Dubai-Lover November 20th, 2004, 10:39 PM Name: Capital Plaza
Location: Abu Dhabi Corniche
Floors: 45, 43, 30
Use: Residential, Commercial, Hotel
Heights: ?, 156.5, 145.5
http://www.meinhardt.com.au/media/userimages/imageB3285583309.jpg
Dubai-Lover November 20th, 2004, 10:39 PM Abu Dhabi firm inks deal for Dh750m Capital Plaza project
posted on 07/01/2004
The Real Estate Investment and Services Company yesterday signed a financial arrangement with a consortium of Abu Dhabi banks led by National Bank of Abu Dhabi, the First Gulf Bank, Union Bank and Commercial Bank of Abu Dhabi to construct a Dh750 million Capital Plaza Commercial Development Project. The project will be located on the Corniche road in Abu Dhabi.
Hamad Rashid Al Nuaimi, chairman of Real Estate Investment and Services Company said: "The tender for the project will start on 25th January and the first phase will be completed in 18 month time. The second phase is expected to begin by early 2006." The project will contain a 250-guestroom luxury hotel, a 25,000 square metre office building, 220 luxury apartments including 21 sky villas and six rooftop villa type apartments located in three towers, with retail facilities and underground parking.
Design work of the project has been awarded to the American Smallwood, Reynolds, Stewart, Stewart and Associated of Atlanta- Georgia, while REISCO Project Management Consultants has been appointed as client representatives and project managers for the project.
Khamis Buharoon, Head of Domestic Banking Division, National Bank of Abu Dhabi, said: "The Capital Plaza project is a beginning of an ongoing investment which will continue for 12 years with new projects in pipeline. The project is also part of the emirate's strategy to create dynamism in the expanding tourism sector in the UAE."
Krazy November 21st, 2004, 12:32 AM cant wait for a better render
Bahraini Spirit November 21st, 2004, 12:35 AM hasn't this project been launched like a while ago. Nonetheless, this is what Abu Dhabi needs.
Emirates ME November 21st, 2004, 04:21 AM Abu Dhabi will bie better than dubai aftre 2005 or 2006 yars
BinDubai November 21st, 2004, 01:01 PM nice project but isn't 750 million alot for such a project ?
Dubai-Lover November 21st, 2004, 01:07 PM i would say it's close to the limit
750m aed are still ok for a 3 tower complex
Krazy February 16th, 2005, 04:40 PM http://www.gulf-news.com/images/2004/01/07_reisco.jpg
Architects: Smallwood, Reynolds, Stewart, Stewart & Associates
Contact: architecture@srssa.com
Website: www.srssa.com
Location: Abu Dhabi corniche
Construction end: June 2007
Bahraini Spirit February 18th, 2005, 10:21 AM any news on this one, cause Abu Dhabi doesn't get much publicity. I suppose if they still didn't break ground, wait another year for this one to rise.
Krazy March 24th, 2006, 07:55 PM ...
http://www.meinhardtgroup.com/media/userimages/imageB3348741650.jpg
Capital Plaza, Abu Dhabi, United Arab Emirates - Corniche Coast, Abu Dhabi
Meinhardt is providing integrated engineering consultancy services for this mega project located along the prominent Corniche Coast, Abu Dhabi.
The development comprises a 30-storey hotel tower, three blocks of 45-storey residential towers, a 43-storey office tower on a 9-storey podium for retail and 3 levels of basement for carpark.
The Architect for this distinguished project is Smallwood, Reynolds, Stewart, Stewart & Associates
Source : http://www.meinhardtgroup.com/content/Projects.asp?ProjectID=1385&SectorID=-1&CountryID=212&Keywords=
dubaiflo March 24th, 2006, 08:20 PM ugly thing sorry AD ;)
well it's a render, u never know.
Towers March 24th, 2006, 08:20 PM lol if it was dubai, this tower would have been ready already, abu dhabi is slow
Krazy March 24th, 2006, 09:03 PM ^^ thats coz abu dhabi doesnt compromise on construction quality unlike dubai.... (remember the rains in greens/meadows/jumeirah islands) ? :sleepy:
Towers March 26th, 2006, 11:34 PM thats true the quality of the buildings here is great, its way better then my friends building in dubai
smussuw March 31st, 2006, 06:23 PM quality better in Abu Dhabi :weird:
it took them 16 months to provide a coloured rendering, 30 years for building it?
AltinD December 16th, 2006, 09:43 PM http://www.bncbulletin.com/pgs/prjbulletin/shared/images/prjb_title.gif
http://www.bncbulletin.com/pgs/prjbulletin/issue96/images/prjb_projname.gif
PROJECT OVERVIEW
Project Type: Commercial / Residential - Multi-Storey (Over 15)
Progress: Under Construction
Estimated Completion: July, 2008
http://www.bncbulletin.com/pgs/prjbulletin/issue96/images/image.jpg
The USD 200 million Capital Plaza project entails the construction of five towers, high luxury apartments (including 21 sky villas and six rooftop villa type apartments), retail facilities and underground parking. It covers the construction of five towers, ranging in height from 30 to 45 storeys on a seven-storey retail podium and a four-level basement car park. The tallest building being more than 300 m. Three of the towers will be residential, providing a total of 260 apartments, one tower will house a 250 room hotel, while the fifth and final tower will be 25,000 square metre office building. It is expected that the development will be connected to the beach via a tunnel under the corniche.
COMPANIES
----------------------------------------------------------------------------------------------------
Real Estate Investment & Services Co. (REISCO)
United Arab Emirates
----------------------------------------------------------------------------------------------------
Company Type: Owner, Corporation
Contact No.: 971-2-6673322
----------------------------------------------------------------------------------------------------
Smallwood, Reynolds, Stewart, Stewart & Associates, Inc. (SRSSA)
United States
----------------------------------------------------------------------------------------------------
Company Type: Consultant, Lead
Scope of Work: Project management.
Key Contact: Mr. Abid Eid, Project Manager
Contact No.: 971-2-6728806
Notes: Site office no: 02-6744032.
----------------------------------------------------------------------------------------------------
CRSS International
United Arab Emirates
----------------------------------------------------------------------------------------------------
Company Type: Consultant, Project Management
Contact No.: 971-2-6743674
----------------------------------------------------------------------------------------------------
Architectural & Engineering Consultants (ARTEC)
United Arab Emirates
----------------------------------------------------------------------------------------------------
Company Type: Consultant, Design
Key Contact: Ms. Biliana, Project Manager
Contact No.: 971-2-6811277
----------------------------------------------------------------------------------------------------
Arabian Construction Company (ACC) - Abu Dhabi
United Arab Emirates
----------------------------------------------------------------------------------------------------
Company Type: Contractor, Main
Scope of Work: Initially carried out excavation, shoring & dewatering.
Key Contact: Mr. Ramsey Al Khalil, Project Manager
Contact No.: 971-2-6771225
Notes: Site office: 02-6744038.
----------------------------------------------------------------------------------------------------
Bauer Spezialtiefbau GMBH
United Arab Emirates
----------------------------------------------------------------------------------------------------
Company Type: Contractor, Piling
Contact No.: 971-2-6721405
----------------------------------------------------------------------------------------------------
Mapco
United Arab Emirates
----------------------------------------------------------------------------------------------------
Company Type: Contractor, MEP
Contact No.: 971-2-6783626
Notes: Site office: 02 6762093
----------------------------------------------------------------------------------------------------
Ready Mix Beton LLC
United Arab Emirates
----------------------------------------------------------------------------------------------------
Company Type: Supplier, Cement & Concrete Products
Key Contact: Mr. Safan Mawaz, Technical Director
Contact No.: 971-2-6337580
NOTES
December 05, 2006
Elevator suppliers to be finalized by December 15, 2006.
March 03, 2006
Bids for the 32-month main construction contract were submitted a year ago by four contractors: Athens-based Consolidated Contractors International Company (CCC), Turkey's Nurol Group, Saudi Oger and Arabian Construction Company (ACC).
October 23, 2005
Negotiations are on-going for the main construction contract.
June 20, 2005
Phase 1 contract that comprises the excavation, shoring and dewatering works is set for completion by October 15, 2005.
April 06, 2005
Four companies submitted bids in November 2004 for the main construction package. The main contractor is expected to be announced by May 2005.
March 03, 2005
Bids have been submitted for the Project Management Consultancy (PMC) contract by: Australia's Bovis Lend Lease, CRSS International (a subsidiary of US' Jacobs Engineering Group), Turner Construction International of the US and UK's E. C. Harris.
August 17, 2004
The Capital Plaza is owned by the Royal Family of Abu Dhabi
wiki December 23rd, 2006, 06:18 PM good proyect.
sami_tabet August 2nd, 2007, 03:05 PM CAPITAL PLAZA, ABU DHABI, U.A.E.
This mixed-use development is located on Abu Dhabi Corniche opposite the Sheraton Hotel. The development includes a 32-story, 256-key, 5 Star, Millennium & Copthorne Hotel; a 34-story, office building; three apartment towers ranging from 39 to 45-story and parking for 1, 400-cars.
Hotel Tower: 32 Floors, Height 166M
Office Tower: 34 Floors, Height 200M
Apartment Tower B: 45 Floors, Height 210M
Apartment Towers A & C: 39 Floors, Height 173M
Total number of apartment units 445
Apartment unit mix: 1, 2, 3 & 4 bedrooms.
Podium: 9 Floors
Basement: 5 Floors
Total car parking spaces 1,400
Estimated Construction Budget 200 million USD
Main Construction Contract Commenced: 01 Jan 06
Time for Completion 32 Months
Delay due to unforeseen ground conditions estimated at 6 Months.
Developer: Real Estate Investment & Services Company www.reisco.ae.com
Architect: Smallwood, Reynolds, Stewart, Stewart Inc. www.srssa.com
Interior Designer: Smallwood, Reynolds, Stewart, Stewart Inc. www.srssa.com
Engineer: Meinhardt Ltd. www.meinhardt.com.sg
Main Contractor: Arabian Construction Company www.accsal.com
MEP Contractor: Mapco Ltd. www.mapco-uae.com
Engineer of Record: AEC, aecaduae@emirates.net.ae
Hotel Operator: Millennium & Copthorne, www.millenniumhotels.com
http://i183.photobucket.com/albums/x134/sami_tabet/CP2.jpg
http://i183.photobucket.com/albums/x134/sami_tabet/CP1.jpg
FEB 06
http://i183.photobucket.com/albums/x134/sami_tabet/CP3.jpg
JUNE 2006
http://i183.photobucket.com/albums/x134/sami_tabet/CP4.jpg
JUNE 2007
http://i183.photobucket.com/albums/x134/sami_tabet/CP5.jpg
abudhabiraper August 2nd, 2007, 04:19 PM fantastic!
very hard job & nice project
Thanks
abudhabiraper August 2nd, 2007, 11:54 PM http://www.bncbulletin.com/pgs/prjbulletin/shared/images/prjb_title.gif
http://www.bncbulletin.com/pgs/prjbulletin/issue96/images/prjb_projname.gif
PROJECT OVERVIEW
Project Type: Commercial / Residential - Multi-Storey (Over 15)
Progress: Under Construction
Estimated Completion: July, 2008
http://www.bncbulletin.com/pgs/prjbulletin/issue96/images/image.jpg
The USD 200 million Capital Plaza project entails the construction of five towers, high luxury apartments (including 21 sky villas and six rooftop villa type apartments), retail facilities and underground parking. It covers the construction of five towers, ranging in height from 30 to 45 storeys on a seven-storey retail podium and a four-level basement car park. The tallest building being more than 300 m. Three of the towers will be residential, providing a total of 260 apartments, one tower will house a 250 room hotel, while the fifth and final tower will be 25,000 square metre office building. It is expected that the development will be connected to the beach via a tunnel under the corniche.
COMPANIES
----------------------------------------------------------------------------------------------------
Real Estate Investment & Services Co. (REISCO)
United Arab Emirates
----------------------------------------------------------------------------------------------------
Company Type: Owner, Corporation
Contact No.: 971-2-6673322
----------------------------------------------------------------------------------------------------
Smallwood, Reynolds, Stewart, Stewart & Associates, Inc. (SRSSA)
United States
----------------------------------------------------------------------------------------------------
Company Type: Consultant, Lead
Scope of Work: Project management.
Key Contact: Mr. Abid Eid, Project Manager
Contact No.: 971-2-6728806
Notes: Site office no: 02-6744032.
----------------------------------------------------------------------------------------------------
CRSS International
United Arab Emirates
----------------------------------------------------------------------------------------------------
Company Type: Consultant, Project Management
Contact No.: 971-2-6743674
----------------------------------------------------------------------------------------------------
Architectural & Engineering Consultants (ARTEC)
United Arab Emirates
----------------------------------------------------------------------------------------------------
Company Type: Consultant, Design
Key Contact: Ms. Biliana, Project Manager
Contact No.: 971-2-6811277
----------------------------------------------------------------------------------------------------
Arabian Construction Company (ACC) - Abu Dhabi
United Arab Emirates
----------------------------------------------------------------------------------------------------
Company Type: Contractor, Main
Scope of Work: Initially carried out excavation, shoring & dewatering.
Key Contact: Mr. Ramsey Al Khalil, Project Manager
Contact No.: 971-2-6771225
Notes: Site office: 02-6744038.
----------------------------------------------------------------------------------------------------
Bauer Spezialtiefbau GMBH
United Arab Emirates
----------------------------------------------------------------------------------------------------
Company Type: Contractor, Piling
Contact No.: 971-2-6721405
----------------------------------------------------------------------------------------------------
Mapco
United Arab Emirates
----------------------------------------------------------------------------------------------------
Company Type: Contractor, MEP
Contact No.: 971-2-6783626
Notes: Site office: 02 6762093
----------------------------------------------------------------------------------------------------
Ready Mix Beton LLC
United Arab Emirates
----------------------------------------------------------------------------------------------------
Company Type: Supplier, Cement & Concrete Products
Key Contact: Mr. Safan Mawaz, Technical Director
Contact No.: 971-2-6337580
NOTES
December 05, 2006
Elevator suppliers to be finalized by December 15, 2006.
March 03, 2006
Bids for the 32-month main construction contract were submitted a year ago by four contractors: Athens-based Consolidated Contractors International Company (CCC), Turkey's Nurol Group, Saudi Oger and Arabian Construction Company (ACC).
October 23, 2005
Negotiations are on-going for the main construction contract.
June 20, 2005
Phase 1 contract that comprises the excavation, shoring and dewatering works is set for completion by October 15, 2005.
April 06, 2005
Four companies submitted bids in November 2004 for the main construction package. The main contractor is expected to be announced by May 2005.
March 03, 2005
Bids have been submitted for the Project Management Consultancy (PMC) contract by: Australia's Bovis Lend Lease, CRSS International (a subsidiary of US' Jacobs Engineering Group), Turner Construction International of the US and UK's E. C. Harris.
August 17, 2004
The Capital Plaza is owned by the Royal Family of Abu Dhabi
more than 300m ???
what is the right info ?
210m tower or 300m
if it will be of 300m , that is very good
reaching my dream
but , as i saw in the construction board it doesn't look as tall as more than 200m
thanks
SeViNiYo August 3rd, 2007, 01:09 AM nice project
sami_tabet August 5th, 2007, 09:28 AM KONE Delivers Middle East's First Double-deck Elevators to Capital Plaza in Abu Dhabi
KONE Corporation, Press Release, 13 April, 2007
KONE has won a major order to deliver all elevators and escalators to
Capital Plaza in Abu Dhabi, United Arab Emirates. The order includes
30 elevators and six escalators. Installation of the devices will
start at the end of 2007 and is scheduled for completion during the
second half of 2009.
Capital Plaza is a 5-tower multi-purpose center covering high-quality
residential, hotel and office space. The tallest of the five towers
will hold 45 floors and reach up to 156 meters.
http://i183.photobucket.com/albums/x134/sami_tabet/CP6.jpg
Four of the delivered units will be KONE double-deck elevators, which
will be installed in the office tower. The double-deck elevators will
be equipped with a destination control, and are the first of its kind
installed in the entire Middle East area. The elevators will travel
at a speed of 6 m/s.
"We are looking forward to the challenging high-rise market in the Middle East, which requires us to create more and more advanced solutions for people flow management."
The double-deck elevators consist of two elevator cars on top of each
other in the same hoist-way, thus enabling more efficient use of the
building core space. The destination control optimizes the traveling
time by directing passengers to specific elevator.
KONE Corporation
Eric
Maziol
Area Director, West and South Europe
www.kone.com
abudhabiraper August 5th, 2007, 08:22 PM abu dhabi is going slowly .. this in my opinion
156 m tower in 2009!!
.. i hope that when abu dhabi going to access year 2009 , it will has a tower reaches 200m and over that
abu dhabi's skyline is very attractive and tasty , it reminds me as Newyork skyline , but the first one needs some of taller buildings.
sami_tabet August 21st, 2007, 09:24 AM CAPITAL PLAZA AUGUST 2007
http://i183.photobucket.com/albums/x134/sami_tabet/CapitalPlazaAug2007.jpg
Krazy August 21st, 2007, 03:21 PM ^^ thanks, now I know where the site is
sami_tabet February 2nd, 2008, 08:33 PM DECEMBER 2007
http://i183.photobucket.com/albums/x134/sami_tabet/CapitalPlazaDec2007.jpg
bizzybonita February 5th, 2008, 06:53 PM AD is capital of uae SO....
killerk February 6th, 2008, 06:29 PM abu dhabi is going slowly .. this in my opinion
156 m tower in 2009!!
.. i hope that when abu dhabi going to access year 2009 , it will has a tower reaches 200m and over that
abu dhabi's skyline is very attractive and tasty , it reminds me as Newyork skyline , but the first one needs some of taller buildings.
AD is not going "slow", they are just following basic urban design / Physical Planning guidelines....one can't expect a "tallest building in the world" at the intersection of Khalifa street and Salaam street, already known for its high density. However, we can definitely hope that they do something exceptional on Reem Island.....
XP March 24th, 2008, 12:14 PM ^^ thanks, now I know where the site is
The following photo might further let you know..
http://archive.gulfnews.com/images/08/02/01/abudhabi_corniche5_5.jpg
sami_tabet April 20th, 2008, 10:50 AM APRIL 2008
http://i183.photobucket.com/albums/x134/sami_tabet/April08.jpg
glitz_boy June 14th, 2008, 06:12 PM any update on this, any1?
MOHMOH June 14th, 2008, 06:58 PM as i know now the middle tower has reached 15 floor + 6floors for the parking
so now its 21 floors
MOHMOH June 14th, 2008, 06:58 PM the project will be over by late 2009
glitz_boy June 20th, 2008, 02:37 PM mohmoh ... take picture for us please :D
MOHMOH June 24th, 2008, 10:35 AM K i will try
sppn i will bring new phtos
MOHMOH June 24th, 2008, 10:36 AM k i will try
soon i will bring new photos
bestkub July 15th, 2008, 05:08 PM 7.07.08 Flickr, By yumnaaa
http://farm4.static.flickr.com/3031/2647394452_c115649030_o.jpg
MOHMOH July 27th, 2008, 11:04 AM i have good news
the middle tower has reached the 30 th floor
and the cladding has started on 4 floors
Mary Marcos August 11th, 2008, 03:31 PM Is this a freehold project?
MOHMOH August 11th, 2008, 05:56 PM no sorry its not a freehold this just a renting building 3 residental building all renting 1 office and 1 hotel
sami_tabet October 14th, 2008, 10:31 AM Abu Dhabi, United Arab Emirates, Capital Plaza
http://i183.photobucket.com/albums/x134/sami_tabet/P1000575.jpg
LoverOfDubai October 15th, 2008, 04:50 AM Thanks for the update.
XP December 22nd, 2008, 03:11 PM Update Please!!
sami_tabet December 25th, 2008, 01:24 PM CAPITAL PLAZA - Progress Photos - November 2008
http://i183.photobucket.com/albums/x134/sami_tabet/CP4-1.jpg
http://i183.photobucket.com/albums/x134/sami_tabet/CP3-1.jpg
http://i183.photobucket.com/albums/x134/sami_tabet/CP2-1.jpg
http://i183.photobucket.com/albums/x134/sami_tabet/CP1-1.jpg
Developer: Real Estate Investment & Services Company www.reisco.ae.com
Architect: Smallwood, Reynolds, Stewart, Stewart Inc. www.srssa.com
Interior Designer: Smallwood, Reynolds, Stewart, Stewart Inc. www.srssa.com
Engineer: Meinhardt Ltd. www.meinhardt.com.sg
Main Contractor: Arabian Construction Company www.accsal.com
MEP Contractor: Mapco Ltd. www.mapco-uae.com
Engineer of Record: AEC, aecaduae@emirates.net.ae
Hotel Operator: Millennium & Copthorne, www.millenniumhotels.com
The Consultant April 14th, 2009, 04:43 PM It is stated that the three residential towers have a total of 260 units.. if that is true, then each tower would have an average of 85 units in total and a little bit above 2 units per floor. it just could not make sense to me, the number sounds really low, if any one could confirm the total number of residential units, i will highly appreciated. thank you guys in advance (S)
cheers
sami_tabet April 27th, 2009, 06:52 PM Abu Dhabi, United Arab Emirates, Capital Plaza
Progress Photos - April 2009
http://i183.photobucket.com/albums/x134/sami_tabet/CP1-3.jpg http://i183.photobucket.com/albums/x134/sami_tabet/CP4-2.jpg
http://i183.photobucket.com/albums/x134/sami_tabet/CP5-1.jpg http://i183.photobucket.com/albums/x134/sami_tabet/CP2-2.jpg
Developer: Real Estate Investment & Services Company www.reisco.ae.com
Architect: Smallwood, Reynolds, Stewart, Stewart Inc. www.srssa.com
Interior Designer: Smallwood, Reynolds, Stewart, Stewart Inc. www.srssa.com
Engineer: Meinhardt Ltd. www.meinhardt.com.sg
Main Contractor: Arabian Construction Company www.accsal.com
MEP Contractor: Mapco Ltd. www.mapco-uae.com
Engineer of Record: AEC, aecaduae@emirates.net.ae
Hotel Operator: Millennium & Copthorne, www.millenniumhotels.com
http://i183.photobucket.com/albums/x134/sami_tabet/CP6-1.jpg
http://i183.photobucket.com/albums/x134/sami_tabet/CP7.jpg
Krazy June 3rd, 2009, 07:04 AM last week:
http://i41.tinypic.com/okxtog.jpg
http://i42.tinypic.com/wcg1lv.jpg
MOHMOH June 3rd, 2009, 10:36 AM Oh My GOD this buildings r relly massive they r beautifull but very close 2 each other
flares June 4th, 2009, 05:56 AM nice facade, more interesting than others
sami_tabet July 8th, 2009, 10:40 AM Abu Dhabi, United Arab Emirates, Capital Plaza
Progress Photos - JULY 2009
http://i183.photobucket.com/albums/x134/sami_tabet/P1010857.jpg
http://i183.photobucket.com/albums/x134/sami_tabet/P1010833.jpg
http://i183.photobucket.com/albums/x134/sami_tabet/P1010856.jpg
http://i183.photobucket.com/albums/x134/sami_tabet/P1010852.jpg
http://i183.photobucket.com/albums/x134/sami_tabet/P1010854.jpg
http://i183.photobucket.com/albums/x134/sami_tabet/P1010826.jpg
Adam2707 July 24th, 2009, 02:34 PM http://lh4.ggpht.com/_hkjl1sOnUME/SmlwNn0gu3I/AAAAAAAABuU/PjidTlBeXr0/s400/DSC_0360.JPG
High Resolution (http://picasaweb.google.com/guy.m.cyr/20090719AbuDhabi#5361940210691128178)
Almost topped out. :cheers:
thelandmark August 7th, 2009, 06:04 PM Lovely buildings,
Capital Plaza: 7/Aug/2009
http://img26.imageshack.us/img26/3996/img1305g.th.jpg (http://img26.imageshack.us/my.php?image=img1305g.jpg)
http://img515.imageshack.us/img515/7306/img1306l.th.jpg (http://img515.imageshack.us/my.php?image=img1306l.jpg)
http://img263.imageshack.us/img263/3533/img1311h.th.jpg (http://img263.imageshack.us/my.php?image=img1311h.jpg)
http://img33.imageshack.us/img33/6421/img1314p.th.jpg (http://img33.imageshack.us/my.php?image=img1314p.jpg)
http://img11.imageshack.us/img11/8408/img1315avw.th.jpg (http://img11.imageshack.us/my.php?image=img1315avw.jpg)
http://img526.imageshack.us/img526/2319/img1316.th.jpg (http://img526.imageshack.us/my.php?image=img1316.jpg)
bizzybonita August 14th, 2009, 04:34 PM Capital Plaza Development in Abu Dhabi
Client: Real Estate Investment Services Company (Reisco)
Actual Value: 205m USD
Contractors: Main Contractor: Arabian Construction Co.
Consultants:Main Consultant: Stewart & Associates
Project Type: Mixed Use
Project Duration:
From: Q1 2006 Actual
To: Q4 2009 Actual
Status: Construction
Scope: The scope of work include construction of a complete development which comprised five tower buildings with a shared podium. The project contains a 250 room five star hotel tower, a 25,000 square metres office building, 220 luxury apartments including 21 sky villas and six rooftop villa apartments located in three towers, with retail facilities and a four storeyed underground carpark. This mixed-use development ranges in height from 30 to 45 floors on a seven floor retail podium and four basement car park.
Schedule: Arabian Construction Co. (ACC) was awarded the main construction contract in December 2005. Construction started in early of 2006 and expected to be completed by the end of 2009.
Mase September 25th, 2009, 05:13 AM Looking at the development from the Corniche the 3 towers at the back are all resi and will provide 469 apartments in total - completion due mid 2010.
Neilmpenny September 28th, 2009, 07:48 AM Consultants:Main Consultant: Stewart & Associates
That would be; Smallwood, Reynolds, Stewart, Stewart & Associates.
Stephan23 October 17th, 2009, 06:38 PM Topped out !
monymoe October 19th, 2009, 09:07 AM Topped out !
I am looking outside my window right now; and its not really topped out.
but its very, very close. They built this thing SO fast though!
Adam2707 November 20th, 2009, 01:59 PM 17th Nov
http://img4.imageshack.us/img4/3986/dsc01142ju.jpg
UAE'er February 13th, 2010, 12:03 PM Pretty much Topped Out!
after many years of slow down, its almost completed. they almost did 50% of the work in 2009 alone.
http://img2.pict.com/df/09/8e/2828456/0/800/img00235201002101304.jpg
UAE'er February 16th, 2010, 12:28 PM WE HAVE SPIRALS :banana:
i was passing by today and I saw spirals installed on 2 of the towers, couldnt see the other towers, so cant confirm if they were topped out.
I will take pictures later today and post them
Javier.med.qqta February 16th, 2010, 06:17 PM :okay:
UAE'er May 19th, 2010, 01:02 PM 6th May
http://lh4.ggpht.com/_47Rbw7YnvJg/S-uQ903N27I/AAAAAAAAAMU/xEgpDdocdMM/s800/IMG00029-20100506-1442.jpg
boschb August 30th, 2010, 09:28 PM ^^ nice, fancy like braj al bait kinnda
andregrant13 November 26th, 2010, 03:08 AM KONE Delivers Middle East's First Double-deck Elevators to Capital Plaza in Abu Dhabi
KONE Corporation, Press Release, 13 April, 2007
KONE has won a major order to deliver all elevators and escalators to
Capital Plaza in Abu Dhabi, United Arab Emirates. The order includes
30 elevators and six escalators. Installation of the devices will
start at the end of 2007 and is scheduled for completion during the
second half of 2009.
Capital Plaza is a 5-tower multi-purpose center covering high-quality
residential, hotel and office space. The tallest of the five towers
will hold 45 floors and reach up to 156 meters.
http://i183.photobucket.com/albums/x134/sami_tabet/CP6.jpg
Four of the delivered units will be KONE double-deck elevators, which
will be installed in the office tower. The double-deck elevators will
be equipped with a destination control, and are the first of its kind
installed in the entire Middle East area. The elevators will travel
at a speed of 6 m/s.
"We are looking forward to the challenging high-rise market in the Middle East, which requires us to create more and more advanced solutions for people flow management."
The double-deck elevators consist of two elevator cars on top of each
other in the same hoist-way, thus enabling more efficient use of the
building core space. The destination control optimizes the traveling
time by directing passengers to specific elevator.
KONE Corporation
Eric
Maziol
Area Director, West and South Europe
www.kone.com
Kone Corporation
andregrant13 November 26th, 2010, 03:09 AM how much land is it on
Julito-dubai April 9th, 2011, 02:32 PM http://www.******************/pc/pc/cat/2772/display/24262084
update
bizzybonita June 15th, 2011, 05:20 PM DONE!
http://img.******************/images/United-Arab-Emirates/Abu-Dhabi/Corniche-Abu-Dhabi-im-Abendlicht-a24262084.jpg
Ahmad Rashid Ahmad April 11th, 2012, 04:34 PM THE NEW SOFITEL ABU DHABI CORNICHE (http://www.hoteliermiddleeast.com/pics-13973-photo-tour-the-new-sofitel-abu-dhabi-corniche/)
|
|