ALGIERS | Metro

http://urbanrail.net/af/alg-line-1-map.jpg


http://sousou582.skyblog.com/ (some picture )


http://wall2807.skyblog.com/7.html ( some picture)


the subway will be working in 2008
icosium no está en línea   Reply With Quote
Old February 27th, 2007, 11:33 PM   #2
madao
casablanca
 
madao's Avatar
 
Join Date: Feb 2007
Posts: 34
haha i heard that whole project was gone failliet?
madao no está en línea   Reply With Quote
Old February 28th, 2007, 05:29 AM   #3
awangmamat
Registered User
 
awangmamat's Avatar
 
Join Date: Jan 2007
Location: Kuala Lumpur
Posts: 46
Looks like a nice system. What's the length of the line? Future alignments, etc?
awangmamat no está en línea   Reply With Quote
Old March 2nd, 2007, 05:43 AM   #4
icosium
Registered User
 
icosium's Avatar
 
Join Date: Dec 2006
Posts: 2,574
algier subway

i invite you to come next years in algiers to see it with yours eyes

Quote:
Originally Posted by madao View Post
haha i heard that whole project was gone failliet?
icosium no está en línea   Reply With Quote
Old June 9th, 2007, 08:14 PM   #5
madao
casablanca
 
madao's Avatar
 
Join Date: Feb 2007
Posts: 34
Quote:
Originally Posted by icosium View Post
i invite you to come next years in algiers to see it with yours eyes
hahaha inshallah
madao no está en línea   Reply With Quote
Old March 1st, 2007, 06:06 PM   #6
MetroGuardian
Registered User
 
MetroGuardian's Avatar
 
Join Date: Dec 2004
Location: Zurich
Posts: 928
That's a good project. Now that you have the money you should built some infrastructure!
__________________
KTIZON

TALLATHENS
MetroGuardian no está en línea   Reply With Quote
Old March 2nd, 2007, 05:49 AM   #7
icosium
Registered User
 
icosium's Avatar
 
Join Date: Dec 2006
Posts: 2,574
http://www.newpressphoto.com/Newpress/newpress.php


go litle down and click when you see ( metro project )

or can see it here

http://www.newpressphoto.com/Newpres...ellepage01.htm
icosium no está en línea   Reply With Quote
Old March 2nd, 2007, 06:01 AM   #8
icosium
Registered User
 
icosium's Avatar
 
Join Date: Dec 2006
Posts: 2,574
another map futur subway algiers


http://www.skyscrapercity.com/showthread.php?t=160839
icosium no está en línea   Reply With Quote
Old March 2nd, 2007, 06:03 AM   #9
icosium
Registered User
 
icosium's Avatar
 
Join Date: Dec 2006
Posts: 2,574
http://www.skyscrapercity.com/showthread.php?t=396171
icosium no está en línea   Reply With Quote
Old March 14th, 2007, 02:28 AM   #10
icosium
Registered User
 
icosium's Avatar
 
Join Date: Dec 2006
Posts: 2,574
Systra to provide assistance for the Algiers metro

Entreprise du Métro d’Alger (Algiers Metro Company - EMA) has awarded the SYSTRA /RATP Development consortium the contract to provide assistance with the follow-up of design studies, installation and fitting out of fixed equipment for all systems on line 1 phase 1 of the Algiers metro. This includes stations, rolling stock and workshops.

Phase 1 runs from Tafourah Grande Poste station to Haï El Badr eastbound, through 11km of tunnel, the main construction of which is already near completion. The line has 10 stations, which are also nearing completion, but which still need to be completely equipped. It also includes the high voltage substation, the control centre and the partly-completed Bachdjarah maintenance complex.

- The SYSTRA / RATP Development consortium is therefore responsible for follow-up, inspection and co-ordination of the construction of the whole transport system.

The work is expected to take 60 months, including the guarantee period of 24 months.

In the event of commercial operation not being awarded to an external operator, the contract also contains an option for the preparation of and assistance with operation to be managed by RATP Development. Specifically, the consortium will be appointed to manage the following activities for a period of 5 years :

- preparation for operation of the first stage of line 1,

- technical assistance with the operation and maintenance of the metro once commercial service has begun.
icosium no está en línea   Reply With Quote
Old March 14th, 2007, 02:30 AM   #11
icosium
Registered User
 
icosium's Avatar
 
Join Date: Dec 2006
Posts: 2,574
ALGERIA - DETAILED PRELIMINARY STUDIES FOR 27 RAILWAY STATIONS

The Algerian National Railways Company (SNTF) has chosen SYSTRA, in partnership with the local service provider, Seti-Rail, to carry out detailed preliminary studies for signalling, telecommunications and energy, and also to prepare the tender consultation documents for 27 stations located in Algiers. Four SYSTRA personnel will be involved in the work which is due to last 11 months.
icosium no está en línea   Reply With Quote
Old March 20th, 2007, 01:26 AM   #12
icosium
Registered User
 
icosium's Avatar
 
Join Date: Dec 2006
Posts: 2,574
http://sousou582.skyblog.com/16.html
icosium no está en línea   Reply With Quote
Old March 22nd, 2007, 08:27 PM   #13
icosium
Registered User
 
icosium's Avatar
 
Join Date: Dec 2006
Posts: 2,574
Subway of Algiers Maghlaoui: the project will be delivered in September 2008 By: EL MOUDJAHID It: Wednesday March 21, 2007 The Minister for Transport, Mr. Mohamed Maghlaoui, announced the beginning yesterday, in the next days, of the installation of the way of the future subway of Algiers, considered as the most important stage before the delivery of the project, in September 2008. "the cross-pieces and the rails are currently aligned along the layout and their installation will start in the next days", declared the minister with the APS in margin of the top of the NEPAD, which is held in Algiers. At the time of a visit to the building site, last September, Mr. Maghlaoui had announced for the first quarter the 2007 beginning of the installation of the rails on the single line (known as n° 1) which composes the project, before its extension envisaged in 2009. It will connect the Large Post office to Hated El Badr on a course of 9 km serving, in ten stations, the communes of Bachdjarah, El Magharia, Hussein Dey, Sidi Me hamed and Algiers-center. In January 2006, the company of the subway of Algiers (EMA) had signed with the Siemens-Vinci group and CIF, the bearing contract on the fixed equipment, the rolling stocks and interior installations of the stations, ultimate stage before the setting according to the project. The contract must be carried out from here in the fourth quarter 2008 for an amount of 77 billion dinars, civil engineering and equipment included/understood. The exploitation and the maintenance of the Subway will be entrusted, through a contract of delegation of management, at tested company a "of international fame" whose choice is in hand. Three extensions, already studied, must be added and enter to it in servicing 2009. It acts of Hated El Badr (Kouba) - El Harrach, Haï El Badr - Ain Naâdja and Grande Post office - Place of the Martyrs. The average estimated request for transport per subway is estimated in peak hour at 21.000 passagers/heure in the Place direction Martyrs - Haï El Badr. It should, in the long term, reach the 40.000 voyageurs/heure. The traffic should reach in the long term the 150 million travellers per annum, according to EMA'S
icosium no está en línea   Reply With Quote
Old June 9th, 2007, 08:51 AM   #15
icosium
Registered User
 
icosium's Avatar
 
Join Date: Dec 2006
Posts: 2,574
icosium no está en línea   Reply With Quote
Old June 9th, 2007, 08:52 AM   #16
icosium
Registered User
 
icosium's Avatar
 
Join Date: Dec 2006
Posts: 2,574
icosium no está en línea   Reply With Quote
Old July 10th, 2007, 11:18 PM   #17
Bitxofo
BANNED
 
Join Date: Feb 2005
Location: Alderaan BCN BKK ATH PAR LON SYD SFO CPT TYO SCL CHC BUE SCG SVQ AGP BDN
Posts: 34,309
Quote:
Originally Posted by icosium View Post
Trains made in Spain!
Bitxofo no está en línea   Reply With Quote
Old July 11th, 2007, 08:54 PM   #18
icosium
Registered User
 
icosium's Avatar
 
Join Date: Dec 2006
Posts: 2,574
yeah train are from spain they will come at the end off 2007
but the algiers subway was built 95/100 by algerian
diging ,enginering,tunel, station
they have german enginer working in the site
2 french company compete to have the management off the subway i guess one off them will have it my guess (ratp)

Quote:
Originally Posted by Bitxofo View Post
Trains made in Spain!
icosium no está en línea   Reply With Quote
Old July 12th, 2007, 03:00 PM   #19
PePi
Tram Fan
 
PePi's Avatar
 
Join Date: Jul 2007
Posts: 18
Algiers: New lines

Salaam aleikum,

Congratulations for the project (at last!!)

And what about the new lines, new phase? Is it planned for when?
PePi no está en línea   Reply With Quote
Old June 10th, 2007, 03:51 AM   #20
icosium
Registered User
 
icosium's Avatar
 
Join Date: Dec 2006
Posts: 2,574






icosium no está en línea   Reply With Quote


Reply

Thread Tools
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off



All times are GMT +2. The time now is 02:05 AM.


Powered by vBulletin® Version 3.8.3
Copyright ©2000 - 2010, Jelsoft Enterprises Ltd.

SkyscraperCity - In Urbanity We Trust

Hosted by Blacksun, dedicated to this site too!
BBS server management by DaiTengu
Forums Directory