Old November 23rd, 2009, 09:23 PM   #1
IU
->
 
IU's Avatar
 
Join Date: Apr 2006
Location: Hanooz Dilli dur ast
Posts: 10,492

Mumbai Airport| Metros| Monorail| Suburban Railway| Sealinks| Supertalls

For a list of Projects u/c in Mumbai and their estimated deadlines, please see the post below this one.

The Mumbai Airport, Metro, Monorail, Suburban Railway, Bandra Worli Sealink, Worli-Haji Ali sealink and the Mumbai Trans-Harbour Bridge projects have separate threads in the Infrastructure and Transportation forums. Here are the links -


Mumbai International Airport thread
http://www.skyscrapercity.com/showthread.php?t=347144


Navi Mumbai International Airport thread
http://www.skyscrapercity.com/showthread.php?t=481410

________

Mumbai Metro Updates!
http://www.skyscrapercity.com/showthread.php?t=451426


Navi Mumbai Metro Updates
http://www.skyscrapercity.com/showthread.php?t=1112765


Mumbai Monorail Project
http://www.skyscrapercity.com/showthread.php?t=608834


Mumbai Railway Discussions: Projects and Updates
http://www.skyscrapercity.com/showthread.php?t=719938

________

Bandra-Worli Sealink thread
http://www.skyscrapercity.com/showthread.php?t=612663


Worli-Haji Ali Sea Link Thread
http://www.skyscrapercity.com/showthread.php?t=908686


Mumbai Trans-Harbour Bridge : Nhava-Sewri Sea Link
http://www.skyscrapercity.com/showthread.php?t=612688

______________________
Supertalls

MARINE LINES | India Tower | 500+ m | 125 fl



LOWER PAREL | World One | 442 m | 117 fl | APP




WORLI | Palais Royale | 67 fl | 320m



JACOB CIRCLE | Orchid Heights | 300m | 80 fl x 2



PRABHADEVI | Orchid Crown | 3 x 75-80fl | 300+ m



TARDEO | Shreepati Skies | 301 m | 88 fl | App
__________________

KuwarOnline, skysun liked this post

Last edited by IU; January 25th, 2013 at 06:35 PM.
IU no está en línea  

Sponsored Links
 
Old January 21st, 2013, 08:07 AM   #2
devendra1
Registered User
 
Join Date: Apr 2010
Location: Pune/Mumbai
Posts: 1,268
Likes (Received): 145

My thoughts in bold. I am not mentioning the deadlines given by MMRDA but what I think when these projects complete.
Quote:
Originally Posted by gyrations95 View Post
Mumbai Metro I (Versova-Andheri-Ghatkopar corridor) - Dec 2013 Mar 2014
Monorail (Chembur - Wadala) - June 2013 around Diwali 2013
Monorail (Wadala - Gadge Maharaj Chowk) - Dec 2014 ?? No idea here. But may go in 2015

Navi Mumbai Metro Line 1 Phase 1 - Dec 2014 Currently deadline is may 2015. May get over around Diwali 2015

Mumbai International Airport New Terminal (SW Pier?) - Dec 2013 ?? No idea Here.
Navi Mumbai International Airport - start Dec 2013 end Dec 2018 Cant say anything until construction starts.


SEAR - Dec 2013??
Eastern Expressway - Feb/Mar 2013 and June 2013 (opened in phases) No idea Here.

Sion Panvel Expressway - June 2014 (may be delayed to Dec 2014)
SCRL - Dec 2013?? Mid 2014
Milan Subway - June 2013 ??
Jogeshwari ROB - June 2013 ??
Oshiwara ROB - June 2013 ??
Thane - Majiwada Flyover - April/May 2013
Thane - Kaburbawadi Flyover - Dec 2013


5th/6th line between Diva-Thane - Dec 2015?? (Kalyan-Diva and Thane-Kurla are already 6 lined) . Thane bridge is well u/c . I don't think this will take that long.

Nerul-Seawoods-Uran railway line - Dec 2014
6th line between MUmbai Central-Borivali - Dec 2015
Escalators on major stations on CR (Thane, Dombivli, Kalyan, Kurla, Dadar) and WR (Borivali, what else) - June/Dec 2013?? Lets wait till they actually start construction.



Not started yet
---------------
Mumbai Metro III (SEEPZ - Nariman Point) - Start Dec 2013 end Dec 2018?? . AFAIK the date was Aug 2013 but we have not yet seen any movement on tenders for construction. Even though tenders are awarded this year. I think Construction will start only next year. End date will be around 2021



Peddar Road Flyover - ??
WR elevated corridor (Churchgate-Virar) - Start Dec 2013 end Dec 2018?? . Less chance of actual construction starting this year. Probably next year.

Vasai-Virar-Panvel corridor - Not approved
Mumbai Trans-Harbour Link (Sewri-Nhava) - Start Dec 2013 end Dec 2018??

fuwad and CG, do you know when Jogeshwari and Oshiwara ROBs are expected to be completed?

I am adding following

Line 2 of Metro - Start date 2015/2016 ?? If they do something in these 2 to 3 years.

Other Phases of Metro - Start date 2022 or even further as the first phase itself will not be done before that. I wish given the delay already happened. They start constructing both Phase 1 and Phase 2 lines simultaneously. Phase 3 can be done afterwards. Need to plan metro N/W till Kalyan Incase similar elevated corridor with A/C trains is not constructed for central line.

.
__________________

Indtrans liked this post
devendra1 no está en línea  


Closed Thread

Thread Tools

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off



All times are GMT +2. The time now is 03:29 AM.


Powered by vBulletin® Version 3.8.8 Beta 1
Copyright ©2000 - 2014, vBulletin Solutions, Inc.
Feedback Buttons provided by Advanced Post Thanks / Like v3.2.5 (Pro) - vBulletin Mods & Addons Copyright © 2014 DragonByte Technologies Ltd.

vBulletin Optimisation provided by vB Optimise (Pro) - vBulletin Mods & Addons Copyright © 2014 DragonByte Technologies Ltd.

SkyscraperCity ☆ In Urbanity We trust ☆ about us | privacy policy | DMCA policy

Hosted by Blacksun, dedicated to this site too!
Forum server management by DaiTengu