Old January 11th, 2012, 12:18 AM   #521
The-King
Registered User
 
Join Date: Mar 2008
Location: Pliezhausen
Posts: 2,342
Likes (Received): 10

Construction Update

02/01/2012
very good progress! this area is gonna be awesome when all these towers are done!
image hosted on flickr

Source: http://www.flickr.com/photos/arminro...57628731865279
High-Res: http://www.flickr.com/photos/arminro...7628731865279/
The-King no está en línea   Reply With Quote

Sponsored Links
 
Old January 21st, 2012, 12:33 PM   #522
SkyscraperCity man
Registered User
 
SkyscraperCity man's Avatar
 
Join Date: Jul 2008
Posts: 391
Likes (Received): 0

21-Jan-12








Last edited by SkyscraperCity man; January 21st, 2012 at 07:34 PM.
SkyscraperCity man no está en línea   Reply With Quote
Old February 4th, 2012, 12:46 PM   #523
Imre
Dubai
 
Imre's Avatar
 
Join Date: Jan 2005
Location: Dubai
Posts: 41,364
Likes (Received): 25

4/February/2012

29 BD Boulevard













Imre no está en línea   Reply With Quote
Old February 4th, 2012, 05:39 PM   #524
Burj Khalifa fan
Photographer
 
Burj Khalifa fan's Avatar
 
Join Date: Sep 2011
Location: Abu Dhabi
Posts: 892
Likes (Received): 15

they must make the name

29 bk Boulevard
Burj Khalifa fan no está en línea   Reply With Quote
Old February 6th, 2012, 04:31 PM   #525
gerald.d
Registered User
 
gerald.d's Avatar
 
Join Date: May 2008
Location: Dubai
Posts: 2,459
Likes (Received): 28

Dubai Marathon gigapixel pano (if you or your friends were there, feel free to tag yourselves!)



http://08.ae/panos/marathon/starttag/Fullsize.html
gerald.d no está en línea   Reply With Quote
Old February 23rd, 2012, 12:30 PM   #526
The-King
Registered User
 
Join Date: Mar 2008
Location: Pliezhausen
Posts: 2,342
Likes (Received): 10

Construction Update

12/02/2012

http://www.flickr.com/photos/vandenb...n/photostream/
The-King no está en línea   Reply With Quote
Old March 16th, 2012, 03:03 PM   #527
Imre
Dubai
 
Imre's Avatar
 
Join Date: Jan 2005
Location: Dubai
Posts: 41,364
Likes (Received): 25

16/March/2012

29 BD Boulevard









Imre no está en línea   Reply With Quote
Old April 13th, 2012, 12:07 PM   #528
Imre
Dubai
 
Imre's Avatar
 
Join Date: Jan 2005
Location: Dubai
Posts: 41,364
Likes (Received): 25

13/April/2012

29 BD Boulevard





Imre no está en línea   Reply With Quote
Old April 13th, 2012, 12:17 PM   #529
Imre
Dubai
 
Imre's Avatar
 
Join Date: Jan 2005
Location: Dubai
Posts: 41,364
Likes (Received): 25

Duplicate post
Imre no está en línea   Reply With Quote
Old May 14th, 2012, 06:13 PM   #530
Berliner01
Registered User
 
Join Date: Apr 2012
Posts: 382
Likes (Received): 31



Berliner01 no está en línea   Reply With Quote
Old May 15th, 2012, 01:23 PM   #531
Old Town Resident
Sunny Intervals.
 
Old Town Resident's Avatar
 
Join Date: Jun 2007
Location: Dubai
Posts: 2,381
Likes (Received): 29

Quote:
Originally Posted by Burj Khalifa fan View Post
they must make the name

29 bk Boulevard
Its name is Emaar Boulevard. Renamed way back.
Old Town Resident no está en línea   Reply With Quote
Old May 16th, 2012, 07:26 AM   #532
italiano_pellicano
BANNED
 
Join Date: Feb 2010
Location: Los Angeles , US / Cancun , MX
Posts: 18,011
Likes (Received): 631

wow amazing , commercial places in this area ?
italiano_pellicano no está en línea   Reply With Quote
Old May 16th, 2012, 11:23 AM   #533
Old Town Resident
Sunny Intervals.
 
Old Town Resident's Avatar
 
Join Date: Jun 2007
Location: Dubai
Posts: 2,381
Likes (Received): 29

Quote:
Originally Posted by italiano_pellicano View Post
wow amazing , commercial places in this area ?

Like the others most will be empty long after they open.

Souq Al Bahar 90* unoccupied shop units.

Qamardeen Souq 99% have moved out after being 10% occupied with only the laundry remaining.

Al Manzil Souq: 50% empty.

Is it high rent from Emaar?
Old Town Resident no está en línea   Reply With Quote
Old May 25th, 2012, 02:27 PM   #534
Imre
Dubai
 
Imre's Avatar
 
Join Date: Jan 2005
Location: Dubai
Posts: 41,364
Likes (Received): 25

25/May/2012

29 BD Boulevard





Imre no está en línea   Reply With Quote
Old May 29th, 2012, 07:06 AM   #535
googly
Where is the next Dubai?
 
googly's Avatar
 
Join Date: Mar 2007
Posts: 512
Likes (Received): 0

thanks imre. How many floors have been made so far and how long will it take to top off?
googly no está en línea   Reply With Quote
Old May 29th, 2012, 08:32 AM   #536
Berliner01
Registered User
 
Join Date: Apr 2012
Posts: 382
Likes (Received): 31

From the concept it looks like the towers just reached half of the total hight. So I would guess one or two years still to come.
Berliner01 no está en línea   Reply With Quote
Old May 31st, 2012, 06:51 AM   #537
doomsdayarmy
Registered User
 
doomsdayarmy's Avatar
 
Join Date: Sep 2011
Posts: 52
Likes (Received): 0

Berliner, you are wrong. The building consist of 45 floors. I counted at least 37-39 floors from the last pictures. Remember the villas/stores in the back or front of the building are deceiving, meaning, you don't get the full perspective. The building will be done and ready for handover, the first quarter of next year, if not sooner. If Emaar goes beyond the first quarter of next year, they will have to pay another set of penalties to the purchasers . Most everyone has already received a percentage for the delays or deducted from the balance due. I doubt if Emaar would be delaying this project any further. God willing, we will have our apartments ready for handover latest, by march of 2013.
doomsdayarmy no está en línea   Reply With Quote
Old June 15th, 2012, 05:24 PM   #538
Berliner01
Registered User
 
Join Date: Apr 2012
Posts: 382
Likes (Received): 31

I dont see much progress here:

Berliner01 no está en línea   Reply With Quote
Old June 19th, 2012, 04:57 AM   #539
doomsdayarmy
Registered User
 
doomsdayarmy's Avatar
 
Join Date: Sep 2011
Posts: 52
Likes (Received): 0

I'm in Dubai and went by the job site offices(across the street from the actual building on Emaar Blvd.) and Emaar Square(building 2) where the handover offices and customer services are located. Last Friday, I went by the job site and tried convincing the security guard to be able to take the service elevator to my floors to see what the progress is like, check out the view and the floor plan. Well, the security guard wouldn't go for it. On Monday, went to the job site offices and spoke to the contractor in charge and asked him if he can arrange the viewing. The answer was absolutely NOT!!! We talked about 15-20 minutes and he informed me that the Tower-1 is slightly taller than Tower-2 (3-4 floors) and by the end of the year the building will be done. According to him they are only 7-8 floors remaining. The handover time will be the 3rd to 4th month in 2013. This is because it takes Dewa and the municipality three months or so to finalize the building for electricity, water etc....God willing and no further delays and no unforeseen events, we should be able to have our apartments soon.
doomsdayarmy no está en línea   Reply With Quote
Old June 19th, 2012, 11:14 AM   #540
MichalHajek
Registered User
 
Join Date: Jul 2011
Location: Bratislava & Dubai
Posts: 125
Likes (Received): 2

how can you be surprised they didnt allow you to the building under construction... that is the law, rules and security procedures, all over the world...
MichalHajek no está en línea   Reply With Quote


Reply

Tags
downtown dubai, uae

Thread Tools
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off



All times are GMT +2. The time now is 07:49 PM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2013, vBulletin Solutions, Inc.
Feedback Buttons provided by Advanced Post Thanks / Like v3.1.2 (Pro) - vBulletin Mods & Addons Copyright © 2013 DragonByte Technologies Ltd.
vBulletin Optimisation provided by vB Optimise (Pro) - vBulletin Mods & Addons Copyright © 2013 DragonByte Technologies Ltd. (Resources saved on this page: MySQL 20.00%)

SkyscraperCity - In Urbanity We Trust

Hosted by Blacksun, dedicated to this site too!
Forum server management by DaiTengu