View Full Version : #COMPLETED: TIME PLACE, 35F Res, 158m (Dubai Marina)


Pages : 1 2 [3] 4 5 6 7 8 9 10 11 12 13 14 15 16

Mr Moose
June 18th, 2006, 11:44 PM
Carpetking
The type 2Bs for floors 2-23 are now 869sqft so there is a difference from floors 24-30.
We bought in January and our contract still shows the old floorplan but also shows the new sqft value.
The maintenance charges are showing in our contract as 869.40*8 = AED6955

carpetking
June 19th, 2006, 06:34 AM
Mr.Moose
I bougt my 2B typ last year August.My contract shows the old floorplan and
the lower maintenance charge as 776,10*8 =6208,80 AED.

carpetking
June 19th, 2006, 11:10 AM
..found in web...i think typ 2C...

http://www.timeplacedubaimarina.com/facilities.htm

onetickin_onetickout
June 20th, 2006, 09:25 AM
..found in web...i think typ 2C...

http://www.timeplacedubaimarina.com/facilities.htm


I think that is 2A - similar to my purchase. Check out Gowealty site, they have floor plans.

http://www.gowealthy.com/realestate/uae/dubai/timeplace/plans.asp

onetickin_onetickout
June 20th, 2006, 09:27 AM
Isn't it a bit early to start advertising for rental anyway?

mission
June 20th, 2006, 11:51 AM
totally agree its way to early

Any updates anyone i reckon 3 to 4th floor now

Jacko
June 20th, 2006, 12:27 PM
I know this is'nt the place to discuss this but I cannot find an investor section on site!
Does anyone know of an agent they would recomend for selling a type 4. Thanks

mission
June 20th, 2006, 12:32 PM
Jacko

I have always been told by agents to keep properties till they are complete then they will be worth more

Jacko
June 20th, 2006, 12:36 PM
If you look on Dubai marina thread, there is a picture from Dubai Freak taken 16th June which just catches TP on right- Still on second floor.

carpetking
June 20th, 2006, 01:30 PM
Jacko

Ask ali from ABRAJ for a type 4

gmalhot
June 21st, 2006, 07:35 AM
Dear All,

All of us have invested in this property in the marina timeplace, I believe that we should do away with the negetivity regarding our building and the marina area.
Well, I have purchased the place to live in and yes even if it is a few months late I dont care as long as the work is good. I believe that the marina area will be always in demand no matter what, those expcting 30% returns in a year should forget about it as those days are gone, I believe that I will be happy with 5-10% appreciation on my apartment year on year and I plan to sell in 5 years time..

Overall I believe in the Dubai story and do believe that it is the place to be even with all its downside. I believe that most of us here are expats and we all have purchased this place based on what we have heard regarding dubai and its property market.

As for the marina area, if you have tracked similar areas all over the world in big cities you will see that even with the property markets going down the marina areas have always mantained their popularity among investors...I understand that there are a few infrastructure problems on that side but if you see all around, all these luxury apartments are coming up, people have spent millions of dollars on these buildings. I do not think that these builders and investors have done so without taking all the parameters into account.

well, sorry for ranting but sometimes I get depressed reading the thread and wanted to speak my mind.

Gaurav

Jacko
June 21st, 2006, 10:08 AM
Why are you suddenly saying all this! It is not related to any of the recent discussions and who is knocking TP?

gmalhot
June 21st, 2006, 02:29 PM
well,

I just saw this discussion and read like the last 100 posts and this was just a general posting of my thoughts.

was not meant agaist anyone in particular. It was a summary of how I felt after reading so many posts of the last few months together.

Cheers

gaurav

Krazy
June 21st, 2006, 02:47 PM
thanks for your views. Which similar areas in big cities around the world have you tracked?

carpetking
June 22nd, 2006, 01:15 PM
no new updates ???

http://i5.tinypic.com/157lo5v.jpg

HAAN
June 26th, 2006, 11:18 AM
"Today, the core building is at level 5, we have completed all cement work in relation to basements, parking and Ground floor. Next week we are starting pouring level one. The work will be quicker once we finish level one since from level 2 onwards we are in typical floors and work moves smoother and faster"

The above was received form Abraj on 13th June. Has there been any further progress. Are they on floor 3 or ?

carpetking
June 27th, 2006, 12:04 PM
Progress.....

I ask Bijay today for new pictures (updates)
and i awaiting an email from him.

HAAN
June 28th, 2006, 12:45 PM
Update received from Abraj

"We have completed the first floor pouring and will be starting on the second floor pouring this week.
I have already spoken to the Engineer at the site and he would be sending me the updated pictures. As soon as I receive them, I will forward it to you."

carpetking
June 28th, 2006, 01:29 PM
Haan

Thank you for the bad news.If i receive the pictures fro Abraj i will post
them too.

see u in Timeplace 2008 ????????

AltinD
June 28th, 2006, 07:11 PM
^^ BAD news??? :weird:

carpetking
June 28th, 2006, 07:47 PM
look this picture AltinD taken between 23.-24th June

http://i3.tinypic.com/160ssgm.jpg

is this progessing ???

dubaiflo
June 28th, 2006, 09:14 PM
u can't really see anything from those pictures, and it always takes long to come out of ground and above the basement, ground and M levels to the regular floors.

carpetking
June 28th, 2006, 09:24 PM
Hi flo,

i wait for new pictures from Abraj and i hope they send it me tomorrow

gmalhot
June 29th, 2006, 09:36 AM
Just some information, spoke to an agent who sold type 2c 850 sq feet, 2nd floor for 700,000 dhs

Well, I purchased mine on the 29th floor for 884,000, feel I paid too much premium for the upper floor even though I purchased from the developer.

Any thoughts all you people...

carpetking
June 29th, 2006, 10:12 AM
gmalhot...

I bought an 2B type on 29th floor last year and i paid 822,000 dhs for
870sqft.You paid a little more but I think your price is ok.
Enjoy the view from 29th floor !!!!!!
I bought from www.gowealthy.com

gmalhot
June 29th, 2006, 10:20 AM
hey carpetking,

Thanks for the quick input.

Well, that makes sense that you purchased it last year. I purchased it a month and a half ago so I guess it was ok taking the time gap into account.

Well are you looking to sell or live in it and what kind of premium do you expect in the next couple of years if you do decide to sell.



Cheers

minime
June 29th, 2006, 10:22 AM
Just some information, spoke to an agent who sold type 2c 850 sq feet, 2nd floor for 700,000 dhs

Well, I purchased mine on the 29th floor for 884,000, feel I paid too much premium for the upper floor even though I purchased from the developer.

Any thoughts all you people...

If you wait until construction has started, prices do go up yes. I have seen the same with Marina Diamond that even though they where developer direct. The last ones are sold at a premium. :)

Jacko
June 30th, 2006, 02:57 PM
According to an agent in Dubai, Abraj have told them they are running 2 months behind. So I see that as May 07.

mission
June 30th, 2006, 11:29 PM
hi all

I have purchased on the 10th floor.

Abraj are running 10 months late. I think it will be ready by Christmas 2008

I have a 1 bedroom for sale if anyone is interested

Krazy
July 1st, 2006, 03:32 AM
Project: Time Place
Type: Residential
Floors: 35
Height: 158m + 40m Sundail
Construction Start: 2005
Construction End: Early 2008

Part 1 (http://www.skyscrapercity.com/showthread.php?t=138739&page=1&pp=20)

www.timeplacedubai.com

Features: World's largest and highest sundial

http://www.skyscrapercity.com/photopost/data/503/11020Time_Place.jpg

http://www.gowealthy.com/realestate/dubai/timeplace/images/timeplace_night_gross_big.jpg

http://www.timeplacedubai.com/content/timeplace/sundial/sundial01_klein.jpg

http://www.gowealthy.com/realestate/uae/dubai/timeplace/images/timeplace_marina.jpg

carpetking
July 1st, 2006, 11:09 AM
mission

what type you have bought....and how much is it ??

AltinD
July 1st, 2006, 12:51 PM
^^ Up to a good start, arent we ... :sleepy:

carpetking
July 1st, 2006, 01:11 PM
lets start !!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!

http://i3.tinypic.com/16azbig.jpg

Kevan
July 1st, 2006, 02:21 PM
Received a letter from Abraj today confirming the size increase in apt. from 1,131.30 sq. ft to 1,314.3 sq. ft and outlining that although this is at no extra cost to the 1.01m AED that I paid, the service charge will be AED 8 x the new apartment area. Fair enough !!!

Just get it completed!!!

New thread! Started to loose the plot on the last one toward the end.

carpetking
July 1st, 2006, 10:31 PM
just received from ABRAJ .....thanks Bijay

http://i4.tinypic.com/16bx79s.jpg

http://i5.tinypic.com/16bx7x0.jpg

http://i3.tinypic.com/16bx9w1.jpg

http://i5.tinypic.com/16bxaj7.jpg

mission
July 1st, 2006, 10:58 PM
mission

what type you have bought....and how much is it ??

I have brought a 1 bedroom with rd view, its one of the smaller apartments on the 10th floor,

Whats with the new thread, they are taking ages to get off the grd

carpetking
July 1st, 2006, 11:15 PM
mission

Is yours a 1A or 1B type ???

and what is the price ???

Krazy
July 1st, 2006, 11:23 PM
Please get back to the construction of the tower itself.... let's not turn this into an investor's chat thread and turn off other forumers... PLEASE

HAAN
July 2nd, 2006, 12:40 AM
I today (Sat 1st) received the same letter as Kevan.

Also received same pictures as CarpetKing.

Now need Abraj to move on and complete.

mission
July 2nd, 2006, 09:51 PM
guys what does the letter say, i am on holiday in Barcelona at the moment

Carpetking

If u r interested mail me privatly

Krazy sorry mate

Jacko
July 4th, 2006, 04:13 PM
timeplaceview

carpetking
July 4th, 2006, 04:39 PM
Jacko

do you have new pictures ??

Jacko
July 4th, 2006, 04:49 PM
carpetking
Hi, I've had a few sent from Dubai but they do not seem that new. There is one giving the potential view but not sure how to upload .

carpetking
July 4th, 2006, 05:31 PM
Jacko

Ask Dubaiflo how to post pictures.He had help me too.

Kevan
July 4th, 2006, 05:38 PM
#92 on the last thread:

upload the pic on www.tinypic.com
-you get an url there (for example www.tinypic.com/uhhsiaojf34.jpg) or whatever.
-click on post reply here over at SSC, click this : button, and copy and -paste the link address given at tinypic.
-press ok, submit reply, that's it.
__________________

Should do it

Jacko
July 4th, 2006, 06:12 PM
Thanks Kevan, I shall have a go shortly. You will probably think they're not worth your effort! :cheers:

carpetking
July 4th, 2006, 06:49 PM
Jacko

comon i can't wait for news from T I M E P L C E......................

Jacko
July 4th, 2006, 09:18 PM
http://i6.tinypic.com/16m55cm.jpg

Jacko
July 4th, 2006, 09:33 PM
http://i6.tinypic.com/16m60yc.jpg

Jacko
July 4th, 2006, 09:34 PM
view from tphttp://i6.tinypic.com/16m67eq.jpg

carpetking
July 4th, 2006, 09:35 PM
thanks Jacko

is this the new board from Timeplace in the front ?

mission
July 4th, 2006, 09:37 PM
cool

Thanks for the update

So what does the letter from Abraj say

Jacko
July 4th, 2006, 10:02 PM
http://i6.tinypic.com/16m7ebo.jpg http://i6.tinypic.com/16m7ebo.jpg

Mission, the letter confirms the fees will remain at 8AED sq ft but on the new increased floor sizes which seems fair enough. I understand that is one of the cheapest in the Marina

Jacko
July 4th, 2006, 10:06 PM
http://i6.tinypic.com/16m7kfk.jpg

carpetking
July 4th, 2006, 10:13 PM
more more please.....

nice updates

i wanna see rising the tower....

raig
July 5th, 2006, 09:58 AM
Hi all

I have a 1 bed appt in timeplace - looking at pictures from march to June there looks like no progress to me. I am a bit worried it will not be completed until 08.

What do everyone think?

I am thinking of selling my apartment on the 11th Floor. Should i sell while I still can - before the bubble bursts

carpetking
July 5th, 2006, 12:29 PM
Hi mission

today i received the letter from ABRAJ:

Subject:TimePlace Tower -Unit No......"the Property"

Dear Mr.&Ms........

On August 25. 2005 you executed the apartment sale agreement"the Agreement"
with Abraj FZCo to purchase the property in the Timeplace Tower to be constructed
at Dubai Marina,the details are as follows:

Unit No:......
Total sq.ft.:776,10
Price:AED 822,666

It is our pleasure to inform you that due to some changes in the layout an latest methods of areas calculation,your apartment size was increased from (776,10 sq.ft.)to
(878,00 sq.ft.) and without any additional cost.

Your obligation under the agreement will accordingly change and increase with the
increase in the size of the unit,in relation but not limited to (for example) the
maintenance fees (clause No.8.3-f)

On the other hand,and despite the fact that the maintenance fees have been recently increased by serval developers,we are glad to inform you that we are maintaining the same maintenace fee (AED 8 ).Therefore and in accordance with your apartment sale agreement (clause 7-schedule A)
the maintenance fee shall remain as it is (AED 8 x the new apartment area as highlitedt above)

W e look forward to receiving you in the new premises

Yours truly

ABRAJ FZCo

mission
July 5th, 2006, 01:43 PM
Hi Carpetking

Cool. I think there will be some progress now but i do feel this will not be completed till the q3 of next year. Krazy i think you were right.

I am going to Dubai at the end of next month and i will take some picutres and hopefully the showroom will be ready.

I am really getting impatient as i brought my apartment in September 2004 and it wont be ready for another 16 months.

I do feel that it will be well worth the wait.

carpetking
July 5th, 2006, 06:26 PM
mission

Abraj have no showroom at the moment.Ali from Abraj told me

they would have a show apartment in timeplace tower

sept./okt. this year.(i think spring 2007) !!!!

If the show-apartment is ready you can see it

fully furnished.

The new Abraj office is in SPECTRUM BUILDING

2nd floor Oud Metha.

This is near Mövenpick Hotel.I was there at eastern this year.

mission
July 5th, 2006, 10:33 PM
is this near the marina, Where is this new office

Cmon boys get the floors moving and it defently wont be ready till 3rd q of 2007

Jacko
July 5th, 2006, 10:43 PM
This might sound a dum question but why can't Abraj simply employ more workers as the more behind schedule it goes, the extra wages bill adds up anyway thus reducing their profit. Last time I visited the site, it seemed as though there were less workers here on TP than the neighbouring builds. If they are trying to build on budget by reducing staff, it will certainly result in a hefty overspend later on.

On a lighter note, is the core where the lifts go and if not, what is their purpose.

carpetking
July 6th, 2006, 06:39 AM
mission

The new Abraj office is not near the Marina.It is near the Deira Citycenter
(5 min ) by taxi.

thedubailife
July 6th, 2006, 11:50 AM
^^ 5 mins from marina to Deria City Center ......what you doing flying hope it's not 5 mins in rush hour too :D

carpetking
July 6th, 2006, 12:03 PM
5 min. from Deira City Center to Spectrum Building

Abraj office !!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!

FriendlyFoe
July 7th, 2006, 04:22 PM
I realise this might be a bit of a dim question, But ABRAJ i thought were meant to be working nearly 24 hours a day, Why in any of the photos does thier seem to be no one on site doing any work? Can anyone confirm if any constuction has actually taken place as from various photos from may to current ones i can see no progress?

Any one shed any usefull info on contruction progress? What happended to the 1 floor a week promise! I reakon the Burj with its 160 floors will be built before timeplace and its 35.

Kevan
July 7th, 2006, 05:57 PM
I was on site in May, see my posts on archived thread, the last posts show what appears tp be a large expanse of concrete on the left, facing the Marina, on the second floor. None of that was there, as they were just completing the basements.
The first three levels above groung contain the pool etc and villas. I would expect those to take the time. However, they are obviosly behind schedule and I agree, there does not appear to be a lot of activity.
We need someone local to get a few more posts of pictures. Anyone out there living in MD1 overlooking the site?

carpetking
July 7th, 2006, 06:59 PM
I ask my friend in Dubai to post new update pictures from T I M E P L A C E.

mission
July 7th, 2006, 09:22 PM
the MD told me once they have completed the first two floors then its a floor a week

Dont worry

Stephan23
July 8th, 2006, 03:41 PM
THX for info :okay:

mission
July 8th, 2006, 09:17 PM
Also guys remember there will not be a lot of work done in July and August due to the employment law.

Imre
July 9th, 2006, 10:38 AM
this is a Timeplace?

http://dubaionline.mconet.biz/images/pictures_galery/2006799487399/729_20060709100016_2.jpg

http://dubaionline.mconet.biz/images/pictures_galery/2006799487399/192_20060709100018_134.jpg

carpetking
July 9th, 2006, 10:40 AM
Thank you very much Imre.
Yes i think in 12 month it is a realy Timeplace
Thanks for the update pictures.

Imre
July 9th, 2006, 10:42 AM
ok, no problem, I like this tower.

Stephan23
July 9th, 2006, 02:33 PM
So slow!!! :bash:

mission
July 9th, 2006, 05:58 PM
imre

thanks alot you are a top man

AltinD
July 9th, 2006, 06:34 PM
08/07/2006

http://i6.tinypic.com/1zexvh2.jpg

carpetking
July 9th, 2006, 07:33 PM
Thanks AltinD for this beautiful picture.Is this made from Bayside Residence ?

AltinD
July 9th, 2006, 09:37 PM
^^ No, from the road.

Jacko
July 10th, 2006, 11:01 AM
I think it is at last starting to get on with things and rising high!! You can see a lot of work has gone into the villa area and first floor which is probably the most complicated areas and hopefully they can now put all their efforts into reaching for the sky :)
I get totally depressed when I look at the Marina view thread and their progress which seems months ahead of TP considering they were at the same stage at the beginning of this year.
Onwards and Upwards

Jacko
July 11th, 2006, 02:09 PM
Abraj have new pictures on their site under 'monthly updates' :)

carpetking
July 11th, 2006, 03:24 PM
Yes, Jacko see post No.6

DUBAI-Boomtown
July 11th, 2006, 10:22 PM
Great buliding!

grow,grow,grow Time Place!

carpetking
July 12th, 2006, 03:23 PM
is this work ?

http://i6.tinypic.com/1zpof82.jpg

BankerMan
July 12th, 2006, 04:33 PM
Hi all

I have a 1 bed appt in timeplace - looking at pictures from march to June there looks like no progress to me. I am a bit worried it will not be completed until 08.

What do everyone think?

I am thinking of selling my apartment on the 11th Floor. Should i sell while I still can - before the bubble bursts
Raig....

It has been over a week since you put up this post and no one has replied. Are you surprised? You should not be, since you committed the following two grave mistakes in putting up this post: (1) You asked an investment question which is a no-no on this thread; and (2) you wrote these four horrendous words which is an absolute taboo in this thread....."before the bubble bursts".

Anyways, to answer your question I can send you a PM if you wish and give you my opinion on what you should do.....an opinion, may I add, that is based on having lived and worked in Dubai as a banker for over 20 years.

Please let me know if you wish me to PM you.

mission
July 12th, 2006, 04:36 PM
Carpetking

Where is TIMEPLACE

maltster
July 12th, 2006, 04:53 PM
Raig....

It has been over a week since you put up this post and no one has replied. Are you surprised? You should not be, since you committed the following two grave mistakes in putting up this post: (1) You asked an investment question which is a no-no on this thread; and (2) you wrote these four horrendous words which is an absolute taboo in this thread....."before the bubble bursts".

Anyways, to answer your question I can send you a PM if you wish and give you my opinion on what you should do.....an opinion, may I add, that is based on having lived and worked in Dubai as a banker for over 20 years.

Please let me know if you wish me to PM you.

Bankerman , if you dont mind me asking, what property did you buy in Dubai and when did you sell it?

carpetking
July 12th, 2006, 05:26 PM
Hi mission,

This picture is from Okt. last year.I get no reaction from my friend in Dubai.

mission
July 13th, 2006, 08:07 PM
I am glad its going off the grd now so hopefully it will now be a floor a week

carpetking
July 13th, 2006, 09:13 PM
look on Abraj website.Their second project China Town (international city)
is finished.

carpetking
July 14th, 2006, 01:29 PM
Yes,one floor per week...

http://i1.tinypic.com/1zxw3dz.jpg


Thank you Abraj

mission
July 14th, 2006, 01:45 PM
I think now they have finished international city they are pulling there resource onto this project

Jacko
July 14th, 2006, 02:21 PM
Thanks for the picture Carpet King. I think you could be right mission about puling resources. It would make sence :)

carpetking
July 14th, 2006, 07:29 PM
I received this pictures from Abraj

http://i2.tinypic.com/1zydapi.jpg

http://i1.tinypic.com/1zyddad.jpg

http://i1.tinypic.com/1zyden7.jpg

http://i1.tinypic.com/1zydhdt.jpg

http://i2.tinypic.com/1zydjyq.jpg

mission
July 14th, 2006, 07:46 PM
HOW COMES YOU ALWAYS GET THE PICTURES AND I NEVER GET ANY WHEN I ASK.

carpetking
July 14th, 2006, 07:55 PM
mission
I have made the fifth payment...and you only the fourth.
No i don't know.It's true i have payed the 5th payment.

mission
July 14th, 2006, 07:56 PM
I have paid the whole balance apart from the final payment over 12 months ago as the Dirham was so week to the pound i got 7.12.

So i do not think its that

carpetking
July 14th, 2006, 08:00 PM
I don't know why i have got the pictures.Ask Mr. Bijay from Abraj

b.rama@timeplace.com

cheers

carpetking
July 14th, 2006, 08:04 PM
If the timeplace is finished,i dink a coffee with Bijay on my balkony.
You can come too.

Kevan
July 14th, 2006, 08:39 PM
I don't care who gets them or how they get them, just keep posting the progress. As for the coffee, hope it's a big balcony as a few of us will be there.
So good to see a bit of progress and hear some optimism ...
Nice update.

carpetking
July 14th, 2006, 08:44 PM
Kevan...

I have a very big balkony.

see you

mission
July 15th, 2006, 07:15 AM
Is it me or does the floor area look very small?

carpetking
July 15th, 2006, 07:20 AM
I think it is too dark inside the building.If its finished and furnished
it looks large.Belive me.

mission
July 15th, 2006, 08:01 AM
No i mean the current core building it looks really small. There are a lot of apartments on each floor.

Kevan
When you visted Dubai and got shown around the site did you just ask the foreman?

mission
July 15th, 2006, 08:34 AM
is the rear of the building which is currently on level 1 is that for apartments 1a and 1b?

carpetking
July 15th, 2006, 08:39 AM
Yes i thing the appartments in the backside (roadview) are 1a and 1 b
but the better side is 1b.You can see the marina from your bedroom window.

mission
July 15th, 2006, 08:41 AM
I have no balcony :(

carpetking
July 15th, 2006, 08:43 AM
no problem we have a nice park on marina level.And i think if we have outside temperatures from 43 degrees,we will sit on the sofa inside.

Kevan
July 15th, 2006, 08:51 AM
I was shown what the floor area of of the two bed was and it's approximate location. If they stick to their agreed areas,120 odd sq. mts is a big piece of property. I do not think there is a lot of apts. the three bed take up one side of the Marina facing, the two bed type 4 take up the other side, so two apts for the whole of the front, a two on the bridge side... not a lot.
Then go look at apts for sale in your native country and ask the floor area.
Concrete is very deceptive, white walls and glass open it out. It's plenty big.
As CK states, we'll all be on his balcony anyway.....

mission
July 15th, 2006, 08:53 AM
What floor is everyone on i am on the 10th ?

carpetking
July 15th, 2006, 09:12 AM
I am on 29th.floor with big b a l k o n y.I would open a restaurant
his name : MARINA-VIEW-RESTAURANT:yes:

mission
July 15th, 2006, 09:24 AM
WOW 29th floor

Is 1b better then do u think i might have a view from my window. I might build a little balcony myself and hang my washing outside.

I will be parking my sofa outside and look up to all you rich boys in your balcony apartments sipping cocktails with all the hot woman.

carpetking
July 15th, 2006, 10:49 AM
mission here is a furniture example for 1 Bedroom app.

http://i1.tinypic.com/20035uh.jpg

mission
July 15th, 2006, 11:11 AM
Cool

What apartment would that be for, I think my bedroom in my apartment is going to be large. When i spoke to the MD he advised the bedroom size has increased.

Dear David,

Please find attached the floor plan of type 1B.
If compared to the previous one you will find that you have gained more
space in the bedroom due to revisions incorporated in the shafts thus giving
more space and larger area.
Best regards

So does this mean my bedroom size has increased by 113sq

carpetking
July 15th, 2006, 11:27 AM
cool mission.
My pictures shows a Suite from ocean-liner "Color-Fantasy"
I mean very luxury.
Ali fro Abraj sad,they would show us in her show appartment in Timeplace
furnitures who we can buy direkt.

mission
July 15th, 2006, 11:35 AM
Cool

I cant wait for this to be finished i do think June/July next year

carpetking
July 15th, 2006, 12:08 PM
no,the information from Abraj is this sept.-okt.
The show appartment will be in one of the first floors.

dubaiflo
July 15th, 2006, 12:23 PM
^^ u really think it will be done by mid 2007 ? :weird:

mission
July 15th, 2006, 12:25 PM
I wonder how much the furniture packages are going to be

carpetking
July 15th, 2006, 02:53 PM
http://www.ikaar.com/almoosa/furniture/home-default.asp

http://www.homecentre.net/homecentre/products/living/living1.htm

If you look for furnitures............

mission
July 16th, 2006, 06:57 AM
^^ u really think it will be done by mid 2007 ? :weird:


Flo keep the faith

Did you buy in the end when you went in April? :)

gmalhot
July 16th, 2006, 07:19 AM
I have also a type 2c on the 29th floor partial marina facing.
Well, I am looking at at least a 3-4 month delay hopeflly not more than that as rents in dubai would kill me just renting out month on month as my current rent contract expires in April 07.

Well, anyway we should all plan a get together once the place is done...

Gaurav

Krazy
July 16th, 2006, 07:22 AM
Time Place will not be completed anytime before first quarter of 2008... I dont know how you guys have your hopes up so high

mission
July 16th, 2006, 08:06 AM
Any excuse for a party.

Krazy me old boy it will be done in 2007

Krazy
July 16th, 2006, 08:11 AM
:ohno:

carpetking
July 16th, 2006, 08:18 AM
Krazy

On first april 2007 i sit on my balkony and dink a coffee !!!!!!!!!!!!!!!!!!!!!!

Krazy
July 16th, 2006, 08:21 AM
u can have it during the "tea break" with the workers having their tea on a few floors about u still under construction :lol:

carpetking
July 16th, 2006, 08:23 AM
:?

Krazy
July 16th, 2006, 08:24 AM
Each one of you TP owners owe the SSC forumers a house warming party if it's completed in 2007

carpetking
July 16th, 2006, 08:30 AM
Yes you are right.lets go :okay:

mission
July 16th, 2006, 08:36 AM
We are planning a get together anyway when its finished.

We are having it at carpetking as he has the biggest and most the highest apartment.

carpetking
July 16th, 2006, 09:14 AM
Better idea,

we make a party in the lobby with all owners and the property-manager :cheers:

dubaiflo
July 16th, 2006, 11:33 AM
:rofl:

u guys are crazy, this will never be done by apri, not even by 2007... ;)

Flo keep the faith

Did you buy in the end when you went in April? :)

yeah but not in time place, no more marina view apts.

i could have gotten a 34th floor studio, but road facing, no thanks.

mission
July 16th, 2006, 11:37 AM
:rofl:

u guys are crazy, this will never be done by apri, not even by 2007... ;)



yeah but not in time place, no more marina view apts.

i could have gotten a 34th floor studio, but road facing, no thanks.

Where did you buy in the end.

Flo it will be 2007 :cheers:

carpetking
July 16th, 2006, 11:40 AM
Flo do you talk about this appartment ?

http://i2.tinypic.com/205usm0.jpg

mission
July 16th, 2006, 11:48 AM
Is 703 sq for a 1bed small?

dubaiflo
July 16th, 2006, 11:50 AM
nope it was the studio in 34th floor.

Where did you buy in the end.

Flo it will be 2007 :cheers:

In Dubai Silicon Oasis.

Don't believe everything the Palm Pirates tell u :rofl:

carpetking
July 16th, 2006, 11:53 AM
No mission

703 sqft. is very good for a 1 Bed and marina view from bedroom window is ok
u have no balkony but your kitchen area is bigger as upper floors

mission
July 16th, 2006, 11:55 AM
Do you reckon marina view from my bedroom?

carpetking
July 16th, 2006, 11:58 AM
mission what do you mean ?

mission
July 16th, 2006, 12:02 PM
Do u think i will have a marina view from my bedroom?

I reckon i might have a slight view as long as they dont build anything to close.

Is the back on tp going to be concrete

carpetking
July 16th, 2006, 12:06 PM
TI think you have a good marina view.Next to TP is bayside residence.You look
left on marina bay.In front of your bedroom window is a small park area.

mission
July 16th, 2006, 12:07 PM
I am going to build my own balcony on my bedroom

carpetking
July 16th, 2006, 12:08 PM
no better you switch the bedroom and the livingroom.

carpetking
July 16th, 2006, 12:11 PM
sorry i mean you change the bedr..........

sorry for my bad english

mission
July 16th, 2006, 12:13 PM
Well its better than my german mines stretches to "Hallo"

So does your contract say anything about compensation if tp is late , have u asked this question ?

I am annoyed with Bijay as he confirmed to me when i was in Dubai that the maintenance fee would be based on the orginal apartment size

carpetking
July 16th, 2006, 12:17 PM
Yes mission he told me the same.Last week i received a letter from ABRAJ.

mission
July 16th, 2006, 12:18 PM
What about your contract regarding late delivery?

carpetking
July 16th, 2006, 12:20 PM
I dont know i must read it.

mission
July 16th, 2006, 12:23 PM
I am going to e-mail them and see if i get a response

dubaiflo
July 16th, 2006, 01:08 PM
^^ sorry... but can't u do this with PMs?

no other forumers are interested in these kinda things...

mission
July 16th, 2006, 02:09 PM
^^ sorry... but can't u do this with PMs?

no other forumers are interested in these kinda things...

Sorry flo

But this forum is to discuss TIMEPLACE and the progress. Some messages that you post do not interest me however i do not make a comment about it......

mission
July 16th, 2006, 02:28 PM
Look Flo
Something interesting

Dear Sir,



It is our policy in Abraj to reply to all comments and queries from our dear customers.

The completion was scheduled to be March 2007 but there was a small delay to the new labor law, therefore we rescheduled the completion to May 2007.

As for the compensation, I will get back to you as soon as I receive a reply from our lawyer on this.

If you have any enquiries, please do not hesitate to contact us any time.

dubaiflo
July 16th, 2006, 02:30 PM
^^ yes, i agree, this is sth worth to post

but i don't chat with one forumer for 20 posts about stuff which has nothing to do with the general interest in Timeplace.

mission
July 16th, 2006, 02:33 PM
Flo cmon you do ,,,,

Plus i am discussing progress and my apartment with a fellow intevestor there is nothing wrong with that.

So your saying that your 11.546 post have all been valid posts and interest to everyone and not just one fellow investor.....

gmalhot
July 16th, 2006, 02:39 PM
Dear All,

I have written to them asking them on the exact date of completion as i will have to vacate my apartment in april 07.

Do they compensate us if it is furthur delayed.

I have asked for definite answers and will post the reply when I have it.

gaurav

mission
July 16th, 2006, 02:41 PM
Gaurav

I have done the same

carpetking
July 16th, 2006, 04:00 PM
Live cam jumeirah beach (residence)
click on cam 2

http://www.jbr.ae/highband/sitevision_live/index.htm

carpetking
July 16th, 2006, 06:13 PM
Sorry i gave your a wrong email adress

b.rama@timeplacedubai.com

Bijay Ramachandran,

Abraj Property Developers,

Office No. 205,

Spectrum Building,

Oud Metha Road,

Dubai, U.A.E

Tel:+971 4 3377977

Fax:+971 4 3377855

Mob:+971 50 5500976

Krazy
July 16th, 2006, 06:23 PM
The last two pages or so have been of interest to no one but to the ones who have purchased in the TP... please limit this kind of a discussion to PMs. Thanks.

carpetking
July 16th, 2006, 07:27 PM
Krazy i dont know what you mean........

see your post 93 , 95 , 97 , 99 it is the same :weird:

dubaiflo
July 16th, 2006, 07:39 PM
but he was giving general opinion and trying to convince you, because u still believe in april 2007.

+ he was not talking to one of you... there is a real difference here.


So your saying that your 11.546 post have all been valid posts and interest to everyone and not just one fellow investor.....

yes.

carpetking
July 16th, 2006, 07:48 PM
OK flo u r right.:)

mission
July 17th, 2006, 07:02 AM
The last two pages or so have been of interest to no one but to the ones who have purchased in the TP... please limit this kind of a discussion to PMs. Thanks.


Krazy this is the TP thread so of course the investors are going to discuss general things about the project that maybe other users would not be interested in. If you look at other threads other users also discuss information that is no use to me but i respect that users will discuss non vital information as this builds moral and communication on this site. This is the whole point of a forum.

I have looked at other threads and when other users just waste pages on stupid cartoons and smiley faces or discussing what the resturant is like on the marina walk. Do you think this is any use to anyone. I think not
:bash:


I respect your comments but i think you are wrong...

Now back to what this thread is for (discussing tp).

carpetking
July 17th, 2006, 09:39 AM
I hope we get new update pictures today.
I have written an email today to Bijay from Abraj.
(one floor per week........! )

Jacko
July 17th, 2006, 10:29 AM
Sorry guys, your probably going to hate me but I've just caught up with the last 3 pages and Boring, Boring,Boring!! As I have purchased in TP, I am also interested in all it's aspects but a lot of what's been said has already been discussed a hundred times in one form or another, eg funriture packages,views etc So please don't be offended by me asking to use the pm for these areas(or you could phone each other!) :cheers:

carpetking
July 17th, 2006, 01:19 PM
OK, the next T I M E P L A C E pictures just received from Abraj

http://i2.tinypic.com/207x8uc.jpg

http://i1.tinypic.com/207xa40.jpg

http://i2.tinypic.com/207xbw4.jpg

carpetking
July 17th, 2006, 01:27 PM
http://i2.tinypic.com/207xeso.jpg

thedubailife
July 17th, 2006, 01:28 PM
Kool....looks like some progress for all the time place owners. Nice updates too

Jacko
July 17th, 2006, 01:47 PM
Great pictures CarpetKing, your now the official spokesman at Abraj

mission
July 17th, 2006, 01:55 PM
carpetking i actually think you work for Abraj

carpetking
July 17th, 2006, 01:55 PM
http://i2.tinypic.com/207xoqx.jpg

carpetking
July 17th, 2006, 01:57 PM
no mission i am an private purchaser.

I like Dubai and the marina.

and TIMEPLACE

mission
July 17th, 2006, 01:59 PM
I was joking

mission
July 17th, 2006, 04:34 PM
This at the same stage as last week pictures

Kevan
July 17th, 2006, 07:28 PM
Get a grip Mission, the core is being increased and the floors are progressing.
CK I am impressed wit the updates.
We are now seeing what has been promised - progress

Grow to the sky!!!

Jacko
July 18th, 2006, 12:47 PM
Well done again Carpet King, these recent pictures seem to have shown really good progress over the recent weeks. Abraj seem to be putting their foot on the gas peddle even with the quite July and August time.
Does anyone fancy a sweepstake to see who is the closest to the official handover. Perhaps a small gathering in CK's executive balcony for the winner.
For the record, I say October 30th 2007. :applause:

carpetking
July 19th, 2006, 08:40 PM
look on abraj website

just two new update pictures.Same as mine.

thedubailife
July 21st, 2006, 11:44 AM
Update 21/07/2006 Thanks to IMRE

http://i5.tinypic.com/20k7t3t.jpg

http://i5.tinypic.com/20k7t77.jpg

http://i5.tinypic.com/20k7thd.jpg

carpetking
July 21st, 2006, 12:20 PM
Yeah,yeah,yeah...........

Thank you for this amazing pic's and don't forget one floor per week:cheers:

mission
July 21st, 2006, 01:05 PM
That is real good progress. I am very impressed with those pictures.

Cant wait for completion......

carpetking
July 21st, 2006, 02:39 PM
I see on first pictures on second floor a balkony in front of app. type 1 B
on my floorplan there is no balkony ???

mission
July 21st, 2006, 03:33 PM
oh yeah maybe they might give us a free balcony for running late

Krazy
July 21st, 2006, 03:34 PM
ok dont start the balcony/compensation/interiors discussion again. Sorry but just wanna stop it before we start again like a couple of pages back.

mission
July 21st, 2006, 04:53 PM
ITSA JOKE CRAZY

You have told us off and i promise i will not start again okay dad

carpetking
July 21st, 2006, 04:59 PM
i agree mission.

Krazy
July 21st, 2006, 08:23 PM
go back a few pages and then tell me it's a joke. I dont want it to start again and that's why I wanna stop it before it starts again!

Again.. use PM for your investment related discussions.

mission
July 22nd, 2006, 06:49 AM
:weirdo:

Krazy i give up

mission
July 24th, 2006, 07:15 AM
I just had a e-mail from Abraj and they advised that by the end of August they will be able to give us a true completion date.

They are saying May 2007 at the moment...

dubaiflo
July 24th, 2006, 08:02 AM
and they are going to tell u end 2007 in august. if they want to tell the truth.

mission
July 24th, 2006, 08:22 AM
Flo i agree with you.

I hope Krazy does not see this post......

carpetking
July 28th, 2006, 11:59 AM
Imre and AltinD guys have your shot new timeplace update pictures ?

I can't wait for new pictures :laugh:

Krazy
July 28th, 2006, 01:48 PM
Today by Imre

http://i7.tinypic.com/219yvcn.jpg

mission
July 28th, 2006, 01:50 PM
Its defenlty a floor a week then soooo cool ,

Cheers Imre/Krazy for posting them

thedubailife
July 28th, 2006, 02:02 PM
Starting to progress now, as usual slow start, but up to full speed now.

Kevan
July 29th, 2006, 11:45 AM
I note with pleasure and a warm feeling as the curves begin to appear, the balconies to the side, small inlets and a wall on the first floor. I feel almost perverse, but only - almost.

mission
July 29th, 2006, 12:20 PM
kevan

is that where the show flat is gonna be on the first floor

carpetking
July 29th, 2006, 12:51 PM
Thanks again Imre/Krazy for this nice photo.
Timeplace is growing fast how they have told us one floor per week.

Thank you very much

Dubai-Lover
August 1st, 2006, 07:25 PM
july 30

http://i7.tinypic.com/21mxco9.jpg

Krazy
August 1st, 2006, 09:38 PM
not much to see there from the last update

chippy
August 2nd, 2006, 10:13 PM
Hi there, im new to this site, i have been reading all the comments, i am really pleased to see the growth of the construction work taking place, i have bought a 2b about half way up, my daughter is over there now hopefully taking loads of snap shots. :

Krazy
August 2nd, 2006, 10:19 PM
^^ welcome to the forum.. if u do get pictures of time place from your daughter please post them here and share with us :cheers:

chippy
August 3rd, 2006, 09:35 AM
cant promise, but will try.

carpetking
August 3rd, 2006, 02:59 PM
Thanks Dubai Lover for the update picture from 30th july.You can see the first walls inside the building.Great shot from the other side also you can see a part of the lobby and entrance.
And a warm welcome to chippy.

Stephan23
August 4th, 2006, 11:25 AM
04.08.2006 By Imre

http://i3.tinypic.com/23ku7ub.jpg

http://i3.tinypic.com/23ku7w1.jpg

http://i6.tinypic.com/23ku80j.jpg

thedubailife
August 4th, 2006, 11:31 AM
Do the average of nearly a floor a week, Timeplace owners must be happy to see good progress after the short tea break

carpetking
August 4th, 2006, 01:16 PM
Thank you Imre you are a good man,what shall we do without you ?:master:

Kevan
August 5th, 2006, 02:51 PM
They appear to be carrying out block work on the poured floors. I have skipped arround some of the other threads, Marina Views etc and they are not following the same trend. Hope the rate of progress continues. I have a pal at his place at the moment and I have asked for some photographs from the other side. Hope he delivers.
However, these ones from Imre are greatly appreciated - thanks for the updates. Makes my week end.

carpetking
August 8th, 2006, 05:31 PM
chippy...

has your daughter taken loads of shots from Timeplace ?

and can you post them here ?

gmalhot
August 9th, 2006, 03:02 PM
Ciao,

am really happy at the progress but if they stick to schedule another 30 floors would mean 30 weeks plus another 15 weeks for the sundial and the decors inside...

I dont think it will be ready before end 2007....

what say people..

gaurav

carpetking
August 9th, 2006, 03:06 PM
Abraj sad it would be may 2007

i think Timeplace is ready summer 2007

(good quality needs time.........)

thedubailife
August 9th, 2006, 03:16 PM
We not going around in that circle again read the whole thread, some think mid 2007 and others think end 2007 / start 2008.

Over and out. Now back to something which is more factual.

chippy
August 9th, 2006, 08:34 PM
chippy...

has your daughter taken loads of shots from Timeplace ?

and can you post them here ?

My daughter is still over there, im sure she has taken pictures ,although she may be using a dvd camcorder, she has a villa on the palm so plenty of snaps of that if she is allowed to get on there. she mailed me today to say she doubts " timeplace" will be ready by end of May 2007 as hoped. we will have to wait and see. but im thinking POSITIVE

carpetking
August 9th, 2006, 11:01 PM
cool chippy :)

carpetking
August 10th, 2006, 11:52 AM
there are two new update-pictures on Abraj website

www.abrajdubai.com

Imre
August 10th, 2006, 12:53 PM
10/08/2006

Time Place for Carpetking:)

http://i5.tinypic.com/2465f2u.jpg

http://i6.tinypic.com/2465ci1.jpg

http://i2.tinypic.com/2465cue.jpg

http://i3.tinypic.com/2465cll.jpg

carpetking
August 10th, 2006, 01:49 PM
Thank you very much Imre,

...today is a good day !!!!

mission
August 10th, 2006, 03:23 PM
Another floor

Cheers for the shots imre

Kevan
August 12th, 2006, 12:53 PM
Thanks to HAAN some new views showing a little more detail.

http://i8.tinypic.com/24ecavr.jpg

http://i7.tinypic.com/24ecbo2.jpg

http://i8.tinypic.com/24ecc3b.jpg

Kevan
August 12th, 2006, 01:01 PM
HAAN

http://i8.tinypic.com/24ece4x.jpg

http://i7.tinypic.com/24ecemp.jpg

http://i7.tinypic.com/24eceug.jpg

carpetking
August 12th, 2006, 02:29 PM
Thank you Kevan/Haan for the pictures.

the front of the tower where you can see the curves looks great. ;)

carpetking
August 12th, 2006, 03:18 PM
MODELAPARTMENT TIMEPLACE

...just received from Abraj



Dear......


A model apartment would be ready by the end of this month or early September. I will keep you updated. Normally, every Sunday or Monday, we get the updated pictures from the site. I will send them to you as soon as I get them.





Thanks and Regards,





Bijay

mission
August 13th, 2006, 06:51 AM
Carpetking

Bijay must love you

mission
August 13th, 2006, 02:05 PM
second picture done by Imre on the 10 August, The numbers on the building are they the 1b Apartments?

carpetking
August 13th, 2006, 03:55 PM
Yes and the pictures made by Haan the 3th and 4th you can see the 1B apartment

carpetking
August 13th, 2006, 06:21 PM
Just received from Abraj.....

http://i7.tinypic.com/24gt5q8.jpg


http://i8.tinypic.com/24gt8jp.jpg


http://i8.tinypic.com/24gt9nr.jpg


http://i8.tinypic.com/24gty52.jpg

carpetking
August 13th, 2006, 06:35 PM
more pics

http://i8.tinypic.com/24guera.jpg


http://i8.tinypic.com/24gugyf.jpg

carpetking
August 13th, 2006, 07:20 PM
last two...

http://i8.tinypic.com/24gvtzb.jpg


http://i8.tinypic.com/24gvwp2.jpg

mission
August 14th, 2006, 07:02 AM
Carpetking

Great pictures, They seem to send you the old ones.. But they are really good shots though. Who is going to Dubai next to try and get some interior shots

mission
August 14th, 2006, 08:27 AM
Dear David,

Sorry for being late in my answer but I was on some emergency leave due to
the sad war and aggression against my country Lebanon.
As explained earlier and due to one force majeure that encountered us so far
(Labor law), the same affected our progress with a 2 months delay i.e.
delivery towards end May 2007.
I hope nothing will face us anymore and we will be in a better position to
give a more accurate date by end September.
You are right and if you frequently visit the website you can clearly notice
the progress and today we have reached the 7th floor.
Hope I answered your queries and feel free to ask at anytime.
Best regards

Saad El Zein
Managing Director

Stephan23
August 14th, 2006, 10:49 AM
This one is so slow!!!! :down:

thedubailife
August 14th, 2006, 12:12 PM
^^ You feeling ok from last few upadtes by Imre it appears to be going at around 1 floor a week

Imre
August 14th, 2006, 08:34 PM
14/08/2006 from La Riviera

http://i7.tinypic.com/24mf39j.jpg

carpetking
August 14th, 2006, 09:09 PM
Another view on Timeplace :shocked:

Thank you Imre

mission
August 15th, 2006, 08:36 AM
Yes and the pictures made by Haan the 3th and 4th you can see the 1B apartment


What is the area sticking from the outside. Its not a balcony as 1b do not have them? Any ideas

:cheers:

carpetking
August 15th, 2006, 09:24 AM
I send you a PM mission ok ?

Norfolk boy
August 16th, 2006, 01:22 PM
Good day

A new member - brought 2D - one bed - was worried as nothing seemed to be happening but things moving now - I will await their comments end Sept as to when it is finished.

Any recent info/ pictures

carpetking
August 16th, 2006, 02:12 PM
Welcome Norfolk boy.

We are waiting for new update pictures from Imre "every friday" ;)

Stephan23
August 18th, 2006, 11:37 AM
18.08.2006 By Imre

http://i8.tinypic.com/24x2kjm.jpg

http://i7.tinypic.com/24x2kjq.jpg

http://i7.tinypic.com/24x2mo6.jpg

http://i8.tinypic.com/24x2mpu.jpg

carpetking
August 18th, 2006, 12:02 PM
Thank you Imre for this great pictures,also from the marina side.Timeplace looks
very good.

What can i say: thank you very much :master::applause::applause::applause:

mission
August 18th, 2006, 12:09 PM
If i ever go to Dubai can you get on site and be shown around?

Imre
August 18th, 2006, 12:34 PM
yes , of course Mission :)

mission
August 18th, 2006, 12:39 PM
Imre you are a legend!!!!!!!!!!!!!!

Norfolk boy
August 21st, 2006, 11:05 AM
Great pictures - it seems to be coming on now - I cant see it being ready until end of 2007 though - hopefully we will be told soon so we all know what we are doing :bash:

Does anyone have a plan of the marina complex - ie shops/ restaurants, parks etc?

I think the the marina will look great when 'finished.'

Norfolk boy
August 23rd, 2006, 01:50 PM
I have heard directly today that expected completion date and moving in date is expected to be end of July 2007

I suppose good news....except that Dubai closes down in July and August, so does that mean September?

mission
August 23rd, 2006, 02:14 PM
Who told you this?

Stephan23
August 23rd, 2006, 02:16 PM
^^very optimistic!!

mission
August 23rd, 2006, 02:35 PM
To be honest if they top out by end of Jan, i would think that September would be a possiblity

Norfolk boy
August 23rd, 2006, 07:43 PM
Bijay answered my email to him

someone else try early next week and see what they say - I guess it is still guess work at this stage

mission
August 23rd, 2006, 07:52 PM
Can you forward the email to me on davedubaidave@yahoo.co.uk

mission
August 23rd, 2006, 08:17 PM
I have some new pictures from Abraj. I have e-mailed Carpetking to upload as i am unable to do this at work