About Project:

Like minded enthusiastic Telugu Film Producers who are members in Telugu Film Producer’s Council, felt to have residential flats of their own – thus came out the dream of having a flat in Towers on the name of MOVIETOWERS emerged.

No of Floors: 20

Height: ?

No. of Blocks: 4

Project Website: http://www.movietowers.com/index.html

Renders:

http://www.movietowers.com/images/banner1.jpg

http://www.movietowers.com/images/banner2.jpg

http://www.movietowers.com/images/banner3.jpg

kailash9999
May 31st, 2012, 01:29 AM
Construction Updates:

http://www.movietowers.com/gallery.html

http://www.movietowers.com/images/progress/apr12_01.jpg
BLOCK-B: 9th FLOOR SLAB CONCRETING COMPLETED ON 19th APRIL 2012

http://www.movietowers.com/images/progress/apr12_02.jpg
BLOCK-B: COLUMN CONCRETING FOR 10th FLOOR SLAB IN PROGRESS

http://www.movietowers.com/images/progress/apr12_03.jpg
BLOCK-C: 8th FLOOR SLAB CONCRETING COMPLETED ON 26th APRIL 2012

http://www.movietowers.com/images/progress/apr12_04.jpg
BLOCK-C: COLUMN CONCRETING IN PROGRESS FOR 9th FLOOR SLAB

http://www.movietowers.com/images/progress/apr12_05.jpg
BLOCK-A: 5th FLOOR SLAB CONCRETING COMPLETED ON 11th APRIL 2012

http://www.movietowers.com/images/progress/apr12_06.jpg
BLOCK-A: 6th FLOOR SLAB SHUTTERING & REINFORCEMENT WORK IN PROGRESS

http://www.movietowers.com/images/progress/apr12_07.jpg
BLOCK-D: 3rd FLOOR SLAB CONCRETING COMPLETED ON 12th APRIL 2012

http://www.movietowers.com/images/progress/apr12_08.jpg
BLOCK-D: 4th FLOOR SLAB SHUTTERING & REINFORCEMENT WORK IN PROGRESS

http://www.movietowers.com/images/progress/apr12_09.jpg
IN B/W BLOCK A&B: CONCRETING FOR CELLAR SLAB COMPLETED ON 30th APRIL 2012

http://www.movietowers.com/images/progress/apr12_10.jpg
IN B/W BLOCK C&D: SHUTTERING FOR SUB-CELLAR SLAB IN PROGRESS

http://www.movietowers.com/images/progress/apr12_11.jpg
BLOCK-B: BLOCK WORK COMPLETED UP TO 3rd FLOOR , WORK IN PROGRESS AT 4th, 5th & 6th FLOOR

http://www.movietowers.com/images/progress/apr12_12.jpg
BLOCK-C: BLOCK WORK COMPLETED AT GROUND & 1st FLOOR, WORK IN PROGRESS AT 2nd & 3rd FLOOR

http://www.movietowers.com/images/progress/apr12_13.jpg
BLOCK-A: BLOCK WORK COMPLETED AT GROUND FLOOR, WORK IN PROGRESS AT 1st & 2nd FLOOR

http://www.movietowers.com/images/progress/apr12_14.jpg
BLOCK-D: BLOCK WORK IN PROGRESS AT GROUND & 1st FLOOR

sriece19
May 31st, 2012, 03:49 AM
This is the best example to say that so many state or art projects are to be constructed across ORR. This is one of the feathers to cap!

Location Map: http://maps.google.com/maps/ms?msa=0&msid=218039384972901815051.0004b85cb8e023cb7a983&ie=UTF8&ll=17.419688,78.333549&spn=0.052576,0.130892&t=m&z=14&vpsrc=6&iwloc=0004b85cbc769a0df9551

World8115
May 31st, 2012, 09:21 AM
Thank you for updates Kailash :cheers:

rockystone
September 21st, 2012, 05:29 PM
BLOCK-C : 13th FLOOR SLAB CONCRETING COMPLETED ON 15th Aug 2012

http://imageshack.us/a/img705/5954/blockcz.jpg (http://imageshack.us/photo/my-images/705/blockcz.jpg/)

rockystone
September 21st, 2012, 05:31 PM
BLOCK-B: 15th FLOOR SLAB CONCRETING COMPLETED ON 24th Aug 2012

http://imageshack.us/a/img822/1460/blockbs.jpg (http://imageshack.us/photo/my-images/822/blockbs.jpg/)

rockystone
September 21st, 2012, 05:32 PM
BLOCK-D: 9th FLOOR SLAB CONCRETING COMPLETED ON 22nd Aug 2012

http://imageshack.us/a/img15/7126/blockd.jpg (http://imageshack.us/photo/my-images/15/blockd.jpg/)

rockystone
September 21st, 2012, 05:34 PM
BLOCK-A: 11th FLOOR SLAB CONCRETING COMPLETED ON 17th Aug 2012

http://imageshack.us/a/img821/5328/blockaw.jpg (http://imageshack.us/photo/my-images/821/blockaw.jpg/)

ranga
September 22nd, 2012, 11:51 AM
This is the best example to say that so many state or art projects are to be constructed across ORR. This is one of the feathers to cap!

Location Map: http://maps.google.com/maps/ms?msa=0&msid=218039384972901815051.0004b85cb8e023cb7a983&ie=UTF8&ll=17.419688,78.333549&spn=0.052576,0.130892&t=m&z=14&vpsrc=6&iwloc=0004b85cbc769a0df9551

Notwithstanding feather on the cap pride can anyone tell the vacancy levels in these towers.It should not be resulting in "TOWERS ARE PLENTY BUT BOOKINGS ARE SCANTY":)

kailash9999
September 22nd, 2012, 12:36 PM
Notwithstanding feather on the cap pride can anyone tell the vacancy levels in these towers.It should not be resulting in "TOWERS ARE PLENTY BUT BOOKINGS ARE SCANTY":)

This project is meant for the movie fraternity it self and not saleable to the general public. So obviously you can asses the vacancy level of these towers.

RENextGen
September 22nd, 2012, 06:46 PM
This project is meant for the movie fraternity it self and not saleable to the general public. So obviously you can asses the vacancy level of these towers.

Do you know of any resales happening?

kailash9999
September 22nd, 2012, 07:02 PM
Do you know of any resales happening?

Hello there, I have no clue about it, but you could contact their office for more info;

Movie Towers
Film Nagar Co-operative Housing Society Complex
Dr. D. Ramanaidu Building Complex, 1st Floor
Film Nagar,Jubilee Hills
Hyderabad - 500096
eMail : movietowers@gmail.com
Phone & Fax: 040 - 2355 6354

rockystone
February 26th, 2013, 03:43 PM
BLOCK-B: 19th FLOOR (TERRACE) SLAB CONCRETING COMPLETED

http://img812.imageshack.us/img812/8373/94775092.jpg (http://imageshack.us/photo/my-images/812/94775092.jpg/)

BLOCK-C : 19th FLOOR (TERRACE) SLAB CONCRETING COMPLETED

http://img688.imageshack.us/img688/7581/29146910.jpg (http://imageshack.us/photo/my-images/688/29146910.jpg/)

rockystone
February 26th, 2013, 03:47 PM
BLOCK-A: 18th FLOOR SLAB CONCRETING COMPLETED ON 25h Dec 2012

http://img855.imageshack.us/img855/3966/94248361.jpg (http://imageshack.us/photo/my-images/855/94248361.jpg/)

BLOCK-D: 16th FLOOR SLAB CONCRETING COMPLETED ON 31st Dec 2012

http://img716.imageshack.us/img716/9784/dec1204.jpg (http://imageshack.us/photo/my-images/716/dec1204.jpg/)