Indian Railways' projects in Tamil Nadu

With several railway projects under various stages of construction in Tamil Nadu (and many more on the anvil), a dedicated thread would serve the purpose in a better way.

Please post all railway-related projects in Tamil Nadu in this thread.

Last edited by Rasnaboy; December 18th, 2008 at 05:26 PM. Reason: Better Title
Rasnaboy no está en línea   Reply With Quote

Sponsored Links
 
Old December 15th, 2008, 01:19 PM   #2
Rasnaboy
I love you Rasna!!
 
Join Date: Apr 2008
Location: Chennai
Posts: 2,128
Likes (Received): 3

Velu inspects railway bridge across the Kollidam

Estimate was revised to Rs. 270 crore owing to cost overruns, natural factors

CUDDALORE:The recent spell of rain has hampered the execution of railway projects, particularly the railway bridges across rivers, said R. Velu, Union Minister of State for Railways.

After inspecting the progress of works on the railway bridge across the Kollidam near Chidambaram on Sunday, Mr. Velu told reporters that the project was originally estimated to cost Rs. 181.82 crore.

But owing to cost overruns and disruption by natural factors, the estimate had been revised to Rs. 270 crore. Mr. Velu said that the survey for starting a train service from Cuddalore to Chennai, via Puducherry and Mahabalipuram, was under way.

The proposal for constructing a subway on Lawrence Road in Cuddalore was awaiting administrative sanction. As regards the Chidambaram flyover, Mr. Velu said the Railways had completed its work and it was for the Highways Department to take up its share of work.

Electrification of the Tiruchi-Chennai sector would be completed by January 15 and the process was under way on the Tiruchi-Madurai stretch.

Gauge conversion works on the Madurai-Tuticorin and Tuticorin-Maniyatchi sectors, taken up at the cost of Rs. 120 crore, was under progress. Services between Vellore and Chennai, and, Chennai and Kancheepuram would begin by December 21.

Within one-and-half years, electric trains linking Kanyakumari to Kolkata, Delhi and Jammu Tawi would be introduced, Mr. Velu said.

At Vikkiravandi near Villupuram, he inaugurated a station building and introduced a halt for the Chennai Egmore-Puducherry-Chennai Egmore train.

Mr. Velu had instructed Divisional Railway Manager Kulsreshtha to examine the feasibility of setting up a goods-shed and improving the platforms at the Vikkiravandi station to tap the potential of about 30 rice mills and considerable number of cotton mills in the vicinity.

K. Dhanraj, MP, said that setting up a goods-shed would help to stack agricultural produce which, in turn, would give a thrust to farm business in the region.

Source: http://www.hindu.com/2008/12/15/stor...1553020300.htm
Rasnaboy no está en línea   Reply With Quote
Old December 15th, 2008, 03:22 PM   #3
Arul Murugan
Registered User
 
Join Date: Jun 2006
Location: Salem-Chennai
Posts: 13,758
Likes (Received): 2188

Good start.

But the thread topic can be:

Indian railways - Projects in Tamilnadu!! If possible please edit it.

Title is mis-leading.
__________________
Click on---->



அருள் முருகன்
தமிழ்நாடு/இந்தியா
Arul Murugan no está en línea   Reply With Quote
Old December 15th, 2008, 04:52 PM   #4
kg4129
Registered User
 
Join Date: Jul 2007
Posts: 5,115
Likes (Received): 1029

Sounds good...
kg4129 no está en línea   Reply With Quote
Old December 16th, 2008, 12:03 AM   #5
Arul Murugan
Registered User
 
Join Date: Jun 2006
Location: Salem-Chennai
Posts: 13,758
Likes (Received): 2188

Tiruvarur-Nagore train service by month-end: officials

Special Correspondent

Commissioner of Railway Safety to inspect section in third week of December

NAGAPATTINAM: Trains might soon start running in the Tiruvarur-Nagore section after a prolonged delay, which postponed the opening of the line for the last couple of years.

Officials said that the Commissioner of Railway Safety was scheduled to inspect the section in the third week of December.

Work on the 31-km stretch between Tiruvarur and Nagore had started in 2006 itself and the project cost was estimated at Rs.34 crore then. This was part of the link between Tiruchi and Karaikal, with the Tiruchi-Thanjavur and Thanjavur-Tiruvarur sections already complete.

This section, along with the proposed work to Karaikal, and the extension to Velankanni, would help a lot of commuters to the pilgrim centres of Velankanni, Nagore and Karaikal, and also the Karaikal Port, which is getting ready.

However, there was a delay, owing to various reasons, and although there had been trial runs even in April of this year, trains were yet to start plying. At an inspection of the Kollidam railway bridge on Sunday, R. Velu, Minister of State for Railways, had assured that trains would be on the tracks by the end of December.

When contacted, railways officials told The Hindu that the inspection by the CRS was scheduled for the third week of December, and if things went according to the plan, trains would indeed start running by December-end. Officials also confirmed that the Kollidam railway bridge was nearing completion with only girders left to be built, and soon the Sirkazhi-Chidambaram line might also be opened for traffic.

http://www.hindu.com/2008/12/16/stor...1656900300.htm
__________________
Click on---->



அருள் முருகன்
தமிழ்நாடு/இந்தியா
Arul Murugan no está en línea   Reply With Quote
Old December 16th, 2008, 12:05 AM   #6
Arul Murugan
Registered User
 
Join Date: Jun 2006
Location: Salem-Chennai
Posts: 13,758
Likes (Received): 2188

SALEM: The Southern Railway has asked the people to exercise extra caution while crossing the unmanned level crossings and tracks in the Erode-Karur-Tiruchi section on December 17 as it has planned to conduct a speed trial.

The Principal Chief Engineer will conduct a speed trial at 125 kmph by a special train using Oscillation Monitoring System (OMS car) on the day. The special train will leave Erode at 9.45 a.m. and reach Tiruchirapalli at 11.15 a.m., a press release said. The speed trial is planned to increase the sectional speed of trains to 110 kmph between Erode Tiruchirappalli. Currently, the trains in the section run at a speed of 100 kmph.

http://www.hindu.com/2008/12/16/stor...1651990300.htm
__________________
Click on---->



அருள் முருகன்
தமிழ்நாடு/இந்தியா
Arul Murugan no está en línea   Reply With Quote
Old December 16th, 2008, 07:37 AM   #7
karthick80
Trichian
 
karthick80's Avatar
 
Join Date: Jul 2008
Location: Trichy, Singapore
Posts: 268
Likes (Received): 0

deleted as it is a repeated posting

Last edited by karthick80; December 17th, 2008 at 09:52 AM. Reason: Deleted as its a repeated posting
karthick80 no está en línea   Reply With Quote
Old December 17th, 2008, 09:08 AM   #8
Arul Murugan
Registered User
 
Join Date: Jun 2006
Location: Salem-Chennai
Posts: 13,758
Likes (Received): 2188



Karthick,before posting the news please check whether it is posted before!!

Your posts are repeated one in many threads.
__________________
Click on---->



அருள் முருகன்
தமிழ்நாடு/இந்தியா
Arul Murugan no está en línea   Reply With Quote
Old December 17th, 2008, 09:44 AM   #9
karthick80
Trichian
 
karthick80's Avatar
 
Join Date: Jul 2008
Location: Trichy, Singapore
Posts: 268
Likes (Received): 0

Quote:
Originally Posted by Arul Murugan View Post


Karthick,before posting the news please check whether it is posted before!!

Your posts are repeated one in many threads.

sorry, hereafter i will check properly before posting.
__________________
karthick
karthick80 no está en línea   Reply With Quote
Old December 18th, 2008, 04:41 PM   #10
Rasnaboy
I love you Rasna!!
 
Join Date: Apr 2008
Location: Chennai
Posts: 2,128
Likes (Received): 3

Quote:
Originally Posted by Arul Murugan View Post
Good start.

But the thread topic can be:

Indian railways - Projects in Tamilnadu!! If possible please edit it.

Title is mis-leading.
Thanks for the suggestion Arul!

But can you tell me how to do that? I tried, but I'm not able to change the thread name but only the titles of my posts.
Rasnaboy no está en línea   Reply With Quote
Old December 18th, 2008, 05:20 PM   #11
Rasnaboy
I love you Rasna!!
 
Join Date: Apr 2008
Location: Chennai
Posts: 2,128
Likes (Received): 3

High-speed trial conducted on the BG section from Erode to Tiruchi

A special train left Erode at 9.45 a.m. and arrived at Tiruchi Junction at 11.10 a.m.


Testing time: A special train, which was used to conduct a high speed trial from Erode to Tiruchi, entering the Tiruchi Junction on Wednesday.

TIRUCHI: A high speed trial was conducted on the broad gauge section from Erode to Tiruchi on Wednesday towards increasing the sectional speed of trains to 110 kilometres per hour.

Principal Chief Engineer, Southern Railway, G. Narayanan conducted the trial in a special train using the Oscillation Monitoring System between Erode and Tiruchi via Karur, covering a total distance of 141 km.

Dr. Narayanan was accompanied by the Senior Divisional Engineer (Coordination) R. Nandakumar and A. Rajkumar Divisional Engineer – both of the Salem Railway Division.

To ensure uninterrupted running of the speed trial special, the authorities had closed the manned level crossing gates well in advance and deputed their staff at unmanned level crossings on the Erode – Tiruchi section.

The special train which left Erode at 9.45 a.m. arrived at Tiruchi Junction at 11.10 a.m. where senior railway officials received the Principal Chief Engineer.

There are 22 railway stations and 74 level crossings including 22 unmanned gates between Erode and Tiruchi Junction.

Speaking to the The Hindu upon his arrival here, Mr. Narayanan said the trial was conducted at 130 kilometres per hour and that “all riding parameters were okay”.

Expressing satisfaction over the track improvement works carried out by the Salem Railway Division officials, Mr. Narayanan said he would make his recommendations based on the trial. The sectional speed had been increased in several sections in Southern Railway limits, he added.

A senior railway official of the Salem Division said the track improvement works were completed within three months to enable the high speed trial.

At present, trains are operated between Erode and Tiruchi Fort at a maximum speed of 100 kilometres per hour.

Source: http://www.hindu.com/2008/12/18/stor...1856530400.htm
Rasnaboy no está en línea   Reply With Quote
Old December 19th, 2008, 02:04 AM   #12
Rasnaboy
I love you Rasna!!
 
Join Date: Apr 2008
Location: Chennai
Posts: 2,128
Likes (Received): 3

CRS begins inspection of Tiruvarur-Nagore BG line


Fitness study: K.J.S. Naidu, Commissioner of Railway Safety, inspecting the Tiruvarur-Nagore broad gauge line on Thursday.

TIRUVARUR: Rail traffic on the broad gauge track between Tiruvarur and Nagore is expected to resume soon with the Commissioner of Railway (CRS) K.J.S. Naidu commencing his two-day inspection on the section on Thursday following the completion of the gauge conversion.

Accompanied by the Chief Administrative Officer (Constructions), Southern Railway R. Ramanathan, Chief Engineer (Constructions) Rajesh Argal, Chief Signal and Telecommunication Engineer B.N. Moorthy, Divisional Railway Manager S. Subramhanyan and other senior officials, Mr. Naidu inspected the track in a motor trolley from Tiruvarur to Nagore, covering a total distance of 31 km.

The CRS will conduct a speed trial in a special train on Friday from Nagore to Tiruvarur, which has eight stations including three crossing stations. Rail traffic, which had been suspended in this section to enable conversion work, will resume once the CRS gives his certification.

The project, sanctioned at a cost of Rs.65 crore, commenced in April 2007. The work included construction of two major bridges and 88 minor bridges. The section has total of 25 level crossings, including 17 manned gates.

The Tiruvarur - Nagore gauge conversion is part of the Tiruchi – Karaikal GC work, covering a total distance of 200 km, which was sanctioned by the Railway Board as early as in 1995-96.

Source: http://www.hindu.com/2008/12/19/stor...1957220300.htm
Rasnaboy no está en línea   Reply With Quote
Old December 20th, 2008, 04:33 AM   #13
Rasnaboy
I love you Rasna!!
 
Join Date: Apr 2008
Location: Chennai
Posts: 2,128
Likes (Received): 3

Rail overbridge inspected

TUTICORIN: Vellakoil M. P. Swaminathan, Minister for Highways, on Friday inspected the rail over bridge that is being constructed at an estimated cost of Rs. 13 crore here. Speaking to mediapersons, he said that the bridge would be completed by April. He said 9,284 kilometres of roads had been affected by the rain. Repair work had been completed in 155 places, he added. Road repair work in flood-affected areas had been taken up at a cost of Rs. 134 crore, the Minister said.

Source: http://www.hindu.com/2008/12/20/stor...2052410800.htm
Rasnaboy no está en línea   Reply With Quote
Old December 20th, 2008, 05:43 AM   #14
Arul Murugan
Registered User
 
Join Date: Jun 2006
Location: Salem-Chennai
Posts: 13,758
Likes (Received): 2188

Rasnaboy,

I think we should approach mods.
__________________
Click on---->



அருள் முருகன்
தமிழ்நாடு/இந்தியா
Arul Murugan no está en línea   Reply With Quote
Old December 20th, 2008, 07:03 AM   #15
sudheeshnairs
Registered User
 
sudheeshnairs's Avatar
 
Join Date: Jun 2005
Location: Trivandrum/Bangalore
Posts: 9,139
Likes (Received): 16

Done
sudheeshnairs no está en línea   Reply With Quote
Old December 20th, 2008, 10:42 AM   #16
kg4129
Registered User
 
Join Date: Jul 2007
Posts: 5,115
Likes (Received): 1029

Thx sudheesh...

Likewise it would be appropriate to change " New Tiruchi Airport-Code VOTR" as " Trichy Airport Developments"

http://www.skyscrapercity.com/forumdisplay.php?f=1249

http://www.skyscrapercity.com/showth...=733972&page=2

Last edited by kg4129; December 20th, 2008 at 10:55 AM.
kg4129 no está en línea   Reply With Quote
Old December 20th, 2008, 12:59 PM   #17
Arul Murugan
Registered User
 
Join Date: Jun 2006
Location: Salem-Chennai
Posts: 13,758
Likes (Received): 2188

Thanks Sudheesh

------------------------------------------

BG train service to Nagore shortly

Speed trial held at 100-120 km per hour


TIRUVARUR: Train services are likely to start on the broad gauge section between Tiruvarur and Nagore in a fortnight.

“There are some minor defects in the track. They will be set right,” said K.J.S. Naidu, Commissioner of Railway Safety, here on Friday, after concluding a speed trial in a special train from Nagore to Tiruvarur. The train was operated at 100 to 120 km per hour speed.

R. Ramanathan, Chief Administrative Officer (Construction), who accompanied Mr. Naidu said that train service in the link between Nagapattinam and Velankanni may start from March.

The line is being laid at a cost of Rs.45 crore. In the Mayiladuthurai-Villupuram section, gauge conversion works are expected to be completed by June.

The section between Mayiladuthurai and Tiruvarur would be made broad gauge at Rs.130 crore and the work would start in March, Ramanathan said. S. Subramhanyan, DRM, Tiruchi, also accompanied the officials.

http://www.hindu.com/2008/12/20/stor...2055771100.htm
__________________
Click on---->



அருள் முருகன்
தமிழ்நாடு/இந்தியா

Last edited by Arul Murugan; December 20th, 2008 at 01:18 PM.
Arul Murugan no está en línea   Reply With Quote
Old December 21st, 2008, 05:08 AM   #18
Rasnaboy
I love you Rasna!!
 
Join Date: Apr 2008
Location: Chennai
Posts: 2,128
Likes (Received): 3

Thanks Sudheesh and Arul!
Rasnaboy no está en línea   Reply With Quote
Old December 22nd, 2008, 03:01 AM   #19
Arul Murugan
Registered User
 
Join Date: Jun 2006
Location: Salem-Chennai
Posts: 13,758
Likes (Received): 2188

Speed of trains increased

CHENNAI: Southern Railway has increased the speed of all mail/express trains on the Erode-Karur-Tiruchi Fort section to 110 km an hour. Earlier, in April speeds of 52 pairs of mail/express trains were increased to 110 kmph on another section of the zone. So far, the speed of 88 pairs of mail/express trains had been increased in the zone.

Permissible speed on recently converted sections have also been increased. They are: Thanjavur- Mayiladuthurai section (60 to 90 kmph), Vriddhachalam-Salem Market section (70 to 80 kmph), and Vanchi Maniyachchi to Tuticorin section (90 to 100 kmph).

The increase in speed will help in maintaining punctuality, according to a Southern Railway release. — Special Correspondent

http://www.hindu.com/2008/12/22/stor...2253730400.htm
__________________
Click on---->



அருள் முருகன்
தமிழ்நாடு/இந்தியா
Arul Murugan no está en línea   Reply With Quote
Old December 23rd, 2008, 10:30 AM   #20
sbbalamurugan
Bala - Madurai
 
Join Date: Oct 2008
Location: Madurai
Posts: 29
Likes (Received): 0

Special Train Yesvanthpur to Nagerkovil - 0651/0652

Dear all,

Last week they have announced the above said special via Bangalore, Hosur ,Salem , Madurai.

I tried for booking last week it shows in IRCTC, but today it is not listed for booking.

Shall any body knows the update, even i tried almost all the railway website.



Its very important train, after an year they have announced a special train from bangalore to South tamil nadu
sbbalamurugan no está en línea   Reply With Quote


Reply

Tags
thanjavur

Thread Tools
Rate This Thread
Rate This Thread:

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off



All times are GMT +2. The time now is 05:07 PM.


Powered by vBulletin® Version 3.8.8 Beta 1
Copyright ©2000 - 2014, vBulletin Solutions, Inc.
Feedback Buttons provided by Advanced Post Thanks / Like v3.2.5 (Pro) - vBulletin Mods & Addons Copyright © 2014 DragonByte Technologies Ltd.

vBulletin Optimisation provided by vB Optimise (Pro) - vBulletin Mods & Addons Copyright © 2014 DragonByte Technologies Ltd.

SkyscraperCity ☆ In Urbanity We trust ☆ about us | privacy policy | DMCA policy

Hosted by Blacksun, dedicated to this site too!
Forum server management by DaiTengu