Ganga Expressway | Noida - Ballia | 1047 Kms | 8 lanes | Proposed
A road project of this massive size needs a thread of its own.
Project background from Wikipedia: The Ganga Expressway Project was launched by Uttar Pradesh Chief Minister Mayawati after coming to power in 2007. The project aims to construct a 1047 km access controlled eight-laned expressway running along the Ganga river. This expressway will connect Greater Noida to Ballia thus ensuring high speed connectivity between the Eastern and Western boundaries of Uttar Pradesh. The project is expected to be completed in the next four years. Relevant posts from the Highways thread: Sept 5, 2007 Quote:
Quote:
Quote:
Quote:
Dec31 2007: Quote:
Quote:
Jan 13: Quote:
Quote:
Quote:
Apr 14: Quote:
Last edited by IndiansUnite; April 22nd, 2008 at 10:53 PM. |
||||||||||||||||
|
|
|
|
|
#2 |
|
Registered User
Join Date: Jul 2004
Posts: 4,015
Likes (Received): 7
|
UP is a doombed state. this will take decades to get off the floor. dont hold your breath on this one.
|
|
|
|
|
|
#3 |
|
->
Join Date: Apr 2006
Location: Hanooz Dilli dur ast
Posts: 10,447
|
Bro, this road project has been the fastest project to get off the ground and be tendered out to a developer. Mayawati announced this project in Sept07 and it got awarded to Jaypee Group in Jan08. If NHAI was constructing it, then they would have taken a good 2 years for it to be awarded to a developer. Read the last article to see how gung-ho Jaypee Group is.
|
|
|
|
|
|
#4 | |
|
Registered User
Join Date: Nov 2004
Posts: 1,505
Likes (Received): 0
|
Quote:
Of course, NHAI is a bureaucracy and has its own delays due to political and administrative reasons. |
|
|
|
|
|
|
#5 | |
|
->
Join Date: Apr 2006
Location: Hanooz Dilli dur ast
Posts: 10,447
|
Quote:
|
|
|
|
|
|
|
#6 | ||
|
Registered User
Join Date: Mar 2006
Posts: 5,709
Likes (Received): 1
|
Quote:
Quote:
Last edited by Babji; May 18th, 2008 at 09:31 PM. |
||
|
|
|
|
|
#7 |
|
MAVerick
Join Date: Apr 2006
Location: Hyderabad/Houston
Posts: 6,713
Likes (Received): 11
|
Yeah.....this is huge.
Hope they have good eco plan.
__________________
Harsh's Photo Thread / Bharadwaj's mini South India Trip Webcams Thread / Hyderabad Cityscapes "We are all atheists about most of the gods that humanity has ever believed in. Some of us just go one god further." - Richard Dawkins |
|
|
|
|
|
#8 | |
|
Registered User
Join Date: Nov 2004
Posts: 1,505
Likes (Received): 0
|
Quote:
|
|
|
|
|
|
|
#9 |
|
sitz, it is.
Join Date: Feb 2008
Location: New Delhi
Posts: 1,888
Likes (Received): 0
|
Ditto on that.Massive project! Once get done, it will not only benefit UP but also Bihar, West Bengal, the North East and other parts of the country
|
|
|
|
|
|
#10 |
|
Registered User
Join Date: May 2008
Posts: 5
Likes (Received): 0
|
Old news but has not yet been posted.
Ganga Expressway alignment plan submitted http://www.financialexpress.com/news...mitted/337001/ |
|
|
|
|
|
#11 |
|
Complex Equation
Join Date: Jun 2005
Posts: 6,246
|
i was skeptical about the project from the very beginning but a relative of mine who works for a firm busy preparing DPR for the project said that its very much on.
The DPR would be submitted to the govt in 6 months from now along with all the environmental implications. The land acquisition process would start then. Meanwhile work on the first stretch of 25 Km of Yamuna Expressway has started on the land where the Noida - Greater Noida E'way ends. Will get the necessary updates as and when possible. |
|
|
|
|
|
#12 |
|
resU deretsigeR
Join Date: Dec 2007
Location: London
Posts: 2,596
Likes (Received): 0
|
thanks for the info
__________________
I don't believe it. Prove it to me and I still won't believe it. - Douglas Adams |
|
|
|
|
|
#13 |
|
aham brahmasmi
Join Date: Jun 2007
Posts: 822
Likes (Received): 20
|
Has there been any news on this lately?
Last edited by india; September 5th, 2008 at 12:05 PM. |
|
|
|
|
|
#14 |
|
unregistered
Join Date: Dec 2004
Posts: 2,578
Likes (Received): 1
|
we all know oim a bit tik but . .
surely the GQ section from dehli to calcutta does this, or a very similar route?Are they gonna run next to each other or am i missing something?
__________________
......guess who's coming to dinner..... |
|
|
|
|
|
#15 | |
|
Registered User
Join Date: Jul 2004
Posts: 4,015
Likes (Received): 7
|
Quote:
![]() Last thing you wanna see is a latest state-of-the-art multi billion $$$ 8-laned expressway fully flooded in moonsoon rains throughout the state.
|
|
|
|
|
|
|
#16 |
|
Registered User
Join Date: Sep 2008
Posts: 49
Likes (Received): 0
|
Post-Singur: expressway developer takes steps to avoid land row
Fri, Sep 5 02:11 AM A Singur in Uttar Pradesh? No way, says Samir Gaur, director of Jaypee Group, which won the development rights for the Rs 40,000 crore, 1047-km Ganga Expressway that would traverse from Ballia on the eastern fringes of the state to the national capital region in Greater Noida. With the group kicking off its land acquisition plans by submitting its proposal to acquire land from 17 villages of Bukandshahr in its first package to the UP Expressway Industrial Development Authority, the ball has set rolling for the highly ambitious project. It may be mentioned that a staggering 30,000 acres of land has to be acquired along 17 districts. The alignment plan for the project has been finalised and given in-principle approval by the government after roadblocks regarding the alignment at Narora and Varanasi were cleared. While the alignment in Narora had to be shifted slightly due to the Narora atomic power station as well as a dolphin sanctuary, a turtle sanctuary near Benaras was the reason why the alignment had to be changed before being approved by the state government. What would be a balm on the shaky morale of India Inc, Gaur said that he did not foresee a Singur-like impasse happening in Uttar Pradesh. "Already, we have 70 survey teams on the ground, preparing a detailed project report and our nodal offices in all the 17 districts are working round the clock on the designing aspect. Once the government clears our proposal, we will start acquiring land and also make sure that we do not have any situation of strife here, for we have always striven to take everyone along with us. We would make sure that we convince the peasants of the benefits of the projects and explain to them the way development can change life for the better for them, too." When asked what could be the solution to growing opposition of farmers, which is acting as a severe deterrent to industrialisation in the country, Gaur was of the opinion that the farmer must be made comfortable and taken along on the path of development. "Land is definitely a scarce commodity and the only way to ensure food security for the farmers. Hence, all efforts must be made to give him a good price for his piece of land." On the issue of coming out with more innovative compensation packages like employment, partnerships and shareholding, Gaur seemed open to it and said the company is keenly studying on all the other patterns of compensation that could be offered to the land owners. "We would follow the Central government's resettlement and rehabilitation policy and do all that is possible for the displaced farmers," he added. Simultaneous to the process of acquiring land, the company is also in talks with many national and international construction firms for the construction of the four packages that the project comprises of. The project has been divided into four individual packages of road sections. It may be mentioned that the state government has an ambitious plan to develop the Expressway as the industrial development corridor of the state. "The Ganga Expressway project will not only be a highway, but would provide us with ample space and opportunity for developing SEZs along its 1,047 km stretch," said a senior government official. |
|
|
|
|
|
#17 |
|
Registered User
Join Date: Aug 2007
Posts: 8,468
|
This is a big dream. In order to complete 1047 km stretch, they will have to dream big and get all the things cleared first- environmental clearances, slum areas and things like that.
|
|
|
|
|
|
#18 |
|
unregistered
Join Date: Dec 2004
Posts: 2,578
Likes (Received): 1
|
my geographies just not good enough.looks like there right on top of each other.
cant get enough roads. . .
__________________
......guess who's coming to dinner..... |
|
|
|
|
|
#19 | |
|
Registered User
Join Date: Jun 2008
Posts: 204
Likes (Received): 0
|
Quote:
And yes, I agree that Bihar should find the will to extend this through their state as well. Of course, the recent flooding was due to the Kosi changing its alignment, so a Ganga levy would not have helped at all. |
|
|
|
|
|
|
#20 |
|
Registered User
Join Date: Jun 2008
Posts: 258
Likes (Received): 0
|
Mulayam goes hard on terror
Here is the latest update of on ganga expressway what Samajwadi Party supremo and former Uttar Pradesh Chief Minister, Mulayam Singh Yadav today said
Source : http://www.saharasamay.com |
|
|
|
![]() |