EPHR and One Central Park update
Construction Report as of February 2008
March 10, 2008, 6:37 am We are pleased to inform you that as of 15 February 2008, the project accomplishment for One Central Park (Tower 3) and Eastwood Park Hotel & Residential Suites (Tower 4) are 56.00% and 42.00% respectively. Concreting works are completed for Tower 3 and Tower 4, both buildings are topped-off at 39th deck level. Interior masonry works are substantially complete while wall partitioning and water proofing works are ongoing on the upper levels. On going architectural works are installation of doors, windows, masonry, plastering and painting. Other works include electro-mechanical fixings on pace with the ongoing civil works. |
|
|
|
|
#122 |
|
k.o.n.t.r.o.b.e.r.s.y.a.l
Join Date: Dec 2004
Location: Sacramento/Caloocan
Posts: 395
|
there has been no update on the eastwood, so I am posting this photo taken by
issa & charlie from flickr, taken April 6, 2008 is it me, or the progress of the four central towers, slow? ![]() and taken by pheared from flickr, around april 12, 2008
__________________
can't read my, can't ready my, can't ready my poker face.... Last edited by IsaganiZenze; May 18th, 2008 at 10:03 AM. |
|
|
|
|
#123 |
|
cityboy
Join Date: Oct 2004
Posts: 159
|
the Parkview towers are they painted already because the color scheme is a bit odd?
|
|
|
|
|
#124 |
|
Property of Chrisvenz™
Join Date: Dec 2002
Location: Dakota Harrison Plaza
Posts: 5,179
|
Yes. And those were the original colors shown in the renderings.
__________________
SSC Philippines' Resident Twink ♥ JQWE Aaron 'da Kota is a property of Chrisvenz |
|
|
|
|
#125 |
|
VAMOS!!!
Join Date: Nov 2004
Location: Villasis, Pangasinan, PH
Posts: 993
|
06.11.2008
Photo by tyronne ![]()
|
|
|
|
|
#126 |
|
Caters Ayala/Rockwell/SM
Join Date: Nov 2007
Location: Quezon City
Posts: 1,730
|
Money Sense Smart Spender chose Eastwood Park Hotel and Residential Suites as No. 11 in the Best Value Condo to Watch Out For list.. see scans below.
![]() ![]() ![]()
|
|
|
|
|
#127 |
|
M-055-1M0
Join Date: Nov 2004
Location: Philippines
Posts: 6
|
Sept. 27, 2008 by me
![]()
|
|
|
|
|
#128 |
|
Registered User
Join Date: Jul 2006
Location: Bitburg/Spangdahlem/Paranaque
Posts: 27
|
EPHR
![]()
|
|
|
|
|
#129 |
|
Registered User
Join Date: Jul 2006
Location: Bitburg/Spangdahlem/Paranaque
Posts: 27
|
EPHR
Construction Report as of November 2008
December 2, 2008, 3:27 am We are pleased to inform you that as of 30 November 2008, the overall project accomplishment for One Central Park (Tower 3) and Eastwood Park Hotel & Residential Suites (Tower 4) are 79.50% and 57.40% respectively. Concreting works are completed for both Tower 3 and Tower 4. Ongoing works include CHB laying, exterior plastering, painting works and installation of electrical and plumbing fixtures. |
|
|
|
|
#130 |
|
Registered User
Join Date: Jul 2006
Location: Bitburg/Spangdahlem/Paranaque
Posts: 27
|
updates
Construction Report as of March 2009
March 17, 2009, 3:23 am We are pleased to inform you that as of 16 March 2009, the overall project accomplishment for One Central Park (Tower 3) and Eastwood Park Hotel & Residential Suites (Tower 4) are 80.0% and 58.0% respectively. Concreting works are completed for both Tower 3 and Tower 4. Ongoing works for Tower 3 includes tile & ceiling works, dry wall partitioning, installation of kitchen cabinets & bedroom closets, lavatory works while for Tower 4 current works include CHB laying, exterior plastering, painting works and installation electrical and plumbing fixtures, aluminum doors and windows, interior finishing works, waterproofing works, painting and elevator works. |
|
|
|
|
#131 |
|
Registered User
Join Date: Jul 2006
Location: Bitburg/Spangdahlem/Paranaque
Posts: 27
|
Construction Report As Of June 2009
June 16, 2009, 6:25 am We are pleased to inform you that as of 15 June 2009, the overall project accomplishment for One Central Park (Tower 3) and Eastwood Park Hotel & Residential Suites (Tower 4) are 80.50% and 61.50% respectively. On-going works for Tower 3 includes tile works, dry wall partitioning & ceiling works, installation of bedroom closets & kitchen cabinets, and lavatory works while for Tower 4 current works include CHB laying, exterior plastering, painting works and installation of electrical and plumbing fixtures, aluminum doors and windows, interior finishing works, waterproofing works and elevator works. |
|
|
![]() |