Hydra Corporate Towers


Location: http://wikimapia.org/#lang=en&lat=24.494042&lon=54.400687&z=18&m=b

Hydra Corporate Towers are two new exclusive office towers located in the heart of Al Reem Island (City of Lights). The towers offer a unique community with unparallel views of the lake and easy access to the centre of Abu Dhabi.

The interior is designed to make optimum use of space and light and every detail has been carefully planned and worked out, from its high-speed elevators and multi level car parks, to its world-class leisure facilities.

The offices are carefully designed to address all business needs, by bridging the gap between work and leisure. Business’ growth depends on the work environment cultivated and with today’s offices being more than just a workplace; ideas come to fruition only in the most conducive environments. Its interiors are complemented by the latest in interior design, facilities and fixtures to create a better work atmosphere. World-class quality is achieved only through attention to every minute detail and design that are sure to exceed the highest expectation.

The tower’s serviced apartments are designed with the latest in interior design and fully equipped with the latest of fixtures and facilities. The apartments are for outright sale in the tower which is located in the heart of City of Lights on Al Reem Island. The five-star property will be managed by a leading luxury hotel group.

Owners of the fully furnished, fully serviced apartments retain total flexibility to occupy their pied-a-terres whenever they want and to release it to the international hotel group to earn income for them at times when they do not use it .
 
See less See more
#3 ·
Hydra finishes excavation work



on Tuesday, August 19, 2008

Hydra Properties, one of the leading property developers, yesterday announced the completion of excavation work for the Hydra Corporate Towers at Al Reem Island in Abu Dhabi.

Dr Sulaiman Al Fahim, Chief Executive Officer, said: "Hydra Corporate Towers will bring hitherto unheard of class and elegance to business towers in Abu Dhabi. This project is especially meant for decision makers and the spaces are planned in such a way that ideas and strategies will flourish in a conducive atmosphere for innovative thinking. I'm confident that the Hydra Corporate Towers will inspire a new business ethos in Abu Dhabi and contribute in towards the growth of the nation."

The project is expected to be completed by September 2011, and is executed by Tafseer Contracting Company, while National Engineering Bureau acts as the engineering consultancy.

Jonathan Ing, Project Manager, said: "Hydra Properties has made much headway in the initial phase of the project and is going ahead of schedule to complete the towers. Excavation has been completed in a smooth manner and now men and materials are ready for the next stage."

Corporate Towers include two office towers and will also feature a number of serviced apartments, which will be managed by a leading luxury hotel group, are available for outright sale.

Hydra Properties is a privately-owned company, established in 2006 in Abu Dhabi, and has projects in Mexico, Kuwait and UAE.
 
#4 ·
NEB wins Hydra Corporate Towers contract


National Engineering Bureau has been confirmed as the engineering consultant for Hydra Corporate Towers. 60% of the excavation work on the towers has already been completed and Hydra Properties has revealed an MEP contractor will be appointed in the next 2-3 months.

The buildings, located at Al Reem Island in Abu Dhabi, will include two 30-storey office towers, a third 24-storey offering serviced apartments and multi-level car parking. The apartments will be managed by a luxury hotel group. The project is expected to be completed by September 2011; Hydra Properties project manager Jonathan Ing revealed: “The initial phase of the project is going ahead of schedule and 60 per cent of excavation work has been completed.” He added that the firm had used its logistics capabilities to “speed up the enabling work”.

National Engineering Bureau is also acting as the architects for the project and Tafseer Contracting will oversee construction.
 
#12 ·
Construction Milestone



Waterproofing to Pile caps and Main Raft for Tower A & B Completed, Rebar to Pile caps and Main Raft for Tower A & B on progress 90%, Concrete Pouring to Water Tank Foundation to Tower A & B Completed, Concrete casting to Columns & Retaining walls podium.

http://www.hydraproperties.com/projects/constructionupdates.php?id=6
 