View Full Version : MAGTAA | Desalination Plant | 500 000 m3/d Reverse Osmosis | Under construction (2008-2012)
LYES January 9th, 2011, 09:51 AM Tahlyat Myah Magtaa - Magtaa Desalination Plant
Location : Magtaa, Oran
Owner : Tahlyat Myah Magtaa (25 years concession)
Shareholders : Hyflux - Singapore - 51.00 % Algerian Energy Company AEC - Algeria - 49.00 %
Project Value : USD 632,000,000
Capacity : 500,000 cu.m./d
In October 2008, construction works started. The project is expected to be completed in Q3 2011.
In July 2008, the EPC, Operation & Maintenance (O&M) contracts, and the Water Sale & Purchase Agreement were all signed by Hyflux.
In March 2008, the BOO contract was awarded to Hyflux.
http://hyflux.infinitesparks.com/new/images/Magtaa-plant.jpg
Upon completion in 2011, Magtaa will be the largest reverse osmosis seawater desalination plant in the world
Video (http://release.theplatform.com/content.select?pid=Lz0JKsTQldHEoRN6QIaa77XhqEOvxUi7&UserName=cmsguest@cnbc.com&key=42XU%2FFshHV5znEu0wNU90Yy7tc0%3D&reporting=part=) of Hyflux spokesman speaking about the project.
gms January 9th, 2011, 04:37 PM Si quelqu'un pouvait nous prendre des photos
LYES January 10th, 2011, 01:13 AM ^^ Oui ça serait super, y a rien sur le net.
espanoldz January 10th, 2011, 01:41 AM Il ne faut pas chercher Magtaa sinon Macta ou Mactaa
J'ai trouvé cette page de l'Algérienne Des Eaux qui parle de tous les projets de stations de dessalement dont le projet de Mactaa prévu pour le deuxième semestre 2008
http://www.ade.dz/Dessalement/dessal.php
espanoldz January 10th, 2011, 02:25 AM La station de Mactaa, la plus grande au monde
Mis à part ces ouvrages, le reste des stations qui devaient être opérationnelles en 2010, selon les prévisions annoncées par les responsables en charge de ce secteur, sont encore en chantier. Il s'agit de celle de Souk Tleta à Tlemcen d'une capacité de 200 000 m3/jour, qui est en réalisation par la société AA, les travaux se poursuivent. Celle de Honaine qui est en train d'être réalisée par l'entreprise MBH pour la même capacité. Les travaux de la station de Mostaganem d'une capacité de 200 000 m3/jour est aussi en réalisation par STMM. A Tipasa, la station de Fouka d'une capacité de 120 000 m3/jour confiée à MT est en voie de réalisation au même titre que celle de Cap Djinet dans la wilaya de Boumerdès, d'une capacité de 100 000 m3/ jour confiée à la société SMD.
Idem pour la station de dessalement de Tenes à Chlef pour un volume de 200 000 m3/jour. Celle de Mactaa près de Mers El Hadjadj à Oran mérite qu'on s'y attarde car elle est d'une capacité de 500 000 m3 par jour. Confiée à la société MTM, cette usine de dessalement est considérée comme étant l'une des plus grandes au monde. Ce qui a suscité l'intérêt et l'engouement d'investisseurs étrangers nombreux à avoir présenté leurs offres techniques en 2007. Sur une superficie de 18 hectares, cet ouvrage permettra l'alimentation en eau des populations. Pour le reste des stations, les travaux ne sont pas encore entamés. C'est le cas de celle d'Ec Chatt à El Tarf de
source: http://fr.allafrica.com/stories/201012270685.html
LYES January 10th, 2011, 01:29 PM Il ne faut pas chercher Magtaa sinon Macta ou Mactaa
J'ai trouvé cette page de l'Algérienne Des Eaux qui parle de tous les projets de stations de dessalement dont le projet de Mactaa prévu pour le deuxième semestre 2008
http://www.ade.dz/Dessalement/dessal.php
Merci espanoldz, j'ai essayé toutes les combinaisons mais pour l'instant rien, pour ce qui est des données de l'Algérienne des eaux c'est déjà intégrées dans ce thread (http://www.skyscrapercity.com/showthread.php?goto=newpost&t=1295765), ne t'inquiète pas je ne lâche pas l'affaire :lol:.
espanoldz January 11th, 2011, 06:29 AM Project Summary
Project Name: AEC - Magtaa Desalination Plant
Name of Client: AEC - Algerian Energy Company
Budget ($ US): 443,000,000
Main Contractor: Hyflux Ltd
Facility Type: Reverse Osmosis Desalination (RO)
Status: Construction
PMC: Not yet appointed
Location: Oran
Last Updated: 2009-07-08 09:50:55
Project Status
Algerian Energy Company(AEC) plans to construct a 500,000 cu.mpd reverse osmosis desalination plant in Magtaa, near Oran (450 km west Algiers).
This project is part of AEC's five year development program that aims to supply 2.3 million cu.mpd of desalinated water.
As of early 2008,The Following companies have bidded for the Build Own Operate(BOO) contract:-
Acciona Agua
Biwater
Hyflux
JV of Arcofina and Toray
JV of Befesa and Sadyt
JV of GE and Orascom Construction Industries
JV of Inima and Aqualia
As of March 2008, the BOO contract was awarded to Hyflux.
As of July 2008, the EPC, Operation & Maintenance (O&M), and the Water Sale & Purchase Agreement were all signed by Hyflux.
As of 4Q of 2008,Hylux has started construction and The heart of the project, namely the filtration process, will utilise Hyflux’s award-winning proprietary Kristal ultrafiltration membranes, making it the world’s single largest ultrafiltration desalination plant.
As of December 16, 2008, Mr. President of the Abdelaziz Bouteflika Republic carried out the installation of the first stone for the realization of the project of desalination of sea water of Magtaa of a capacity of 500.000 m3/jour, the site of Magtaa which situ at Mars El Hadjadj in Wilaya d' Oran. The Investisseurs part of this project is made up of Algerian Energy Company and the Singaporean partner Hyflux. Mr. President was accompanied in particular by Mister the Minister by Energy and the Mines Doctor Chakib KHELLIL like Mister the Minister by the water resources Abdelmalek SELLAL.
A presentation of the project was made with Its Excellence Mr. President of the Republic. Thereafter, Its excellence carried out the installation of the first stone for the realization of this factory which will be born in the first half of 2011 and which will produce 500 Million liter of water de-salted per day and which will cost in the 35 Algerian Dinars for m3. With noted that this project is assembled in project Financing and technology used is Opposite Osmosis and who is more the great project of desalination d' sea water in the world in Opposite Osmosis.Construction of the plant will commence and is scheduled to be completed in 28 months time. In addition, the project company, Tahlyat Myah Magtaa SpA, has executed the financing agreement with the Banque Nationale Algeria and is now in the process of satisfying various conditions stipulated under the agreement.
As of late June 2009,Hyflux has awarded ABB Ltd a contract worth $28 million for a turnkey electrical solution to power the world's largest membrane based reverse osmosis seawater desalination plant.
ABB will be responsible for the design, engineering, supply, installation and commissioning of the electrical plant system.
The project is scheduled for completion by 2011.
Project Scope
The project work includes Construction of a 500,000 cu.mpd reverse osmosis desalination plant.
As part of the contract, ABB will set up a 220kV outdoor substation to provide power to the facility and also supply products such as power transformers, medium-voltage drives and a range of medium and low-voltage switchgea.Besides powering the water treatment facility, ABB technologies will help to enhance plant performance by addressing critical operational needs such as minimizing down time and optimizing energy consumption to improve efficiency.
Project Structure
The Client is Tahlyat Myah Magtaa,which is a consortium of
Algerian Energy Company- 49%
Hyflux - 51%
The project will be financied 70 percent by state-owned Algerian Banks, with the Banque Nationale d'Algérie leading the group. The remaining 30 percent will be provided by Hyflux.
As of late 2008, Hyflux Limited (“Hyflux”) financial close is in accordance with the terms of the non-recourse project financing facility agreement executed with Banque Nationale d’Algerie ("BNA") has been completed today.
BNA, the sole lender for the non-recourse project financing facility will make available a loan of approximately USD350 million to the Project company, Tahlyat Myah Magtaa SpA ("TMM"). The debt to equity ratio is 70:30.
All the conditions precedents under the non-recourse project financing facility agreement, including the issue of advance payment and performance bonds to the value of approximately USD146 million, have been satisfied. The mandated lead arrangers for this approximately USD146 million syndicated facility are BNP Paribas, Arab Banking Corporation and Calyon.
TMM will now proceed to drawdown in accordance with the terms of the non-recourse project financing facility with BNA.
The developer of the Project with an approximate value of USD468 million, is TMM; a joint venture company between Hyflux’s wholly owned subsidiary, MenaSpring Utility (S) Pte Limited (MenaSpring) and Algerian Energy Company (AEC).
Wholly owned subsidiaries of Hyflux will be responsible for completing the Engineering, Procurement and Construction (EPC) works for the Project at a total value of approximately USD443 million. The EPC works include the design, install, erect, build, complete, test and commission of the Project, and is expected to be completed within 28 months’ time. Hyflux’s award winning Kristal ultra filtration membranes will be used in the Project.
Upon completion of construction, the Operations and Maintenance (O&M) work for the Project will be undertaken by Hyflux’s wholly owned subsidiary, Hyflux Operation & Maintenance Algérie, for a term of 25 years. The O&M fees will contribute towards the long term recurring income of Hyflux. Following financial close, MenaSpring will divest 4% of its shareholding in TMM to AEC, who will at the same time divest 10% of its shareholding to the Algerian state-owned national public water entity, L’Algerienne Des Eaux (ADE). As a result, MenaSpring will hold 47% of the issued shares in TMM, while AEC and ADE shall become the remaining 43% and 10% shareholders in TMM respectively.
http://www.cceec.com.cn/English/Project/2010/0906/8034.html
LYES January 13th, 2011, 09:58 PM HyFlux building biggest desalination water plant in Algeria
THAP-xXasWU
gms January 15th, 2011, 10:37 AM HyFlux building biggest desalination water plant in Algeria
THAP-xXasWU
So, Magtaa is a small village in the middle of nowhere and the nearest city is 3 hours by raod?????
LYES January 15th, 2011, 01:24 PM They are exaggerating you know to show how the work conditions are tough, for them if you don't work in a big with many bars an entertainement places it's a sacrifice, in this kind of seminaries they always trying to motivate workers by showing that it's possible to work everywhere without using suicide :lol:
espanoldz January 15th, 2011, 06:26 PM Oran est a une demie heure, Mostaganem a une demi heure et Arzew a un quart d'heure!!
J'ai cru entendre "the nearest town is at 3 houres drivin' away on a bad road"!!
The bad road c'est celle-la et elle est magnifique
http://farm6.static.flickr.com/5084/5338328457_bba2ce3d61_b.jpg
On ne motive pas les gens en disant des mensonges !!!
LYES January 15th, 2011, 07:06 PM Oran est a une demie heure, Mostaganem a une demi heure et Arzew a un quart d'heure!!
J'ai cru entendre "the nearest town is at 3 houres drivin' away on a bad road"!!
The bad road c'est celle-la et elle est magnifique
http://farm6.static.flickr.com/5084/5338328457_bba2ce3d61_b.jpg
On ne motive pas les gens en disant des mensonges !!!
C'est notre faute espanoldz, on ne communique pas sur les projet et on autorise les compagnies étrangère à tout ramené de chez eux.
J'ai des statistiques d'une compagnie espagnole (Abengoa, tu connais je pense) qui annonce un taux d'intégration locale (main d'œuvre, sous traitance et matériels et matériaux de construction) pour l'Algérie de 3%, alors que le plus bas (au Pérou) est de 56%( si mes souvenirs sont bons) alors c'est pour ça qu'ils essayent de mentir pour motiver leurs travailleurs, tant qu'on aura des gens qui font des courbette devant les étrangers pour avoir des avantages et méprisent les compétences locales tout le monde pourra s'essuyer sur nous comme ils veulent et même avec notre argent.
Mais cette incident n'est pas le pire à mon avis j'ai travailler avec d'autres et c'est pire l'image qu'ils ont de l'Algérie (parfois même sans la connaitre).
LYES January 15th, 2011, 07:09 PM Dans les champs pétrolier on autorise même des marché de catering pour des compagnie étrangère:bash:, c'est hallucinant, ils ramène même la nourriture par avion, et après on nous dis pas d'argent pour le travail dsl :bash::bash::bash::bash:.
LYES January 15th, 2011, 07:13 PM En voici la preuve, je voulais pas en parler avant pour éviter la polémique inutile :
La Base de Vie (2009)
http://farm3.static.flickr.com/2777/4030227802_5d74dc7f35_b.jpg
C'est à Menzel Ledjet Est : almafrique est compagnie de catering italienne.
BAKU-ORAN January 23rd, 2011, 12:26 PM http://commondatastorage.googleapis.com/static.panoramio.com/photos/original/46965863.jpg
Photo of project , 03 months ago , was in my archive files...
soyous_2040 January 23rd, 2011, 01:07 PM Bonjour baku-oran bienvenue chez toi merci pour la foto voici le lien pour te presenter nous sommes en manque de reporters à oran
ICI (http://www.skyscrapercity.com/showthread.php?t=799504&page=30)
LYES January 23rd, 2011, 01:27 PM Merci à Baku-Oran pour cette photo, thanks a lot :)
http://commondatastorage.googleapis.com/static.panoramio.com/photos/large/46965863.jpg
And welcome, you live in Baku or Oran?
Sandervalya February 1st, 2011, 02:22 AM La Mactaâ est une vaste région de marais déséchés, totalement désolée entre la la wilaya d'Oran et celle de Mostaganem mais qui se trouve geographiquement faire partie de la wilaya de Mascara.
espanoldz February 1st, 2011, 03:04 AM J'espere que ça n'affectera pas la belle plage de Sidi Mansour qui est juste a coté!!
soyous_2040 February 1st, 2011, 04:16 PM J'espere que ça n'affectera pas la belle plage de Sidi Mansour qui est juste a coté!!
une tres belle plage ou jai passé de bons moments
LYES May 12th, 2011, 07:37 AM Powering Magtaa desalination plant*
ABB solutions are making a significant contribution to the world's largest seawater desalination plant – Magtaa in Algeria – and to the award–winning Changi Water Reclamation Plant in Singapore.
Magtaa, which is scheduled for completion in 2011, will use seawater reverse osmosis to produce up to 500,000 cubic meters of drinking water a day, sufficient to meet the daily requirements of about five million people. ABB is providing a complete electrical solution for the entire desalination plant, including a 220kV outdoor substation to connect the facility to the Algerian power grid and ensure it receives a reliable supply of electricity.
http://www.waterworld.com/etc/medialib/platform-7/Water___WasteWater_International/Print_Articles_/volume-25/issue-2.Par.69236.Image.600.320.1.gif
The solution includes 33 ABB medium–voltage drives, which will not only reduce pump energy consumption and plant power losses down to a uniquely low level but also reduce mechanical stress on the pumps and electrical stress on the motors....
Source : WaterWorld (http://www.waterworld.com/index/display/article-display/2542820123/articles/water-wastewater-international/volume-25/issue-2/regulars/show-preview__singapore/powering-singapore.html)
* titre modifié ;).
gms May 12th, 2011, 02:30 PM Je ne sais pas s'il y a un thread dédiée au projet de station de dessalement d'eau de mer de Mostaghanem, ce projet avance bien et la phase de test à démarré
abdeka May 12th, 2011, 02:33 PM Je ne sais pas s'il y a un thread dédiée au projet de station de dessalement d'eau de mer de Mostaghanem, ce projet avance bien et la phase de test à démarré
Ici : http://www.skyscrapercity.com/showthread.php?t=895700&highlight=mostaganem
LYES August 9th, 2011, 07:35 AM Warehouse fire delays Magtaa desalination by nine months
Posted on 07 August 2011
Completion of the 500,000 m³/d Magtaa desalination plant in western Algeria will be delayed by nine months after a fire destroyed the contractor's onsite warehouse on 28 July 2011.
Cho Wee Peng, group chief financial officer for Hyflux of Singapore, announced the same day that, while all buildings and equipment at the construction site were unaffected by the fire, the warehouse, sited a few hundred metres away, housed equipment which was to be used for the project.
According to preliminary estimates, related costs and estimates arising from the fire are around US$ 50 million. The company is working with its insurers to investigate the cause of the fire and to make claims accordingly.
As a result of this incident, all damaged equipment and other supplies will have to be reprocured. The project completion is expected to be delayed till May 2012 instead of this month.
Source : desalination.biz (http://www.desalination.biz/news/news_story.asp?id=6053&channel=0&title=Warehouse+fire+delays+Magtaa+desalination+by+nine+months)
GravityFree August 9th, 2011, 01:02 PM Warehouse fire delays Magtaa desalination by nine months
Posted on 07 August 2011
Source : desalination.biz (http://www.desalination.biz/news/news_story.asp?id=6053&channel=0&title=Warehouse+fire+delays+Magtaa+desalination+by+nine+months)
LOL that's funny, just one month before delivery we announce a big fire in the warehouse and we get 9 months added to deadline WOW
Usually at one month from delivery it's just finishing, the warehouse of any project should be almost empty, not worthing US$ 50 million!!!!...so tricky
bidonv August 9th, 2011, 01:16 PM LOL that's funny, just one month before delivery we announce a big fire in the warehouse and we get 9 months added to deadline WOW
Usually at one month from delivery it's just finishing, the warehouse of any project should be almost empty, not worthing US$ 50 million!!!!...so tricky
Elle est louche cette affaire!!!:ohno:
tomorrowZZbetter August 9th, 2011, 11:56 PM Warehouse fire delays Magtaa desalination by nine months
Posted on 07 August 2011
Source : desalination.biz (http://www.desalination.biz/news/news_story.asp?id=6053&channel=0&title=Warehouse+fire+delays+Magtaa+desalination+by+nine+months)
complot:lol:
bien SURE!!!ce n'est pas le moment d'annocer que l'Algerie inaugure une des plus grandes station RODP au monde....en Algerie y a juste des problèmes.Hassi Rmel hybride plant BIS
Ça serait très intéressant de suivre les annonce dans ce domaine durant les 9 mois
bidonv August 10th, 2011, 12:14 AM complot:lol:
ce n'est pas le moment d'annocer que l'Algerie inaugure une des plus grandes station RODP au monde....en Algerie y a juste des problemes.
YA JMA3a lebled est COMPLETEMENT INFILITRÉE :bash:
Non peut-être une tentative pour échapper aux pénalités de retard?:lol:
tomorrowZZbetter August 10th, 2011, 12:23 AM Non peut-être une tentative pour échapper aux pénalités de retard?:lol:
ça peut etre ça aussi...
bledi October 16th, 2011, 06:26 PM La plus grande usine de dessalement du monde
Le singapourien Hyflux usine de dessalement à Magtaa pour 468 millions
La société Algerian Energy Company (AEC) a confié au groupe Hyflux de Singapour un contrat d'un montant de 468 millions de dollars pour la réalisation d'une unité de dessalement d'eau de mer à Magtaa (ouest de l'Algérie), d'une capacité de 500.000 m3/jour.
L'usine de Magtaa sera financée à hauteur de 30% sur fonds propres du groupe Hyflux, les 70% restants étant assurés par des banques publiques algériennes avec pour chef de file la Banque nationale d'Algérie (BNA).
il s'agit du projet de dessalement "le plus important au monde", qui doit entrer en service en fin 2011 et couvrir les besoins en eau de prés de cinq millions d'habitants.
http://img811.imageshack.us/img811/4089/scrypercity19.jpg
http://http://img692.imageshack.us/img692/5127/scrypercity20x.jpg
http://http://img849.imageshack.us/img849/2083/scrypercity21.jpg
soyous_2040 October 16th, 2011, 07:19 PM Je crois qu'il y'a un thread la dessus merci quand méme bledi
gms July 23rd, 2012, 07:47 PM L'eau dessalée d'El Mactaâ à la fin de l'année
La méga-station de dessalement d'eau de mer d'El Mactâa, commune de Mers El Hadjadj, entrera en exploitation, à la fin de l'année en cours, selon des sources de la direction de l'Hydraulique. Cette station, l'une des plus importantes à l'échelle nationale, d'une capacité de 550.000 m³/jour, alimentera la ville d'Oran avec 255.000 m³/jour, alors que le reste sera dirigé pour l'alimentation d'autres wilayas notamment Mascara, Relizane et Mostaganem.
Les travaux de cet ouvrage confiés à l'entreprise «Hyflux» de Singapour, avancent. Les travaux de raccordement de la station aux réservoirs de stockage devant alimenter un nombre de communes du sud de la wilaya d'Oran, seront achevés incessamment. L'entrée en exploitation de cette méga-station permettra de renforcer le secteur. Puisque même avant l'entrée en service de cette station l'approvisionnement de la wilaya d'Oran était jugé satisfaisant.
Le cauchemar des longues attentes de l'arrivée du liquide précieux dans les robinets n'est qu'un lointain souvenir. Pour sécuriser la wilaya d'Oran en eau potable, l'Etat a mené plusieurs actions. Le directeur de l'Hydraulique de la wilaya d'Oran a affirmé, auparavant, que la wilaya d'Oran ne souffre pas du problème du manque d'eau, mais dans la distribution. «Les ressources en eau sont disponibles en abondance, cependant le problème de sa distribution pour répondre aux besoins de toute la population oranaise, répartie sur 26 communes, se pose toujours», a-t-il souligné.
Pour remédier à cette situation un grand projet de réalisation de canalisations de raccordement des réservoirs nouvellement réalisés dans plusieurs communes tel celui de Belgaïd, au réseau de distribution d'eau potable est en cours de réalisation, rappelle-t-on.
Destinée à l'alimentation en AEP, sur une distance globale dépassant les 115 km, la conduite a atteint un taux d'avancement très appréciable. Cette opération ciblera le raccordement de ces réservoirs à d'autres plus petits réalisés récemment, à l'image de celui de Kristel dont la capacité de stockage est estimée à environ 10.000 m³ et de 2 autres de la localité d'Ain Beida d'une capacité de 50.000 m³ chacun.
D'autres réservoirs seront réalisés prochainement dans plusieurs communes qui en sont dépourvues, à l'instar de Misserghine. Ces réservoirs permettront d'approvisionner la population et assurer une autosuffisance durant quelques jours, en cas de panne technique ou d'un éventuel problème.
source : Q-O
karim2096 August 19th, 2012, 08:05 PM world's largest seawater desalination plant – Magtaa in Algeria
a 2014
Saudis Open World’s Largest De-Salination Plant 800000cubic meters
karim2096 September 7th, 2012, 01:47 PM تعتبر من بين المحطات الثلاث الكبرى عالميا
''هيفلوكس'' تجهّز محطة المقطع بوهران لتزويد المنطقة الغربية بالمياه
ستستفيد المناطق الغربية الجزائرية من إمدادات تقدر بـ500 ألف متر مكعب يوميا من المياه، بفضل أكبر محطة تحلية مياه البحر بمنطقة المقطع قرب وهران، المشروع الذي فازت بإنجازه الشركة السنغافورية ''هيفلوكس''، تمتلك هذه الأخيرة فيه نسبة الأغلبية بـ51 بالمائة مقابل 49 بالمائة للشركة الجزائرية للطاقة.
يسمح المشروع، الذي شرع في إنجازه بعد فوز الشركة السنغافورية بالعقد في 2008 بقيمة بلغت حوالي 468 مليون دولار، بضمان جزء كبير من الموارد المائية في منطقة عانت لفترة زمنية طويلة من شح المياه، ولكن أيضا يعكس توجها جديدا للسلطات العمومية مع امتلاك شركة أجنبية خاصة لنسبة الأغلبية ولحق التسيير في مشاريع هيكلية في قطاع الموارد المائية، إذ يمكن لمثل هذا المشروع أن يضمن تزويد حوالي 5 ملايين شخص في المنطقة الغربية بمعدل 100 لتر يوميا من المياه.
وبرمج تشغيل المشروع في 2011 ولكنه عرف تأخرا، ويضمن الشريك الأجنبي تمويل جزء من المشروع في حدود 30 بالمائة بموارده الخاصة، مقابل تمويل مركب بنكي جزائري. وتعتبر محطة المقطع قرب وهران من بين أكبر المحطات الثلاث في العالم، والأهم التي تشرف عليها الشركة، حيث تفوق بكثير محطة ''تواسبرينغ'' بسنغافورة التي تصل قدرتها الإنتاجية إلى 500.318 متر مكعب يوميا، كما يعتبر السوق الجزائري الأهم بالنسبة للمجموعة، إذ تصل قدرة إنتاج الشركة من خلال محطتي المقطع وسوق الثلاثاء بتلمسان إلى 700 ألف متر مكعب يوميا.
وقدّر المتر المربع للماء المنتج من قبل المحطة بحوالي 34 دينارا في المرحلة الأولى، وهو مستوى أقل من ذلك المسجل في محطات أخرى على غرار بني صاف بعين تموشنت وسكيكدة التي تصل قدرة إنتاجها إلى 200 ألف متر مكعب يوميا، وهو نفس مستوى إنتاج محطتي حنين وسوق الثلاثاء بولاية تلمسان ومحطة مستغانم. وتستفيد الجزائر من خلال مشروعي المقطع وتلمسان من الخبرة والتكنولوجيا التي اكتسبتها المجموعة السنغافورية ''هيفلوكس'' المصنفة ضمن أهم الشركات العشر العالمية في مجال تخصصها، بعد أن أسستها في 1989 أوليفيا لوم، وتجاوز رقم أعمال الشركة حاليا 460 مليون دولار، مع تشغيل 2300 عامل ومهندس.
على صعيد آخر، كشفت الشركة السنغافورية عن حصول محطة تحلية مياه البحر بسوق الثلاثاء بتلمسان على شهادة تقدير دولية في إطار الجائزة الدولية للمياه الشاملة لسنة 2012 التي تقدمها الهيئة الدولية للاستعلامات الشاملة حول المياه، وتمثل المحطة التي دخلت الخدمة في 2011 الأولى التي تشغلها المجموعة السنغافورية في الجزائر بتكنولوجية مستحدثة، وتم منح الشهادة التقديرية الدولية للمحطة الجزائرية كأفضل تسيير هندسي دولي. ضمن عدد من المحطات التي ترشحت أيضا
http://www.elkhabar.com/ar/economie/301454.html
bledi September 7th, 2012, 05:54 PM http://img15.imageshack.us/img15/795/img3499gr.jpg
http://img21.imageshack.us/img21/5276/img3500nu.jpg
http://img528.imageshack.us/img528/4038/img3501w.jpg
http://img641.imageshack.us/img641/8586/img3502cm.jpg
http://img534.imageshack.us/img534/2125/img3503zt.jpg
http://img546.imageshack.us/img546/8218/img3504ec.jpg
http://img651.imageshack.us/img651/6479/img3506n.jpg
bon je remarque que le forum est mort participer un peu meme avec des photos de vos vacances tout le monde sera content
gms October 29th, 2012, 08:32 PM Phase des essais à la station de dessalement d’eau de mer de Mers El Hadjadj (Oran)
ORAN - Le mégaprojet de dessalement d’eau de mer de Mers El Hadjadj (Oran) est entré en phase des essais, a-t-on appris lundi du directeur de l’hydraulique de la wilaya.
"Il s’agit des essais des équipements et de la performance de la station", a indiqué Djelloul Tarchoune, qui a annoncé que la mise en exploitation de ce mégaprojet, d’une capacité de 500.000 mètres cubes/jour, est prévue pour le début de l’année 2013.
La wilaya d’Oran qui reçoit actuellement un volume de 360.000 m3 d’eau potable, couvre 99,3 % des besoins de la population en H 24, a souligné le même responsable.
Des zones éparses, dont notamment celles de Tafraoui et de Sidi Ghanem, seront bientôt raccordées au réseau d’AEP, a-t-il ajouté, indiquant que d’importantes ressources sont mobilisées pour satisfaire les besoins des populations de la wilaya en eau potable.
"Si de grands efforts ont été effectués au niveau de la wilaya pour alimenter au quotidien la population en eau potable, beaucoup reste à faire en matière d’assainissement et de protection des zones inondables pour en finir avec les points noirs qui sont apparus avec les pluies intenses qui se sont abattues ces dernières 48 heures", a-t-il souligné d’autre part.
Il a évoqué, dans ce sens, la programmation de plusieurs opérations dont celles ayant trait à la protection des centres urbains de Misserghine et de Sidi Benyebka contre les inondations, la réalisation d’un bassin de rétention au niveau de la RN 11, un point noir situé sur la voie express Oran-Arzew, le traitement de la zone de dépression de Sidi Chahmi et de Oued Ras El Aïn qui accueille les eaux pluviales du bassin versant du mont Murdjadjo jusqu’à Sidi El Houari.
A propos de l’endiguement d’Oued Tlélat, le directeur de l’hydraulique a indiqué que la moitié de son tracé en béton nécessite l’inscription d’une opération d’un coût de 650 millions de dinars.
Concernant l’opération de réhabilitation des ovoïdes en cours, il a signalé, à titre indicatif, que quatre (4) kilomètres seront réalisés en 2013.
Au sujet du projet de raccordement de haï Nedjma (ex Chteïbo) au réseau d’assainissement, il a fait remarquer qu’il ne reste que le branchement des pénétrantes, rappelant que 7.000 fosses septiques ont été éradiquées en 2011 et 17.000 le seront en 2012, sur un total de 28.000.
Source : APS (http://www.aps.dz/Phase-des-essais-a-la-station-de.html)
karim2096 March 24th, 2013, 01:11 AM van_DzrgjxU
|
|