Originally Posted by mangalore mania View Post

Some time back we have seen here a part of Gazette Notification for land acquisition and I have read the whole in TOI..
I think NHAI is moving quietly without much fanfare to avoid untoward opposition from environmentalist..

This is just land acquisition, we may see tenders to be called soon once the land is marked and acquired completely..
Yes exactly MM,this was done quietly and I wish the tenders are called soon.
In the report above posted by you it is mentioned as the land acquisition may go til the end of this year.
Can the construction work start while the land is in acquisition simultaneously or it should wait until the acquisition is over??
__________________
Mangalore-A beautiful city on the west coast and a thriving commercial hub.
Suj Mangalore no está en línea   Reply With Quote

Sponsored Links
 
Old Yesterday, 05:49 PM   #2042
Suj Mangalore
Registered User
 
Join Date: May 2011
Location: Bangalore
Posts: 1,455
Likes (Received): 108

Quote:
Originally Posted by rsrikanth05 View Post
I doubt it'll be an expressway, but a dual carriageway is badly needed.
I hope it is given to someone reputed like L&T or SPG.
Expressway probably not
But it will be a kind of that when completed I am sure.
I was just thinking that NHAI will go ahead with tunnels in Shiradi Ghat and that would have cut short some distance and there by minimized environmental damage
I hope a reputed company like L&T executes this
__________________
Mangalore-A beautiful city on the west coast and a thriving commercial hub.
Suj Mangalore no está en línea   Reply With Quote
Old Yesterday, 05:59 PM   #2043
rsrikanth05
Ladkiyon ka Hero
 
rsrikanth05's Avatar
 
Join Date: Mar 2009
Location: Kovai
Posts: 6,079
Likes (Received): 70

Quote:
Originally Posted by Suj Mangalore View Post
Yes exactly MM,this was done quietly and I wish the tenders are called soon.
In the report above posted by you it is mentioned as the land acquisition may go til the end of this year.
Can the construction work start while the land is in acquisition simultaneously or it should wait until the acquisition is over??
Better to have all the land in hand before starting.
Simultaneous LA has screwed up major projects like the Avinashi-Coimbatore projects where certain people haven't given land thus delaying indefinitely.
Quote:
Originally Posted by Suj Mangalore View Post
Expressway probably not
But it will be a kind of that when completed I am sure.
I was just thinking that NHAI will go ahead with tunnels in Shiradi Ghat and that would have cut short some distance and there by minimized environmental damage
I hope a reputed company like L&T executes this
They will have to tunnel if they are going to make it four lanes or six.
rsrikanth05 no está en línea   Reply With Quote
Old Yesterday, 06:09 PM   #2044
Suj Mangalore
Registered User
 
Join Date: May 2011
Location: Bangalore
Posts: 1,455
Likes (Received): 108

Quote:
Originally Posted by rsrikanth05 View Post
Better to have all the land in hand before starting.
Simultaneous LA has screwed up major projects like the Avinashi-Coimbatore projects where certain people haven't given land thus delaying indefinitely.


They will have to tunnel if they are going to make it four lanes or six.
Hope LA goes smoothly and work begins soon.
I think the tunneling is ruled out and they are going for four or six lane concrete road in Shiradi.
__________________
Mangalore-A beautiful city on the west coast and a thriving commercial hub.
Suj Mangalore no está en línea   Reply With Quote
Old Yesterday, 06:14 PM   #2045
rsrikanth05
Ladkiyon ka Hero
 
rsrikanth05's Avatar
 
Join Date: Mar 2009
Location: Kovai
Posts: 6,079
Likes (Received): 70

Quote:
Originally Posted by Suj Mangalore View Post
Hope LA goes smoothly and work begins soon.
I think the tunneling is ruled out and they are going for four or six lane concrete road in Shiradi.
It's the western ghats boss.
You'll have to tunnel somewhere.
NHAI and MSRDC tunneled in less hilly areas like Pune-Kolhapur, this is more hilly than Mumbai Pune.
rsrikanth05 no está en línea   Reply With Quote


Reply

Tags
karnataka, karnataka highways

Thread Tools
Display Modes Rate This Thread
Rate This Thread:

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off



All times are GMT +2. The time now is 12:24 AM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2013, vBulletin Solutions, Inc.
Feedback Buttons provided by Advanced Post Thanks / Like v3.1.2 (Pro) - vBulletin Mods & Addons Copyright © 2013 DragonByte Technologies Ltd.
vBulletin Optimisation provided by vB Optimise (Pro) - vBulletin Mods & Addons Copyright © 2013 DragonByte Technologies Ltd. (Resources saved on this page: MySQL 21.43%)

SkyscraperCity - In Urbanity We Trust

Hosted by Blacksun, dedicated to this site too!
Forum server management by DaiTengu