Old July 19th, 2014, 02:14 AM   #3261
mopc
Registered User
 
mopc's Avatar
 
Join Date: Jan 2005
Location: Santos Sao Paulo
Posts: 17,239
Likes (Received): 11993

**OVERVIEW OF PROJECTS UNDER CONSTRUCTION IN SAO PAULO AS OF JULY 2014**

Line 4 - 5 stations (underground)
Line 5 - 10 stations (underground)
Line 6 - 15 stations (underground)
Line 13 - 3 stations (elevated/ at grade)
Line 15 - 18 stations (elevated monorail)
Line 17 - 8 stations (elevated monorail)

That makes it 59 stations under construction

To be awarded within months:

Line 2 - 13 new stations (underground)
Line 17 - 10 additional stations (elevated monorail)
Line 18 - 15 stations (elevated monorail)

So it's an additional 38 other stations "in othe oven", with tenders to be awarded still this year.

A grand total of 97 stations to be built until 2020 or a little later (this does not include a few random CPTM suburban stations that will be renewed or created)
mopc no está en línea   Reply With Quote

Sponsored Links
Old July 19th, 2014, 02:32 AM   #3262
mopc
Registered User
 
mopc's Avatar
 
Join Date: Jan 2005
Location: Santos Sao Paulo
Posts: 17,239
Likes (Received): 11993

Line 15 Monorail - Pic update. The line is not yet open to the public, its still in tests. Opening will be within a few weeks.

Quote:
Originally Posted by Eduardo GJF View Post
























mopc no está en línea   Reply With Quote
Old July 19th, 2014, 03:29 AM   #3263
PRG_São Paulo
Registered User
 
Join Date: Mar 2008
Location: São Paulo
Posts: 245
Likes (Received): 134

Quote:
Originally Posted by mopc View Post
**OVERVIEW OF PROJECTS UNDER CONSTRUCTION IN SAO PAULO AS OF JULY 2014**

Line 4 - 5 stations (underground)
Line 5 - 10 stations (underground)
Line 6 - 15 stations (underground)
Line 13 - 3 stations (elevated/ at grade)
Line 15 - 18 stations (elevated monorail)
Line 17 - 8 stations (elevated monorail)

That makes it 59 stations under construction

To be awarded within months:

Line 2 - 13 new stations (underground)
Line 17 - 10 additional stations (elevated monorail)
Line 18 - 15 stations (elevated monorail)

So it's an additional 38 other stations "in othe oven", with tenders to be awarded still this year.

A grand total of 97 stations to be built until 2020 or a little later (this does not include a few random CPTM suburban stations that will be renewed or created)
That is really nice! Tahnks for sharing it. Which stations are going to be built at Line 2?
PRG_São Paulo no está en línea   Reply With Quote
Old July 19th, 2014, 03:36 AM   #3264
mopc
Registered User
 
mopc's Avatar
 
Join Date: Jan 2005
Location: Santos Sao Paulo
Posts: 17,239
Likes (Received): 11993

The 13 stations east of Vila Prudente

mopc no está en línea   Reply With Quote
Old July 19th, 2014, 10:37 PM   #3265
mopc
Registered User
 
mopc's Avatar
 
Join Date: Jan 2005
Location: Santos Sao Paulo
Posts: 17,239
Likes (Received): 11993

Line 17 - pic by forumer Fischer. Metallic emergency walkways installed.



original post
mopc no está en línea   Reply With Quote
Old July 20th, 2014, 09:45 AM   #3266
Jim856796
Registered User
 
Jim856796's Avatar
 
Join Date: Jun 2006
Location: Citizen of the World
Posts: 8,955
Likes (Received): 849

Quote:
Originally Posted by mopc View Post
Line 18 Monorail - Sao Paulo's third monorail line is awarded to consortium called ABC Integrado, construction to start until November 2014. Scomi will build the 5-car trainsets.
How is the Line 18 Monorail gonna have five-car trainsets when the Lines 15 and 17 (also Monorail) will have seven-car trainsets? Is it because the area that will be served by Line 18 has a lower density?
__________________
I honestly think all development projects must be sustainable and futureproof.

You support the good projects... and oppose the bad.
Jim856796 no está en línea   Reply With Quote
Old July 20th, 2014, 04:30 PM   #3267
killerjag
Registered User
 
killerjag's Avatar
 
Join Date: Jul 2013
Location: Rio de Janeiro
Posts: 317
Likes (Received): 455

Actually, line 17 will also have five-car trainsets.
killerjag no está en línea   Reply With Quote
Old July 20th, 2014, 05:37 PM   #3268
lkstrknb
Chicago Luke
 
Join Date: Jan 2009
Posts: 445
Likes (Received): 804



Here is a video I filmed of the Sao Paulo Monorail Line 15.
__________________
lkstrknb no está en línea   Reply With Quote
Old July 20th, 2014, 07:31 PM   #3269
PRG_São Paulo
Registered User
 
Join Date: Mar 2008
Location: São Paulo
Posts: 245
Likes (Received): 134

Quote:
Originally Posted by mopc View Post
The 13 stations east of Vila Prudente

And about the west side, I read news in 2012 that they have started basic project of Aurelia and Cerro Corá stations? The last one would cross with line 20 (Pink) from Lapa to Santo Amaro.
PRG_São Paulo no está en línea   Reply With Quote
Old July 20th, 2014, 07:33 PM   #3270
PRG_São Paulo
Registered User
 
Join Date: Mar 2008
Location: São Paulo
Posts: 245
Likes (Received): 134

Quote:
Originally Posted by mopc View Post
The 13 stations east of Vila Prudente

And about the west side, I read news in 2012 that they have started basic project of Aurelia and Cerro Corá stations? The last one would cross with line 20 (Pink) from Lapa to Santo Amaro.
By the way, is there more news about line 20?
PRG_São Paulo no está en línea   Reply With Quote
Old July 21st, 2014, 05:15 AM   #3271
mopc
Registered User
 
mopc's Avatar
 
Join Date: Jan 2005
Location: Santos Sao Paulo
Posts: 17,239
Likes (Received): 11993

The western expansion to Cerro Corá is still just a promise and has no date to start. I would bet it would only be built after 2020.
mopc no está en línea   Reply With Quote
Old July 22nd, 2014, 03:44 AM   #3272
mopc
Registered User
 
mopc's Avatar
 
Join Date: Jan 2005
Location: Santos Sao Paulo
Posts: 17,239
Likes (Received): 11993

Quote:
Originally Posted by mopc View Post
**OVERVIEW OF PROJECTS UNDER CONSTRUCTION IN SAO PAULO AS OF JULY 2014**

Line 4 - 5 stations (underground)
Line 5 - 10 stations (underground)
Line 6 - 15 stations (underground)
Line 13 - 3 stations (elevated/ at grade)
Line 15 - 18 stations (elevated monorail)
Line 17 - 8 stations (elevated monorail)

That makes it 59 stations under construction

To be awarded within months:

Line 2 - 13 new stations (underground)
Line 17 - 10 additional stations (elevated monorail)
Line 18 - 15 stations (elevated monorail)

So it's an additional 38 other stations "in othe oven", with tenders to be awarded still this year.

A grand total of 97 stations to be built until 2020 or a little later (this does not include a few random CPTM suburban stations that will be renewed or created)
UPDATE / CORRECTION

**OVERVIEW OF PROJECTS UNDER CONSTRUCTION IN SAO PAULO AS OF JULY 2014**

Line 4 - 5 stations (underground)
Line 5 - 10 stations (underground)
Line 6 - 15 stations (underground)
Line 13 - 3 stations (elevated/ at grade)
Line 15 - 18 stations (elevated monorail)
Line 17 - 19 stations (elevated monorail)

That makes it 70 stations under construction

To be awarded within months:

Line 2 - 13 new stations (underground)
Line 18 - 13 stations (elevated monorail)

So it's an additional 26 other stations "in othe oven", with tenders to be awarded still this year.

A grand total of 96 stations to be built until 2020 or a little later (this does not include a few random CPTM suburban stations that will be renewed or created)
mopc no está en línea   Reply With Quote
Old July 22nd, 2014, 04:29 AM   #3273
mopc
Registered User
 
mopc's Avatar
 
Join Date: Jan 2005
Location: Santos Sao Paulo
Posts: 17,239
Likes (Received): 11993

Line 11 - train near Calmon Viana station seen from Road Ring




source= http://www.skyscrapercity.com/showth...89252&page=240
mopc no está en línea   Reply With Quote
Old July 22nd, 2014, 04:53 AM   #3274
mopc
Registered User
 
mopc's Avatar
 
Join Date: Jan 2005
Location: Santos Sao Paulo
Posts: 17,239
Likes (Received): 11993

Line 17 Monorail - pic update


















original post
mopc no está en línea   Reply With Quote
Old July 22nd, 2014, 05:44 AM   #3275
437.001
Sister Greed U
 
437.001's Avatar
 
Join Date: Mar 2009
Location: on the road (Spain)
Posts: 32,012
Likes (Received): 15438

Boa tarde/noite.

I have a question.

Reading the thread from the beginning (currently I´m on page 50, I haven´t read between pages 50 and 150 yet, so I´m sorry if I´ve missed anything), on some early page I read that República station and... can´t remember which other one, had some platforms for line 4 that were finally not used.

Could they be used for another new line to be built in the future?

Obrigado.
__________________
&&& abcde PMR en Cat ImpTgn Cat2017
Everybody got a job to lose (A.E, Vision Thing, WEA, 1990)

malegi liked this post
437.001 no está en línea   Reply With Quote
Old July 22nd, 2014, 08:19 AM   #3276
Jim856796
Registered User
 
Jim856796's Avatar
 
Join Date: Jun 2006
Location: Citizen of the World
Posts: 8,955
Likes (Received): 849

Quote:
Originally Posted by killerjag View Post
Actually, line 17 will also have five-car trainsets.
What, the area to be served by that line has a lower density, too?
__________________
I honestly think all development projects must be sustainable and futureproof.

You support the good projects... and oppose the bad.
Jim856796 no está en línea   Reply With Quote
Old July 22nd, 2014, 09:34 PM   #3277
Julio CAF
L3, L11 user
 
Julio CAF's Avatar
 
Join Date: Jul 2010
Location: São Paulo
Posts: 5,118
Likes (Received): 4232

Quote:
Originally Posted by mopc View Post
**OVERVIEW OF PROJECTS UNDER CONSTRUCTION IN SAO PAULO AS OF JULY 2014**

Line 4 - 5 stations (underground)
Line 5 - 10 stations (underground)
Line 6 - 15 stations (underground)
Line 13 - 3 stations (elevated/ at grade)
Line 15 - 18 stations (elevated monorail)
Line 17 - 8 stations (elevated monorail)

That makes it 59 stations under construction

To be awarded within months:

Line 2 - 13 new stations (underground)
Line 17 - 10 additional stations (elevated monorail)
Line 18 - 15 stations (elevated monorail)

So it's an additional 38 other stations "in othe oven", with tenders to be awarded still this year.

A grand total of 97 stations to be built until 2020 or a little later (this does not include a few random CPTM suburban stations that will be renewed or created)
Line 9 under constuction too, more 2 stations (Mendes and Varginha stations).
__________________
Lema profissional no ramo do transporte: "País desenvolvido não é onde o pobre pode comprar um carro, é onde o rico usa o transporte público" - Desconhecido.

Last edited by Julio CAF; July 22nd, 2014 at 09:53 PM.
Julio CAF no está en línea   Reply With Quote
Old July 22nd, 2014, 09:46 PM   #3278
mopc
Registered User
 
mopc's Avatar
 
Join Date: Jan 2005
Location: Santos Sao Paulo
Posts: 17,239
Likes (Received): 11993

Line 2 - Line 2 Eastern Expansion Pack (13 stations, underground) - Tender published and receives proposals from 3 consortiums. The Eastern Expansion pack will make Line 2 the longest and busiest line in the whole Sao Paulo Heavy Rail system when complete, circa 2021, going from 670,000 pax/day today to a whopping 1,5 million/day, along 27 stations. A total of 35 new 6-car trainsets will be added to the line. The global cost of the expansion is around US$5 billion. Construction may start by early 2015.




Quote:
Originally Posted by RMeier View Post
Depois de adiar duas vezes, o Metrô realizou ontem a abertura dos envelopes contendo as propostas comerciais das empresas pré-qualificadas para a licitação da extensão da Linha 2-Verde, que ligará Guarulhos à capital paulista.

No total, foram 19 empresas interessadas, mas apenas três apresentaram propostas para todos os oito lotes da construção, sendo eles os consórcios Construcap-Copasa Obras Civis L2, com R$ 7,9 bilhões; Constran AZVI Linha 2 Verde, com R$ 7,7 bilhões, e Cetenco-Acciona-Ferreira Guedes, com proposta de R$ 7 bilhões.

Com 13 propostas, o lote 8 foi o que mais obteve interesse dentre as empresas. No entanto, segundo o Metrô, as propostas serão submetidas a exame mais apurado e o resultado desta análise será divulgado posteriormente, mas ainda sem uma data definida.

As obras de extensão da Linha 2 se estenderão por 15,5 km e acrescentarão 13 estações ao sistema metroviário que será todo subterrâneo. Em Guarulhos, beneficiará diretamente os bairros e Vila Leonor, Vila Galvão, Ponte Grande e Vila Endres. Assim, o número de usuários da Linha 2 passará dos atuais 672 mil usuários, por dia, em média, para cerca de 1,52 milhão. Para a operação da Linha 2 até Guarulhos a frota de trens receberá 35 novas composições. O investimento previsto para essa linha é de R$ 10,19 bilhões.

Interesse – Seis lotes obtiveram a proposta de três empresas, sendo os consórcios HFTB Linha 2 Verde (R$ 3,9 bi) e Linha 2 Verde-Vila Prudente-Dutra (R$ 3,7 bi), e a companhia Mendes Junior Trading e Engenharia S.A (R$ 3,4 bi). Já o Consórcio Linha 2 Verde-Vila Prudente-Dutra (R$ 4,6 bi) apresentou propostas para quatro lotes, seguido do Consórcio CCI (R$ 1,9 bi) e da Construtora Andrade Gutierrez S.A (R$ 4,4 bi), que apresentaram interesse em três lotes.

Outros quatro consórcios apresentaram proposta para dois lotes, sendo o Carioca Ferrovial (R$ 3,6 bi), CR Almeida-Ghella-Consbem (R$ 3,3 bi), Fidens-Servix-Via, (R$ 1,4 bi) e Construções e Comércio Camargo Corrêa S. (R$ 3,9 bi. Por fim, outros seis apresentaram interesse para apenas um lote, sendo as empresas Azevedo e Travassos S/A (R$ 578,5 milhões), Spavias Engenharia S/A (R$ 644,8 milhões) e Construtora Cowan S.A (R$ 738,9 milhões), e os consórcios Contracta-Planova-Rual (R$ 634,9 milhões), Consórcio Hersa-MPD (R$ 738 milhões) e Schahin, Trail e Telar (R$ 614,7 milhões).

http://www.guarulhoshoje.com.br/port...linha-2-verde/
mopc no está en línea   Reply With Quote
Old July 22nd, 2014, 10:46 PM   #3279
mopc
Registered User
 
mopc's Avatar
 
Join Date: Jan 2005
Location: Santos Sao Paulo
Posts: 17,239
Likes (Received): 11993

Quote:
Originally Posted by 437.001 View Post
Boa tarde/noite.

I have a question.

Reading the thread from the beginning (currently I´m on page 50, I haven´t read between pages 50 and 150 yet, so I´m sorry if I´ve missed anything), on some early page I read that República station and... can´t remember which other one, had some platforms for line 4 that were finally not used.

Could they be used for another new line to be built in the future?

Obrigado.
Republica station was built in 1982 already with additional platforms for future line 4. These platforms have been in use since 2011, when Line 4 reached Republica. They remained unused from 1982 to 2011. The original layout of the Line platforms, however, was drastically changed, because the construction method changed. Originally they planned to use two small tunneling machines to dig one tunnel each, eventually they ended up using a single wider tunneling machine to dig one tunnel for two tracks. Then they had to tear down the original central platform at Republica to allow for the driling machine to pass by.

Now, like every Line 4 station, Republica has only side platforms.
__________________
BRAZIL URBAN TRANSPORT COMPILATION - full updates of all projects on first page!
SAO PAULO PUBLIC TRANSPORT - BRAZIL GENERAL INFRASTRUCTURE - SANTOS TRAMWAY (VLT) - MONORAILS
LINGUÍSTICA - CETICISMO

437.001 liked this post
mopc no está en línea   Reply With Quote
Old July 22nd, 2014, 10:48 PM   #3280
mopc
Registered User
 
mopc's Avatar
 
Join Date: Jan 2005
Location: Santos Sao Paulo
Posts: 17,239
Likes (Received): 11993

Quote:
Originally Posted by Jim856796 View Post
What, the area to be served by that line has a lower density, too?
I don't know, I am indeed a bit concerned that the choice of 5-car trainsets instead of 7 may lead to overcrowded trains, or an underperforming line. It will all depend on the promise of very low headways (2 minutes).
mopc no está en línea   Reply With Quote


Reply

Tags
metro, são paulo, subway, trains

Thread Tools

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off

Related topics on SkyscraperCity


All times are GMT +2. The time now is 06:55 PM.


Powered by vBulletin® Version 3.8.11 Beta 4
Copyright ©2000 - 2018, vBulletin Solutions Inc.
Feedback Buttons provided by Advanced Post Thanks / Like (Pro) - vBulletin Mods & Addons Copyright © 2018 DragonByte Technologies Ltd.

vBulletin Optimisation provided by vB Optimise (Pro) - vBulletin Mods & Addons Copyright © 2018 DragonByte Technologies Ltd.

SkyscraperCity ☆ In Urbanity We trust ☆ about us | privacy policy | DMCA policy

tech management by Sysprosium