt044zl9.jpg (http://imageshack.us)

http://img340.imageshack.us/img340/1658/imresolt077tt8.jpg (http://imageshack.us)

http://img522.imageshack.us/img522/9492/imresolt078ml4.jpg (http://imageshack.us)

http://img518.imageshack.us/img518/6324/imresolt080mi4.jpg (http://imageshack.us)

ramzy
January 9th, 2009, 12:56 AM
Imre, as ever we are greatful for the photo updates.

WhatIfTheWatersRise?
January 9th, 2009, 02:05 PM
YES IMRE...THANKS FOR KEEPING US UP TO SPEED!^^

CIPUS
January 9th, 2009, 04:53 PM
64 or 65 F?

pinnacle1
January 13th, 2009, 11:24 AM
MONTHLY REPORT TO TIGER PROPERTIES

Project : Marina Pinnacle Tower
4B+G+HC+3S+58 Residential Floors
Bldg No. : Plot No. 392-206
Location : Marsa, Dubai

1. ACCOMPLISHMENT TO DATE (As of JANUARY 04, 2009)

1. Finished concreting of slab, columns and lift lobby up to 64th floor.
2. Finished concreting of core wall up to 65th floor.
3. Finished plastering woks of internal wall of all flats units up to 51stfloor using DUBAI CEMENT PLASTER (ready for wall tiles setting and wall paints). In progress works at 52nd floor.
4. Finished concreting of core wall stair-1 up to 64th floor and core wall stair-2 up to 64th floor level.
5. Finished concreting of electrical and garbage room up to 53rd floor and finished form and steel works at 54th floor ready for casting concrete.
6. 95% finished fixing fire stop (fire zone) thermal fiber between AAC blocks and slab up to 51st floor and 75% in progress at 52nd and 53rd floor.
7. Finished staircase railings at core wall up to 43rd floor and in progress installation up to 60th floor at stair-1 at stair-2 in progress installation up to 49th floor.
8. Finished block works up to 55th floor and in progress block works at 56th floor.
9. 90% finished installation of G.I. pipes riser for LPG Gas up 45th floor and 75% finished at kitchen gas pipe line up to 40th floor and in progress woks at 41st floor by BC Lootah Gas contractor.
10. 90% finished in repairing of plastering works for internal walls up to 51st floor and in progress up to 52ndfloor using NATIONAL PAINTS product.
11. Finished application of waterproofing on slab of kitchen and T&B up to 27th floor.
12. Finished ceramic tiles setting on wall of all kitchen and bathroom up to 44th floor and in progress works at 45th up to 49th floor, for floor tiles 88% finished up to 24th floor.
13. 85% installation of ceiling cornice at 9th floor up to 11th floor.
14. 85% finished installation of AC Ducting up to 43rd floor and in progress woks at 46th floor and 80% finished installation of chiller pipes up to 50th floor.
15. Finished installation of Fire Fighting pipe riser up to 44th floor and at 46th typical floor for Fire Fighting pipe lines at all flats.
16. Finished painting (primer coat) of internal walls of all flats and stair case up to 50th floor and for ceiling paint (primer coat) up to 25th floor.
17. 75% finished of balconies curtain wall at four elevations from 7ht floor up to 45th floor, and 75% at external curtain wall for front & right elevation at 6th up to 32nd floor.



NEXT ACTIVITY FOR THE MONTH OF DECEMBER 2008


1. Installation and fixing of steel rebar, shuttering works and casting of concrete on slab, columns and lift lobby at 65th floor.
2. Installation and fixing of steel rebar, shuttering works and casting of concrete on core wall from 66th floor.
3. Installation and fixing of steel rebar, shuttering works and casting of concrete for core wall stair-1 at 65th floor and core wall stair-2 from 64th floor.
4. Installation and fixing of rebar, shuttering works and casting of concrete on electrical and garbage room from 54th up to 60th floor.
5. Continue on wall plastering using Dubai plaster on bedrooms, corridors, kitchen, T&B and stair.
6. MEP builders work.
7. Continue installation and fixing of stair case railing at core wall (2sets).
8. Continuous AAC and SOLID blocks laying for walls and partitions.
9. Continuous works for all surfaces to receive spray plaster.
10. Jack-up on 2 sets of tower cranes.
11. Continue installation and fixing of chiller pipes and exhaust for AC ducting by TIGER.
12. Continue activities for Fire Fighting rough-ins of main and branches pipe for sprinkler, by JUMA AL MAJID EST.
13. Continue repairing of wall plaster by TIGER using National Paint product.
14. Continue elevator activities by KONE contractor.
15. Continue floor tiles setting of all flat units and wall tiles setting for all kitchens and bathrooms.
16. Continue fixing and installation of LPG gas pipes by BC Lootah gas contractor.

icemannapoli
January 19th, 2009, 12:45 PM
no progress here since 8th January... :-( MAG 218 and The Torch are going faster!!

PICTURE TAKEN YESTERDAY (Thanks Jeetha)

http://i43.tinypic.com/rk09sj.jpg

Stephan23
January 21st, 2009, 11:24 AM
Anything is going faster than this one here !!! :wallbash:
How many floors for topping out??

dirtyharry1
January 21st, 2009, 01:07 PM
At least it won one award: The slowest tower in Dubai!

icemannapoli
January 21st, 2009, 07:13 PM
Still like one week ago....it needs just 2-3 floors to completion

Thanks DW

http://i36.tinypic.com/2e3bg4y.jpg

WhatIfTheWatersRise?
January 22nd, 2009, 10:19 PM
no progress here since 8th January... :-( MAG 218 and The Torch are going faster!!

PICTURE TAKEN YESTERDAY (Thanks Jeetha)

http://i43.tinypic.com/rk09sj.jpg

At least the other towers are moving along. It would be a disaster if the other towers weren't completed as no-one wants to look out at a building site.

JimDublin
January 27th, 2009, 12:23 PM
Are Tiger putting pressure on anyone to make payments? They appear to have gone very quite

pinnacle1
January 27th, 2009, 10:06 PM
not heard a word.
Their last e.mail to me said they would contact me with a revised schedule and compensation details

Imre
January 29th, 2009, 01:03 PM
29/January/2009

Marina Pinnacle

http://img299.imageshack.us/img299/1795/imresolt014qe4.jpg (http://imageshack.us)

http://img299.imageshack.us/img299/3515/imresolt019ld9.jpg (http://imageshack.us)

pinnacle1
January 29th, 2009, 10:16 PM
Spoke to Mr Hamdy today, asked why no additional floors had been built in the last month, and what was happening about compensation.
His reply was he did not know what was happening on site, and the last thing Tiger was worrying about at the moment was compensation. I continued to quiz him, but as usual, when he cannot answer questions he hangs up. Tried to call him back, but he was busy. Looks like they are in the shit.

bylowsellhi81
January 30th, 2009, 03:26 AM
Spoke to Mr Hamdy today, asked why no additional floors had been built in the last month, and what was happening about compensation.
His reply was he did not know what was happening on site, and the last thing Tiger was worrying about at the moment was compensation. I continued to quiz him, but as usual, when he cannot answer questions he hangs up. Tried to call him back, but he was busy. Looks like they are in the shit.

Hi Pinnacle,

Don't waste your time with him, hes going to drive you crazy :bash: . He lied to me in my face...in person...

ramzy
February 2nd, 2009, 02:00 AM
Hi

Does anyone actually know of someone or has managed to sell an apartment in marina pinnacle?

Please can you pm me if you prefer.

Ramzy

ramzy
February 2nd, 2009, 02:16 AM
What kind of capital appreciation could one expect on completion? 10, 20 , 30%?

Stephan23
February 5th, 2009, 08:11 PM
05.02.2009

http://farm4.static.flickr.com/3257/3256044158_d1131e905b_o.jpg

icemannapoli
February 6th, 2009, 12:16 PM
Finally they began to clad....look at the corners...there are several green window glasses!
But thay are still going toooooooo slow... :ohno:

icemannapoli
February 6th, 2009, 01:49 PM
One picture from today.... Nothing to comment, MAG218 is going very fast while Pinnacle is quit stopped :ohno:

Thanks to Desert Diver

http://www.quetschluft.de/dubai/300_1356_qa.jpg

pinnacle1
February 6th, 2009, 02:55 PM
I did recieve pictures from Tiger a couple of days ago, all internal, but a lot of tiling and marble going on, pictures of completed kitchens, so maybe they are doing a lot of internals. It has all got to be done I suppose, I'd be happy at the moment just to know it is going to be completed.

High Times
February 6th, 2009, 03:51 PM
Can you post the pictures please or is it all take take take.

I have personaly posted my pics on this thread of your tower and i have no financial interest in it.

Come on lets see the pics.

Were all one big SSC happy family. :)

icemannapoli
February 6th, 2009, 05:59 PM
Yes HT is right! Please post them! we are all waiting to see internal appliances...

pinnacle1
February 6th, 2009, 06:00 PM
They have sent them over on pdf, and as much as I have tried to find a way of sending them I don't have a clue. Would love to post them, if anyone can instruct. Sorry.

High Times
February 7th, 2009, 01:31 PM
They have sent them over on pdf, and as much as I have tried to find a way of sending them I don't have a clue. Would love to post them, if anyone can instruct. Sorry.
^^^^

Your interior pics extracted from the pdf. not great quality pics but at least you can get an idea of how things are looking inside.

http://i44.tinypic.com/33e3dag.jpg

http://i44.tinypic.com/2dtx1yq.jpg

http://i43.tinypic.com/359k1lc.jpg

http://i42.tinypic.com/wswlsj.jpg

http://i41.tinypic.com/earrxe.jpg

http://i41.tinypic.com/15iaija.jpg

http://i40.tinypic.com/2zsuqeh.jpg

pinnacle1
February 7th, 2009, 02:39 PM
HT

Did you get the updates

pinnacle1
February 7th, 2009, 02:42 PM
HT,
Considering the builder took these photos on his Indian mobile phone, they are not that bad.

High Times
February 7th, 2009, 03:14 PM
Considering the builder took these photos on his Indian mobile phone, they are not that bad.

Yes thats true,

Maybe when they sell a few more units he can upgrade his phone to 5megapics +. :)

Morrismarina
February 7th, 2009, 06:46 PM
Looks very good. Nice large tiles, very modern. And I like the light wood units. Certainly much better than we're going to get in the Torch.

Imre
February 8th, 2009, 02:37 PM
08/February/2009


http://img120.imageshack.us/img120/3783/imresolt067nm8.jpg (http://imageshack.us)

http://img24.imageshack.us/img24/5257/imresolt038in8.jpg (http://imageshack.us)

icemannapoli
February 9th, 2009, 11:55 AM
I don't like the kitchen wood.... but which apartment type is? T01,T02...

icemannapoli
February 13th, 2009, 12:35 PM
Any news from tiger? I'm happy that they are going ahead on internal fittings, while the external seem to be "on hold"...

ramzy
February 14th, 2009, 12:05 PM
Can someone remind me what a T10 aspect is? Does it face The Torch directly in front?

icemannapoli
February 14th, 2009, 12:19 PM
T10 is a one bedroom with a small balcony directly facing The Torch, but with a good marina view till MST is a parking area....

Imre
February 15th, 2009, 02:23 PM
15/February/2009

Marina Pinnacle

http://img4.imageshack.us/img4/4686/imresolt16pv9.jpg (http://imageshack.us)

http://img13.imageshack.us/img13/1244/imresolt18vr6.jpg (http://imageshack.us)

http://img261.imageshack.us/img261/8405/imresolt65fk9.jpg (http://imageshack.us)

http://img511.imageshack.us/img511/3369/imresolt66zt0.jpg (http://imageshack.us)

http://img12.imageshack.us/img12/9518/imresolt67cr4.jpg (http://imageshack.us)

ramzy
February 15th, 2009, 10:46 PM
thanks for the pics Imre.

Stephan23
February 16th, 2009, 09:48 AM
Looks like topped out in Imre's pics??!! :hm:

ramzy
February 16th, 2009, 09:55 AM
How can you tell? Imre are you able to capture the floor number?

Stephan23
February 21st, 2009, 10:44 PM
:omg: :okay:

This morning

http://i40.tinypic.com/a5hiqc.jpg

THEPOINT
February 23rd, 2009, 04:00 PM
:omg: :okay:
That'll be the view from PENTOMINUM in 2020 !! Can't wait !!

pinnacle1
February 23rd, 2009, 11:06 PM
Don't know if this is true, but I have just recieved an e.mail to say construction has stopped on Marina Pinnacle, and a for sale sign has gone up.
Has anyone any news.

malec
February 23rd, 2009, 11:49 PM
^^ We will see as more pictures come.

ramzy
February 24th, 2009, 12:59 AM
I too have received an email from someone else who has an apartment on MP regarding a for sale sign and construction stopped.

I have emailed a friend of mine in MH (assuming he hasn't fled Dubai) to see if he can shed light on this. :ohno:

If this is true, then I think we have a bigger problem on our hands.:bash:

Joannides
February 24th, 2009, 08:14 AM
^^

not true. just drove past MP 10 mins ago. construction HASNT stopped. the big for sale sign actually says "Luxury apartments for Sale":)

pinnacle1
February 24th, 2009, 10:13 AM
Thanks Joanrides.
The e.mail I recieved had gone to at least 150 adresses. Why are people always scaremongering?.

icemannapoli
February 24th, 2009, 10:47 AM
Thanks a lot Joannides!!

I hoped it was a "joke"... Tiger would be crazy to stop works now!! Anything is going well finally....
When someone can take other pictures from inside, he makes us happy...

pinnacle1
February 24th, 2009, 11:45 AM
I think it was put out by Tiger or an ex employee, otherwise how would someone have access to 150 plus e.mail addresses of Tigher clients.

pinnacle1
February 24th, 2009, 12:17 PM
This is what I recieved, maybe someone knows this idiot.


There is no sign of any construction going on there and there is a big For Sale sign on the building itself. These guys are a bunch of palestinian /syrian yahoos who have duped many people... good luck...


Lastly, take me off this list... i am done with this issue and tiger and the pinnacle that might never be...






On Mon, Feb 23, 2009 at 11:59 PM, Sonali Bahri <sonali.bahri@gmail.com> wrote:

Anjam
February 24th, 2009, 12:46 PM
Forward it to Tiger. If it is an (ex) investor they will know. The last thing you need in the current climate is for someone to start rumors and start a panic.

Good luck with your investment and hang in there!

Stephan23
February 24th, 2009, 03:36 PM
http://www.quetschluft.de/dubai/300_1949_qa.jpg

Stephan23
February 24th, 2009, 03:50 PM
http://www.quetschluft.de/dubai/300_1936_qa.jpg

pinnacle1
February 25th, 2009, 04:25 PM
Spoke with Mr Hamdy today, he confirmed construction is still going ahead, and the site can be inspected at any time, he confirmed things had slowed down, as per the rest of the marina, but they were still hoping for completion July 2010. So we can all sleep tight now, because we all trust Mr Hamdy.:ohno:

ramzy
February 26th, 2009, 01:03 PM
Did he mention about compensation for delays?:ohno:

pinnacle1
February 26th, 2009, 04:56 PM
I would love to get compensation, but I am more interested in having the project finished. I think if everyone starts claiming compensation as well, then the site will probably never get finished. I am not saying we should not get compensation, I just think the time is probably not right at the moment.

Imre
February 27th, 2009, 01:24 PM
27/February/2009

Marina Pinnacle

http://img291.imageshack.us/img291/427/imresolt048.jpg (http://imageshack.us)

icemannapoli
March 3rd, 2009, 12:05 PM
From Tiger update:

MONTHLY REPORT TO TIGER PROPERTIES
Project : Marina Pinnacle Tower
4B+G+HC+3S+58 Residential Floors
Bldg. No. : Plot No. 392-206
Location : Marsa, Dubai

1. ACCOMPLISHMENT TO DATE (As of MARCH 01, 2009)
1. Finished concreting of slab, columns and lift lobby up to 64th floor.
2. Finished concreting of core wall up to 65th floor.
3. Finished plastering woks of internal wall of all flats units up to 52nd floor using
DUBAI CEMENT PLASTER (ready for wall tiles setting and wall paints). In
progress works at 53rd floor.
4. Finished concreting of core wall stair-1 up to 64th floor and core wall stair-2 up to
64th floor level.
5. Finished concreting of electrical and garbage room up to 59th floor and start
installation of steel reinforcing bars at 60th floor.
6. 100% finished fixing fire stop (fire zone) thermal fiber between AAC blocks and
slab up to 54th floor and 85% in progress at 55th floor.
7. Finished staircase railings at core wall up to 50th floor and in progress installation
up to 60th floor at stair-1 at stair-2 in progress installation up to 50th floor.
8. Finished block works up to 58th floor and in progress block works at 59th and 60th
floor.
9. 90% finished installation of G.I. pipes riser for LPG Gas up 50th floor and 75%
finished at kitchen gas pipe line up to 48th floor and in progress woks at 49th and
50th floor by BC Lootah Gas contractor.
10. 90% finished in repairing of plastering works for internal walls up to 52nd floor
and in progress up to 53rd floor and at stair case 1& 2 up to 53rd floor using
NATIONAL PAINTS product.
11. Finished application of waterproofing on slab of kitchen and T&B up to 36th floor
and in progress at 37th floor.
12. Finished ceramic tiles setting on wall of all kitchen and bathroom up to 44th floor
and in progress works at 45th up to 49th floor, for floor tiles 90% finished up to 28th
floor and progress at 29th up to 32th floor.
13. 85% installation of ceiling cornice at 9th floor up to 11th floor.
14. 85% finished installation of AC Ducting up to 44th floor and in progress woks at
46th floor and 80% finished installation of chiller pipes up to 50th floor.
15. Finished installation of Fire Fighting pipe riser up to 50th floor and 50%at 48th
typical floor for Fire Fighting pipe lines at all flats.
16. Finished painting (primer coat) of internal walls of all flats and stair case up to 51st
floor and for ceiling paint (primer coat) up to 30th floor.
17. 90% finished of balconies curtain wall at four elevations from 6th floor up to 48th
floor, and 90% at external curtain wall for front & right elevation at 6th up to 48th
floor.
18. for cladding works 100% installed of runner and brackets at all elevation from 6th
to 32nd floor and continuous from 34th to above for all elevations.
19 95% installed of elevator machine at P1, P2, P3, P4, and P8, 15% installed at P5,
P6, and P7, start installation at S1 & S2 by KONE
NEXT ACTIVITY FOR THE MONTH OF MARCH 2009
1. Continuous fixing of steel rebar, shuttering works and casting of concrete on slab,
columns and lift lobby up to last floor` level.
2. Continuous fixing of steel rebar, shuttering works and casting of concrete on core
wall from 67th floor.
3. Installation and fixing of steel rebar, shuttering works and casting of concrete for
core wall stair-1 at 65th floor and core wall stair-2 from 65th floor.
4. Installation and fixing of rebar, shuttering works and casting of concrete on
electrical and garbage room from 60th up to 62nd floor.
5. Continue on wall plastering using Dubai plaster on bedrooms, corridors, kitchen,
T&B and stair.
6. MEP builders work.
7. Continue installation and fixing of stair case railing at core wall (2sets).
8. Continuous AAC and SOLID blocks laying for walls and partitions.
9. Continuous works for all surfaces to receive spray plaster.
10. Jack-up on 2 sets of tower cranes.
11. Continue installation and fixing of chiller pipes and exhaust for AC ducting by
TIGER.
12. Continue activities for Fire Fighting rough-ins of main and branches pipe for
sprinkler, by JUMA AL MAJID EST.
13. Continue repairing of wall plaster by TIGER using National Paint product.
14. Continue elevator activities by KONE contractor.
15. Continue floor tiles setting of all flat units and wall tiles setting for all kitchens and
bathrooms.
16. Continue fixing and installation of LPG gas pipes by BC Lootah gas contractor.

icemannapoli
March 3rd, 2009, 12:51 PM
Some pictures from inside.... Very poor quality! :ohno:

http://img6.imageshack.us/img6/7135/photo1jr5.jpg

http://img19.imageshack.us/img19/3245/photo2pv5.jpg

http://img18.imageshack.us/img18/2111/photo3vm8.jpg

http://img10.imageshack.us/img10/7352/photo4zv0.jpg

http://img17.imageshack.us/img17/2457/photo5ao7.jpg

http://img8.imageshack.us/img8/2203/photo6qp8.jpg

Naz UK
March 3rd, 2009, 02:01 PM
It is quite apparent now that for most of Dubai's luxurious apartments (apart from a few exceptions) the term "5-star interior quality" is obviously being compared to the average slum dwellings of Botswana.

Audi04
March 4th, 2009, 06:06 AM
naz uk- what does it stand for?

Imre
March 5th, 2009, 07:21 PM
05/March/2009

Dubai Marina , tallest block

http://img16.imageshack.us/img16/7962/imresolt69.jpg (http://img16.imageshack.us/my.php?image=imresolt69.jpg)


http://img213.imageshack.us/img213/8724/imresolt80.jpg (http://img213.imageshack.us/my.php?image=imresolt80.jpg)

Imre
March 7th, 2009, 06:13 PM
07/March/2009

Marina Pinnacle

http://i42.tinypic.com/30at43q.jpg

H.Maleki
March 8th, 2009, 12:11 AM
Looks like a shit hole, what is this?

Imre
March 8th, 2009, 03:56 PM
08/March/2009

Marina Pinnacle

http://i41.tinypic.com/24do5ys.jpg

icemannapoli
March 12th, 2009, 02:48 PM
Thanks Mackie1964

http://i39.tinypic.com/s488yx.jpg

Stephan23
March 15th, 2009, 10:10 PM
http://i44.tinypic.com/1oltsp.jpg

http://i40.tinypic.com/jkhy5h.jpg

pinnacle1
March 17th, 2009, 03:01 PM
Recieved e.mail today, Tiger chasing last but one payment. Being it is supposed to be going into an Escrow account, I thought they were not allowed to draw on that money until they had reached the equivilent amount of construction. Told them I was not paying until compensation had been agreed. Right or wrong? We will have to wait and see.

pinnacle1
March 19th, 2009, 04:51 PM
Had major row with Hamdy today, he made it quite clear that Tiger were not going to pay any compensation, also would not answer why Marina Pinnacle was registered as one building and not apartments, and why was money still being asked to be sent to Walheed Mohammed Mohammed (the owner) and not Marina pinnacle. It stinks.

JimDublin
March 20th, 2009, 12:34 PM
Has anyone approached RERA regarding any of these issues. As the agency with responsibiilties for the regualtion of the developmetns I would have thought that they may have and interest/responsibility in some of these issues?

pinnacle1
March 20th, 2009, 02:08 PM
I sent e.mail yesterday to R.E.R.A. awaiting a reply.

They only open 8 -2.30 Monday to Thursday

I think everyone should be sending them an e.mail, it will take more than just mine. Although I do have e.mail addresses of at least 50 other purchasers and have told R.E.R.A. that I was speaking on behalf of all of us.
We will see, I don't think R.E.R.A. have any balls, which is why these developers ignore the Dubai laws, and it would appear getting away with it.
I emailed Hamdy again today, as I have still not had a response from yesterday. I have told him that the contract I signed and the payment schedule, related to a completion date of June 2008, therefor as there was a completion delay of 30 months, then all my payment schedule dates should be put back 30 months. This still means that they would have been sitting on at least 60% of my money for over 3 years.
Obviously still no reply. The only way they will do anything, and thats if we all keep on at them.
There does not seem to be any passion on the Pinnacle forum, unlike the Torch. Maybe people have just accepted they will loose money, and are happy with it.

Audi04
March 20th, 2009, 11:39 PM
aa

Audi04
March 21st, 2009, 12:12 AM
aa

Audi04
March 21st, 2009, 12:14 AM
I sent a similar email to Hamdy expressing the same points as Pinncale1. They are sitting on over 75% of my money. I believe we should act collectively to express our issues to RERA.

I am sure you all are aware RERA has over 35 Billion worth of complaints on their hand from various projects.

icemannapoli
March 23rd, 2009, 04:39 PM
Thanks Dubai Steve

from 20th March

http://i41.tinypic.com/2cnjt4l.jpg

pinnacle1
March 25th, 2009, 06:32 PM
Has anyone heard about registering our apartments.

icemannapoli
March 26th, 2009, 12:31 PM
Thanks to Joannides

Everything is stopped....

http://i42.tinypic.com/2iqy22v.jpg

ramzy
March 26th, 2009, 12:33 PM
How did you come to that conclusion?

icemannapoli
March 26th, 2009, 05:14 PM
The floor construction have been stopped for 3-4 weeks. The cladding is going very very slow. For the interiors I can't judge, but the overall impression is not good.

aldopardo
March 27th, 2009, 09:12 PM
Does anybody have any information about when this project will finish ?

bizzybonita
March 27th, 2009, 09:45 PM
not before 2011 if not 2012 ...

Imre
April 3rd, 2009, 03:59 PM
03/April/2009

Marina Pinnacle and MAG 218

http://i42.tinypic.com/fckjl.jpg

depassage298
April 5th, 2009, 01:25 PM
This project is a disaster in term of delivery

dirtyharry1
April 5th, 2009, 02:00 PM
There is absolutely no work going on there...

Audi04
April 5th, 2009, 11:04 PM
Received an email from Hamdy stating the he will apply the contract terms to force me to pay the remaining installment. I have paid over 75% since 05 and my reply to him is, I see you in court.

I not lobbying here but we should be thinking/acting collectively as investors
because no doubt we are being f---ed in lieu of what's happening in the world economies.

pinnacle1
April 6th, 2009, 02:47 PM
Totally agree. I to have told Hamdy, they are not recieving any more money from me. I had a massive argument with him and called him a liar and his company cheats. I think it is pointless paying anymore money, as it will be just more money to loose. They have told so many lies I just don't trust them. I don't care if they take the property back and pay me my money back less the 20% stoppages as per contract. I would still be better off. I have contacted R.E.R.A. but they are totally useless and are on the construction companies sides. No one is ever going to form a group to stop these crooks, so I now think it is every man for himself.
If Tiger had not held back 400 units, thinking they were going to sell them at a higher price near completion, they would not be in this mess. It is all down to greed. If anyone thinks they are going to get compensation, they need their head testing. You will be lucky if you ever get an apartment.
If anyone who owns a property in this development, and who actually gives a shit that their money is going to be lost, please pm me. I will give an update in one week on how many people actually care.

Stephan23
April 7th, 2009, 12:43 PM
Almost 4 years are gone since the first floor was up !! Unbelievable !! Still always NOT topped out... :doh: :wallbash:

icemannapoli
April 8th, 2009, 04:11 PM
Stephan you're absolutely right!! :bash:

Even if in these pictures, taken by Desert Diver yesterday, we can note that while glasses are going very slow, the external finishings seems good, particularly in the second picture

http://www.quetschluft.de/dubai/300_3377_qa.jpg

http://www.quetschluft.de/dubai/300_3374_qa.jpg

Imre
April 9th, 2009, 01:12 PM
09/April/2009

Marina Pinnacle

http://i39.tinypic.com/rk7orb.jpg

http://i42.tinypic.com/iw0y6q.jpg

http://i41.tinypic.com/t6asgn.jpg

http://i41.tinypic.com/2qlg3dh.jpg

pinnacle1
April 9th, 2009, 02:19 PM
Excellent pictures Imre.
Almost makes you feel it might get finished one day.

H.Maleki
April 11th, 2009, 10:11 PM
Nice Imre, pictures do look fantastic, lets just hope the inside is the same

WhatIfTheWatersRise?
April 14th, 2009, 11:21 PM
President His Highness Shaikh Khalifa Bin Zayed Al Nahyan visited the Marina today. With any luck he looked up and decreed that MP be finished immediately as it is an eyesore!!:lol:

Imre
April 17th, 2009, 04:32 PM
17/April/2009

Marina Pinnacle

http://i41.tinypic.com/25s28ld.jpg

http://i44.tinypic.com/w0mlh3.jpg

pinnacle1
April 18th, 2009, 12:31 PM
Just recieved this from someone who has also been experiencing problems from Tiger with threats over non payments

According to ESCROW LAW no Developer can or could collect ay payments but through the ESCROW ACCOUNT.



To be able to collect the following payment(s) the DEVELOPER should send a copy of the Escrow latest report mentioning the percentage that he reached in his project and have the right to claim the payment as per the ESCROW report. Meaning that if you do not receive any ESCROW report the Developer can not ask you to make any payment at all.



The ESCROW law has been established to protect buyers from wrong pressures from Developers and has organize the percentage of payments which deletes automatically the Payment Schedule mentioned in our Contract Agreements.



The Project being delayed beyond the date mentioned in it will automatically be organized by ESCROW percentage.



WITHOUT ESCROW REPORT NO FUTHER PAYMENT(s). This is final and please stop asking the same question. The answer is there by the Land Department to protect us.



My advise is for you to answer Developer’s demand for next payment is to answer him that you are ready to pay provided he sends you the copy of the ESCROW report he received lately and that you will abide by the LAW and not by the Agreement’s schedule because the ESCROW LAW already deleted that schedule.

montranieri
April 18th, 2009, 12:32 PM
Today in the gulf news one bedroom on sale at 490,000 AED.
The ad say "good size apartment on the third floor" how big can it be?
Price seems really low..............

pinnacle1
April 18th, 2009, 01:01 PM
I have just seen this ad on agents website


Apartment FLocation: Marina Pinnacle - Dubai
A prominent 1 bedroom apartment of Marina Pinnacle located in Dubai Marina close to Jebel Ali Free zone, Dubai Internet and Media Cities and offers a sophisticated multi-cultural community lifestyle.Bayut ID:399808Type:ApartmentStatus:For SaleBedrooms:1Area: 749 Sq. Ft. Price: 3,333,523 AED

So it just goes to show what a load of b*****ks these agents are talking.

WhatIfTheWatersRise?
April 21st, 2009, 12:25 AM
Did many of you get the email from Tigers Marketing department outlining the apartments they are selling off. Best of luck to them at those prices. (My apartment type listed at three times what I paid!!!).
At least they have updated their website www.tigergroup.net :wtf:

pinnacle1
April 21st, 2009, 02:45 PM
Yes I got one as well, absolute bargin, I think I will buy six.
I think they have lost the plot, fancy trying to sell to existing customers, who paid a fraction of their current prices.

icemannapoli
April 21st, 2009, 05:40 PM
Pinnacle1, what do you mean when you say "they have lost the plot"? I'm warried about it...

High Times
April 21st, 2009, 05:53 PM
Yes I got one as well, absolute bargin, I think I will buy six.
I think they have lost the plot, fancy trying to sell to existing customers, who paid a fraction of their current prices.


Probably a PR excercise to make existing investors think "wow look how much my investment is worth now".

Take the heat off a bit.

pinnacle1
April 21st, 2009, 11:35 PM
No Icepoleman. Obviously they have not that plot. Mind you the amount of work that is going on, maybe they have and the workers cannot find it.

pinnacle1
April 21st, 2009, 11:36 PM
sorry I meant icemannapoli

icemannapoli
April 22nd, 2009, 10:51 AM
Looking at the work on the site, maybe you're right!! :-)

pinnacle1
April 22nd, 2009, 12:58 PM
Recieved e.mail today from Tiger, offering 1 bedroom marina facing apartment,35th floor, for the bargin price of 2,465,909

pinnacle1
April 22nd, 2009, 10:43 PM
just out of interest, has anyone had their property registered at land registry.

WhatIfTheWatersRise?
April 22nd, 2009, 11:03 PM
just out of interest, has anyone had their property registered at land registry.

No I haven't.
The marketing department seem to be the only Tiger dept working at the moment. I received an email from them today asking if I wished to purchase an apartment in a new development to be handed over in 2012. As if!!

pinnacle1
April 23rd, 2009, 05:13 PM
Is Asif, the man who tried to sell you one.:lol:

icemannapoli
April 24th, 2009, 04:12 PM
Thanks Imre

http://i42.tinypic.com/2pra83b.jpg

Imre
May 1st, 2009, 12:53 PM
01/May/2009

Marina Pinnacle

http://i41.tinypic.com/ilvkaa.jpg

http://i39.tinypic.com/2nsq240.jpg

Imre
May 15th, 2009, 02:10 PM
15/May/2009

Marina Pinnacle

http://i43.tinypic.com/2ck3m1.jpg

http://i42.tinypic.com/20pc9si.jpg

pinnacle1
May 17th, 2009, 09:37 PM
Just read interesting if not worrying article, about Dubai changing an existing law to benefit developers

Legal changes

The Dubai government has indicated that it is to make certain amendments to article 11 of property Law 13 2008, regulating the system of dealing with defaulters.

Law 9 of 2009 will serve to clarify how much developers can keep if investors default on payments. If at least 80% of the project has been completed prior to default, the investor loses all money paid to that point. The property will then be auctioned as compensation to the developer to account for the missing increments.

If at least 60% of the project has been completed prior to default, the developer is entitled to keep 40% of the original purchase price. If less than 60% has been built the developer is only entitled to keep 25% of the purchase price.
If construction has not been begun prior to default, but this is not due to 'negligence or omission on the developer's part', the developer may keep 30% of the installment money paid up to that point.


There is going to be a lot of properties up for auction. It stinks.

scoot68
May 27th, 2009, 07:39 PM
http://i42.tinypic.com/69n70p.jpg

dirtyharry1
May 28th, 2009, 09:28 AM
What is happening at the Pinnacle? Is Tiger finished finally? Bancrupt? There is nothing going on on that jobsite for months and months.

icemannapoli
May 28th, 2009, 01:09 PM
They are working very very slow....

They need to build the last 6 floors, but I think they are still thinking if do it or don't!

The problem is that many people is not paying the installments and maybe they are going to have a great number of flats empty....

Imre
May 29th, 2009, 03:46 PM
29/May/2009

Marina Pinnacle

http://i44.tinypic.com/sbndxs.jpg

http://i42.tinypic.com/2i6f2io.jpg

malec
May 29th, 2009, 06:51 PM
I would like to know, is there any work happening on this tower despite being very slow?

dirtyharry1
May 29th, 2009, 06:55 PM
I am living quite vis a vis, and whenever I am at the pool or on my balcony, there is absolutely no activity going on.

depassage298
June 3rd, 2009, 04:04 PM
What is the completion date announced by TIGER?

pinnacle1
June 3rd, 2009, 05:28 PM
Last year it was this year. this year it is next year, I think you know the next line.

AltinD
June 3rd, 2009, 06:21 PM
Some years ago they were advertising the tower as the tallest residential tower in the World, despite the title at the time was held by a recently completed way, way much taller tower that had just dethroned a Dubai tower already taller then what The Pinnacle was supposed to be. :nuts:

icemannapoli
June 4th, 2009, 07:57 PM
WOW it seems they built up one more floor!! :banana:

- 5 floors to completion...but at this speed 5 months needed...:ohno:

Thanks Machie1964

http://i39.tinypic.com/1zn4f83.jpg

Imre
June 5th, 2009, 03:00 PM
05/June/2009

Marina Pinnacle

http://i40.tinypic.com/2duys6.jpg

http://i41.tinypic.com/oup187.jpg

depassage298
June 7th, 2009, 07:54 AM
Edit.

Audi04
June 8th, 2009, 12:34 AM
nn

Imre
June 12th, 2009, 01:12 PM
12/June/2009

Marina Pinnacle

http://i41.tinypic.com/14dq7ex.jpg

Imre
June 17th, 2009, 06:01 PM
17/June/2009

Marina Pinnacle

http://i40.tinypic.com/25tgm4o.jpg

pinnacle1
June 18th, 2009, 06:46 PM
http://i40.tinypic.com/14tr8fr.jpg

view from 21st floor, one week agohttp://http://i40.tinypic.com/14tr8fr.jpg

pinnacle1
June 18th, 2009, 06:50 PM
http://http://i40.tinypic.com/ke80ig.jpg

pinnacle1
June 18th, 2009, 06:51 PM
http://i40.tinypic.com/ke80ig.jpghttp://http://i40.tinypic.com/ke80ig.jpg

pinnacle1
June 18th, 2009, 06:54 PM
http://i42.tinypic.com/ao8g41.jpg

icemannapoli
June 19th, 2009, 11:12 AM
Thanks a lot Pinnacle1...did you see the interiors? How they are coming up?
Did you see many workers on site or not?

pinnacle1
June 20th, 2009, 01:00 PM
Things are getting done but slowly.
Had meeting with three of two of the directors, usually bull, but at least it is still going forward. They are still saying Dec 2010.
Only looked at floors 16 and 21. Tilings finished, balcony doors in, lifts operational. Lot of work still to be done.
Tiger said 72% complete. Don't know where that figure came from. I guess it is just a case of waiting.
Builders on site were very helpful though, and did not mind showing us where ever.

icemannapoli
June 20th, 2009, 01:38 PM
Thanks for these info.... let's hope for the end of 2010...but all we know that it's quite impossible!!

So, if you have some picture of the enteriors, please post it to let us to judge the fittings...

Thanks

WhatIfTheWatersRise?
June 21st, 2009, 10:25 PM
Thanks for updates Pinnacle1. Worried that we haven't been given any monthly updates recently.

Imre
June 26th, 2009, 01:10 PM
26/June/2009

Marina Pinnacle

http://i42.tinypic.com/2uj1e6x.jpg

http://i41.tinypic.com/lzj0o.jpg

ramzy
June 28th, 2009, 03:50 PM
Would anyone know what the area size of the blacony would be on an T10 (747 sq/ft) apartment?

pinnacle1
June 28th, 2009, 04:09 PM
I have got t10, when we were there 2 weeks ago, we stood on our 21st balcony. Good size, roughly 10ft x 4ft maybe slightly bigger, views at the moment, really good. marina and sea. Tiger advertise our apartments as 1061 sq ft not 747.

ramzy
June 28th, 2009, 07:33 PM
We're on the 12th floor. Looks like fab sea and marina views. Was the torch blocking views to the marina?

pinnacle1
June 29th, 2009, 12:02 PM
What you see in my photos, is the actual view you would get if you were sitting on your balcony.

ramzy
June 30th, 2009, 09:08 AM
Awsome. Clear views to the sea. The marina view looks fab for the next few years at least. Thanks.

icemannapoli
July 2nd, 2009, 03:35 PM
Hi all,

anybody has some picture of interior fittings?

I'm still curious to see the quality.

Imre
July 2nd, 2009, 09:50 PM
02/July/2009

Marina Pinnacle

http://i40.tinypic.com/f3xoc4.jpg

http://i43.tinypic.com/2utlpap.jpg

http://i40.tinypic.com/jgqxk9.jpg

icemannapoli
July 3rd, 2009, 12:02 PM
Thanks IMRE for these pictures!!

the problem is....just 2-3 people on site!! :ohno:

Imre
July 10th, 2009, 02:40 PM
10/July/2009

Marina Pinnacle

http://i26.tinypic.com/28bu1xt.jpg

ramzy
July 11th, 2009, 02:59 AM
Thanks for the pic Imre.

If you compare this last photo with that of the 26/June you can see a difference. The balconies are White. Is this cladding?

Imre
July 11th, 2009, 08:33 AM
yes, the white panels cladding has begun there.