continue from here:
http://www.skyscrapercity.com/showthread.php?t=450384
http://www.skyscrapercity.com/showthread.php?t=450384
http://www.asianage.com/presentatio...ata-steel-posts-net-profit-at-rs-6,388cr.aspxChennai, Aug. 29: String Real Estate Information Service, a mortgage process outsourcing company, is planning to double its headcount to 1,100 by December 2007.
The Chennai-based company is also setting up centres at Trichy and Madurai. Both these centres will be operational by March 2007 and will accommodate 200 people each. The $6 million company would be spending over 4 million for the expansion projects.
"Being uniquely and exclusively focused on outsourcing solutions for the mortgage industry, Strings sees an opportunity in the current crisis,’’ said String’s CEO and founder Prashant Kothari adding that the total value of all back-office and transaction-processing activities annually is $100 billion of which $10 billion is add-ressable offshore market.
The trust website says it is a college established in 17 acres.. It is in Velammal Nagar where they already have a Matriculation school and the construction of huge hospital is going on..From today's Dinamalar Epaper, I saw the Ad about the inauguration of Velammal Engineering College on the 30th. This college will be at Viraganoor I guess. Anyone knows more about it? Good to see an additional Engineering college at Madurai.
Velammal Engg college is in Viraganoor. It is located between Viraganoor Ring road junction and Madhagu Anai(Viraganoor Dam) in MDU-Rameshwaram NH. Both Velammal school and Velammal Engg. college is located in Velammal Nagar.^^ Can you say where is velammal nagar or garden? i wll capture it in my next visit.
Hi All,^^
It looks like a very good progress. I heard it from mduvignesh about the same few days ago too. Also, it looks like the old MG line has been dismantled in the entire Madurai-Dindigul stretch and new BG sleepers have been put in place, ready for laying the BG line. But, no major work seems to have happened on that.
mduvignesh, can you explain further? Can you share any photos or videos, if you have ?
BG is exactly going to be laid over the MG line? or BG is going to adjacent to existing BG line?Hi All,
The MDU - DG doubling work is progressing good . All MG rails were removed from Dindugal to Madurai. Small bridge (ground works)works are progressing on, all the way between madurai and dindugal.RCC boxes were kept in place below the track.
Regarding Vaigai bridge - work is progressing good. i have taken some photos and videos, will upload later.
Also i have noted Madurai - dindugal NH work is also progressing well, roads are laid in many parts.Many small bridge construction works are going on.
New BG will be replaced with the existing MG line becauseBG is exactly going to be laid over the MG line? or BG is going to adjacent to existing BG line?
Previously,the MG line was not always going adjacent to the BG line,some places BG line moves away from the MG line.
Now what is the design proposal?The new BG is going to exactyly replace the existing MG line or it is designed to be laid parallel to existing BG line?