View Full Version : #ON HOLD: DELTA 1, 22F Res


AltinD
July 9th, 2006, 02:03 PM
Name: DELTA 1
Developer: DELTA PROPERTIES LLC
Plot: 2Q, #392-259
Floors:
Height:
Started: 2006
Completed: 200?

http://i6.tinypic.com/1zel74l.jpg

AltinD
July 9th, 2006, 02:05 PM
Location is just next to Radisson SAS Residence.

The Project Board

http://i6.tinypic.com/1zel7kl.jpg


The site

http://i6.tinypic.com/1zel84i.jpg

Stephan23
July 9th, 2006, 03:55 PM
Any idea how much floors?? :hm:

AltinD
July 9th, 2006, 07:03 PM
^^ The render has some 20 floors.

Chad
July 9th, 2006, 07:08 PM
Sounds like Delta Nu...:D

Dubai-Lover
July 11th, 2006, 02:20 AM
i count 21
nice building
you can tell from the render it's been designed by norr
lol

added to emporis

thedubailife
July 11th, 2006, 11:50 AM
Seams odd that there is machinery on site but no launch or anything on these i know Emaar do that but they are big.

But may sell quicker if work already started.

Dubai-Lover
August 1st, 2006, 08:28 PM
july 30

http://i7.tinypic.com/21mxfut.jpg

Krazy
August 1st, 2006, 10:38 PM
:eek: quite a bit of progress there in about 3 weeks!

thedubailife
August 2nd, 2006, 12:24 PM
OMG thats more progress then Infinity in 3 weeks

Imre
March 9th, 2007, 04:01 PM
any info of this???

Imre
August 8th, 2008, 10:50 AM
U/C again, board has been changed, construction has started, Delta 2 as well.

AltinD
August 8th, 2008, 02:47 PM
Yeah, I've also seen new portacabins and mobilization on site.

bizzybonita
August 19th, 2008, 12:07 AM
U/C again, board has been changed, construction has started, Delta 2 as well.

yupppp

Imre
December 28th, 2008, 02:58 PM
grand concrete pouring today, will be rising soon:)

Tarix_C
March 23rd, 2009, 11:29 AM
Do we know anything about the developers of this project? Is it still U/C?

Imre
April 22nd, 2009, 03:44 PM
U/C and rising

22/April/2009

Delta 1

http://i43.tinypic.com/mx226f.jpg

http://i41.tinypic.com/b4cihd.jpg

Imre
July 10th, 2009, 06:55 PM
ON HOLD again

Imre
September 5th, 2009, 08:43 AM
05/September/2009

Delta 1 ,same as the Delta 2 , ON HOLD

http://i28.tinypic.com/kbt7yf.jpg

TMZ
March 1st, 2010, 07:06 AM
anything new from this developer 6 months later, I am trying to get an acurate list of all projects on hold or canceled in the marina

Imre
March 1st, 2010, 07:11 AM
Started: 2006
Completed: 200?


201? :)

Still ON HOLD.

TMZ
July 8th, 2010, 10:58 PM
its still on hold , at least it was until june 6th, rebars all rusted

UAE_AD
December 6th, 2010, 10:09 AM
Still on hold.

GTR11
February 25th, 2011, 10:49 PM
anything new from this one?

Imre
February 26th, 2011, 05:07 AM
ON HOLD

DR.SHREJMAN
December 9th, 2011, 05:20 PM
still on hold?

Imre
December 9th, 2011, 05:21 PM
Yes.

AppleMac
December 10th, 2011, 02:42 PM
They were putting up new fencing the other day - I was hoping that that signaled the start of something.

Imre
December 10th, 2011, 04:52 PM
They were putting up new fencing the other day - I was hoping that that signaled the start of something.

I saw the same front of the site offices ,I think they just try to hide the site with higher fence.

Probably after they will cover the whole site with the green plastic as at the Delta 2 site..