Waiting game
Join Date: Nov 2010
Posts: 41
Likes (Received): 0
|
looking good
|
|
|
|
|
|
#122 |
|
Waiting game
Join Date: Nov 2010
Posts: 41
Likes (Received): 0
|
spoke to TFG about a month ago to ask about rental rates and said it should be quite promising as the diamond managed to rent there's out and i think the location is not as good.
|
|
|
|
|
|
#123 |
|
Registered User
Join Date: May 2008
Posts: 76
Likes (Received): 0
|
December 2010 Report
100% of sub structure is complete 100% of block work has been completed up to 29th floor and in progress on 30th floor. 100% of plastering work has been completed up to 28th floor and in progress on 29th floor. Wall tiling is in progress as per the following percentage; Ground floor: 85%. Floors 2-10: 80%. Floors 12&13: 68% Floors 14-21: 70%. Floors 22-26: 65%. Floor tiling is in progress as per the following percentage: Floors 14-17: 80% Floors 18-24: 70% 25th Floor: 30% Drainage and water supply works are in progress on the 27th floor; 85% completed. AC works are in progress up to the 24th floor with an average of 77% completion, 55% in 25th and 20% in the 26th floors receptively. Fire alarm & emergency cabling is in progress up to the 26th floor with an average of 70% completion. Electrical works are in progress up to the 29th floor with 64% completed. The Curtain walling work is in progress as per the following percentages: Frame work: 66% Glass work: 35%. Aluminium cladding work: 43%. http://www.thefirstgroup.com/thebrid...ion-status.php |
|
|
|
|
|
#124 |
|
Registered User
Join Date: May 2008
Posts: 76
Likes (Received): 0
|
January 2011 Report
100% of sub structure is complete 100% of super structure is complete 100% of plastering work has been completed up to 28th floor and 50% completed in the 29th floor. 100% of block work has been completed up to 30th floor and 60% completed in the 30th floor. Wall tiling is in progress as per the following percentages; Ground floor: 93%. Floors 2-10: 87%. Floors 12 &13: 75% Floors 14-21: 77% Floors 22-28: 70% Floor tiling is in progress as per the following percentages: Ground floor: 35% Floors 14-17: 85% Floors 18-24: 80% Floors 25-28: 40% Drainage and water supply works are in progress up to the 28th floor; 88% completed. AC works are in progress up to the 29th floor with an average of 75% completion, Fire alarm & emergency cabling is in progress up to the 28th floor with an average of 70% completion. Electrical works are in progress up to the 29th floor with 70% completed. The Curtain walling works progressing as per the following details and percentages: Frame work: 72% Glass work: 44% Aluminium cladding work: 57% http://www.thefirstgroup.com/thebrid...ion-status.php |
|
|
|
|
|
#125 |
|
Registered User
Join Date: May 2008
Posts: 76
Likes (Received): 0
|
February 2011 Report
100% of sub structure is complete 100% of super structure is complete 100% of plastering work has been completed up to 31st 100% of block work has been completed up to 31st floor 80% of toilet wall tiles completed up to 29th floor Toilet floor tiles completed up to 16th floor 85% of kitchen wall tiles completed up to 28th floor 70% of floor tiling completed up to 28th floor 90% of false ceiling suspension and framing work completed up to 26th Floor 70% of gypsum board into false ceiling fixed up to 16th floor 80% of wooden doors have been fixed up to 14th floor 80% of garbage chute fixing is complete up to 31st floor 93% of wet area waterproofing completed up to 30th floor Paint primer and stucco in progress in 31ST Floor 70% of 1st coat painting to walls and 40% 1st coat painting to ceiling completed up to 14th Floor 95% of staircase terrazzo tiling completed in stair well 2 up to 31st floor. 95% of staircase terrazzo tiling completed in stair well 1 up to 30th floor. 85% of staircase handrail fixing completed up to 13th floor in stair well 1 85% of staircase handrail fixing completed up to 28th floor in stair well 2 Installation of commercial and Solo office lifts in progress Installation of window cleaning equipment at roof floor in progress 93% of drainage and water supply works completed up to the 28th floor and 40% completed between 29th & 31st floor 85% of air conditioning works completed up to 29th floor and 20% completed in 30th floor 80% of fire fighting system completed up to 28th floor 70% of electrical works are completed up to the 29th floor http://www.thefirstgroup.com/thebrid...ion-status.php |
|
|
|
|
|
#126 |
|
Registered User
Join Date: May 2008
Posts: 76
Likes (Received): 0
|
Hi all,
Did anyone payed above 8 Th installment for The Bridge? and did anyone get a discount? |
|
|
|
|
|
#127 |
|
Waiting game
Join Date: Nov 2010
Posts: 41
Likes (Received): 0
|
which is the 8th installment and why would you get a discount????
|
|
|
|
|
|
#128 |
|
Registered User
Join Date: May 2008
Posts: 76
Likes (Received): 0
|
This is the order of the payment schedule 10 installments as shown in the contract:-
1- 1st installment reservation deposite of 10% plus 5000 Dirhams admin fee. 2- 2nd payment 10% 3- 1st installment 10% 4- 2nd installment 10% 5- 3rd installment 10% 6- 4th installment 10% 7- 5th installment 10% 8- 6th installment 10%........> I was talking about this payment did anyone paid The First Group yet? 9- 7th installment 10& 10- Final installment 10% and why not asking them for a discount... all the building material is very cheap and the delay of this project .. it froze our assets. Last edited by G.invester; March 15th, 2011 at 09:24 PM. |
|
|
|
|
|
#129 | |
|
Waiting game
Join Date: Nov 2010
Posts: 41
Likes (Received): 0
|
Quote:
Have you tried asking for a discount G.Investor? |
|
|
|
|
|
|
#130 |
|
Registered User
Join Date: May 2008
Posts: 76
Likes (Received): 0
|
yes I tried but they refused, that was in mid 2010
|
|
|
|
|
|
#131 |
|
Waiting game
Join Date: Nov 2010
Posts: 41
Likes (Received): 0
|
What was there reason?
If you work out the delay by interest lost and potential rental income it comes to around 10-14% of the unit prices which is alot. Might have a word if they can compensate in anyway. If they dont give some discount then i will say the least they can do is for me to delay the final payment till the end of the year or get 2-3 weeks extra personal usage. |
|
|
|
|
|
#132 | |
|
Registered User
Join Date: May 2008
Posts: 76
Likes (Received): 0
|
Well their reason was that they bought the building material way back in 2008
which is nonsense in my point of view. and besides if we can gather more then 20 invester and ask them for a discount no less then 17% . By the way in the contract we get a free 4 weeks of free stay in our units. Quote:
|
|
|
|
|
|
|
#133 |
|
Registered User
Join Date: May 2008
Posts: 76
Likes (Received): 0
|
March 2011 Report
100% of sub structure is complete. 100% of super structure is complete. 100% of plastering work has been completed up to 31st floor. 100% of block work has been completed up to 31st floor. 90% of toilet wall tiles completed up to 30th floor. Toilet floor tiles on average 90% completed from the17th floor to the 30th floor. 90% of kitchen wall tiles completed up to 29th floor. 80% of floor tiling completed up to 30th floor. 90% of false ceiling suspension and framing work completed up to 27th Floor. 80% of gypsum board into false ceiling fixed up to 20th floor with 10% progress in 21st & 23rd floors. 80% of wooden doors have been fixed up to 14th floor 80% of garbage chute fixing is complete up to 31st floor. 95% of wet area waterproofing completed up to 30th floor. Paint primer and stucco in progress in 31ST Floor. Primer and Stucco in progress in 31ST Floor. 70% of 1st coat painting to walls and 40% 1st coat painting to ceiling completed up to 14th Floor. 95% of staircase terrazzo tiling completed in stair well 2 up to 31st floor. 95% of staircase terrazzo tiling completed in stair well 1 up to 30th floor. 85% of staircase handrail fixing completed up to 28th floor in stair well 1. 90% of staircase handrail fixing completed up to. Installation of commercial and Solo office lifts in progress. Installation of window cleaning equipment at roof floor in progress. 93% of drainage and water supply works completed up to the 28th floor and 50% completed between 29th & 31st floor. 90% of air conditioning works completed up to 29th floor and 30% completed in 30th floor 80% of fire fighting system completed up to 30th floor. 70% of electrical works are completed up to the 29th floor. http://www.thefirstgroup.com/thebrid...ion-status.php |
|
|
|
|
|
#134 |
|
Registered User
Join Date: May 2008
Posts: 76
Likes (Received): 0
|
Postpond handover until 31, Dec, 2011
The Bridge, Dubai Sports City As you will have seen from our website and regular construction updates the construction progress at The Bridge is well advanced and the exterior of the building now looks stunning. Regretfully, we have suffered a delay to our construction programme with regard to the Mechanical, Electrical and Plumbing (MEP) works which form the core infrastructure of the property. By way of clarification and as is commonplace in developing property markets, new building regulations are constantly being introduced, to refine local safety provisions and to comply with international safety standards, with Dubai as no exception. While safety is always uppermost in our minds in the construction and design process, it is always a challenge to modify systems which are advanced in terms of installation in order to retrofit to new compliance standards. Dubai Civil Defense authority introduced a completely new set of regulations requiring modifications to the fire fighting system, electrical distribution boards (DB), Low Voltage (LV) panels and pipe specifications. As a direct result we had to submit revised plans and specifications to the authorities and after due process, we gained the required approval. This process required us to halt Mechanical, Electrical and Plumbing (MEP) works causing an inevitable delay in construction. This was further exacerbated by a longer than anticipated lead time for procurement of new Distribution Boards, LV panels and pipes. By way of an example of the type of impact of these delays was the inability to commence the false ceiling works until the revised MEP is inspected and approved by the consultants and authorities. As is inevitable the construction programme has been delayed by these events which were clearly outside of our control, and, or, influence. As a result of the above and on behalf of Omega I Limited, we ask you to accept this letter as formal notification that the Completion Date as defined in your Sale and Purchase Agreement is now revised to 31st December 2011. In the meantime the Dubai Sports City Master Community is rapidly evolving. There is now a buzz around Sports City as the Cricket Stadium gets ready to host even more international events and the 700 families living in Victory Heights create a hive of activity. Our construction team will as always be working very closely with the contractors and project managers to ensure the revised construction program is complied with and we will use our best endeavors to improve on this timeline wherever possible. We are committed to working with you, and keeping you informed and regularly updated on the status of the project is of the utmost importance to us. You will be able to view the images of monthly progress through The First Group's new secured web-application which is exclusively for property owners only. This application will provide you with full information about your personal account within The First Group, current property portfolio, construction progress, statement of account, special offers on Dubai Travel and much more. Kindly refer to http://owners.thefirstgroup.com; If you not yet registered for First Online kindly inform us on firstonline@thefirstgroup.com and we will arrange for your registration. If you have any queries or require any clarification with regard to the content of this letter, or any other matters related to your purchase, our Client Services Department will be happy to assist you. Please call us on +971 4409 7500 / +44 870 383 0407 (UK) or e-mail us at: clientaccounts@thefirstgroup.com |
|
|
|
|
|
#135 | |
|
Waiting game
Join Date: Nov 2010
Posts: 41
Likes (Received): 0
|
Quote:
tried calling them but the lines were busy. gonna give them grief tomorrow. not happy about this one bit. it will work out to be over 2 and a half year delay. didnt they learn from the Diamond project regarding the current delay. 2 and a half worth of interest as well as rental income is our compensation. |
|
|
|
|
|
|
#136 |
|
Waiting game
Join Date: Nov 2010
Posts: 41
Likes (Received): 0
|
at least!!!
|
|
|
|
|
|
#137 |
|
Waiting game
Join Date: Nov 2010
Posts: 41
Likes (Received): 0
|
|
|
|
|
|
|
#138 |
|
Registered User
Join Date: Jan 2010
Posts: 19
Likes (Received): 0
|
I am just grateful that it is still being built. If you watch the latest video posted on skyscraperlist of the drive around DSC, you will note a lot of vacant lots and stalled projects. I assume that the unfinished towers where the cranes have been removed are stalled / mothballed, the Oasis tower is the one that springs to mind. I agree it is frustrating, but we must just be patient.
|
|
|
|
|
|
#139 | |
|
Registered User
Join Date: Nov 2008
Location: dubai
Posts: 93
Likes (Received): 0
|
Quote:
|
|
|
|
|
|
|
#140 |
|
Registered User
Join Date: Aug 2009
Posts: 51
Likes (Received): 0
|
Anybody seeking to employ the services of Mr Sunil Thacker needs to be a ware that this man was given the sack from the law firm TLG. He was given the sack for ill advising and misleading clients as well as making promises that were not true. This man is a crooked cheat and will seek to take advantage of desperate investors. Everybody needs to be warned.
|
|
|
|
![]() |