Old January 8th, 2010, 01:02 PM   #81
youzef
Registered User
 
Join Date: Nov 2009
Posts: 95
Likes (Received): 0

Quote:
Originally Posted by youzef View Post
Do you know why progress in block A is ahead by 2 levels ?
Any update? , does the work proceeded in Block B ?Is the next billing notice will be next month ?

Last edited by youzef; January 8th, 2010 at 01:38 PM.
youzef no está en línea   Reply With Quote

Sponsored Links
 
Old January 12th, 2010, 05:32 PM   #82
youzef
Registered User
 
Join Date: Nov 2009
Posts: 95
Likes (Received): 0

Quote:
Originally Posted by nismoboy View Post
Progress as at 1 January 2010.

Block A - Foundation work began on Level 8.
Block B - Foundation work still at Level 6.

The whole site was closed. I guess New Year is a big day for all.
I send Enquiry to IJM they said it reached Level 9 for Menara B ( as below link)
how come you said Menara B still level 6 ?

Last edited by youzef; May 20th, 2010 at 08:46 PM.
youzef no está en línea   Reply With Quote
Old January 13th, 2010, 03:14 AM   #83
nismoboy
Registered User
 
Join Date: Aug 2009
Posts: 42
Likes (Received): 0

Quote:
Originally Posted by youzef View Post
I send Enquiry to IJM they said it reached Level 9 for Menara B ( as below link)
how come you said Menara B still level 6 ?

http://helpdesk.ijmproperties.com/in...BhbGFobGkuY29t
No idea. But don't you find it strange? If it is now at Level 9, you and I would have received the 2(b) notice for payment. I'm still waiting.
nismoboy no está en línea   Reply With Quote
Old January 13th, 2010, 08:27 PM   #84
youzef
Registered User
 
Join Date: Nov 2009
Posts: 95
Likes (Received): 0

Quote:
Originally Posted by nismoboy View Post
No idea. But don't you find it strange? If it is now at Level 9, you and I would have received the 2(b) notice for payment. I'm still waiting.
I share this with u, as my position the only thing I can do is just waiting (I am living oversea)
youzef no está en línea   Reply With Quote
Old January 14th, 2010, 03:04 AM   #85
nismoboy
Registered User
 
Join Date: Aug 2009
Posts: 42
Likes (Received): 0

Quote:
Originally Posted by youzef View Post
I share this with u, as my position the only thing I can do is just waiting (I am living oversea)
Bottom line, as at 1 Jan 2010 my 20/20 visual sight of the site is per earlier thread.

Irrespective of the progress, we should be hoping that they keep to their promise to complete it by mid-2011.

Cheers.
nismoboy no está en línea   Reply With Quote
Old January 14th, 2010, 12:44 PM   #86
youzef
Registered User
 
Join Date: Nov 2009
Posts: 95
Likes (Received): 0

Quote:
Originally Posted by nismoboy View Post
Bottom line, as at 1 Jan 2010 my 20/20 visual sight of the site is per earlier thread.

Irrespective of the progress, we should be hoping that they keep to their promise to complete it by mid-2011.

Cheers.
Agree
youzef no está en línea   Reply With Quote
Old January 15th, 2010, 09:42 AM   #87
youzef
Registered User
 
Join Date: Nov 2009
Posts: 95
Likes (Received): 0

Quote:
Originally Posted by youzef View Post
Agree
According to IJM they target stage 2 b on March , I am fully understand your concern , the project will be completed at least on Sep 11

Last edited by youzef; January 15th, 2010 at 04:32 PM.
youzef no está en línea   Reply With Quote
Old January 16th, 2010, 04:38 PM   #88
nismoboy
Registered User
 
Join Date: Aug 2009
Posts: 42
Likes (Received): 0

Quote:
Originally Posted by youzef View Post
According to IJM they target stage 2 b on March , I am fully understand your concern , the project will be completed at least on Sep 11
Thanks for your update.
nismoboy no está en línea   Reply With Quote
Old January 27th, 2010, 04:07 PM   #89
youzef
Registered User
 
Join Date: Nov 2009
Posts: 95
Likes (Received): 0

Quote:
Originally Posted by nismoboy View Post
Thanks for your update.
Is LB is success project, what is the basis?
How many units are left?
Is the location perfect?

Last edited by youzef; January 28th, 2010 at 11:53 AM.
youzef no está en línea   Reply With Quote
Old January 31st, 2010, 05:11 PM   #90
nismoboy
Registered User
 
Join Date: Aug 2009
Posts: 42
Likes (Received): 0

Quote:
Originally Posted by youzef View Post
ok

Your expectation is

2b Feb 2010
2c April 2010
2e Aug 2010
2f Oct 2010
2g Dec 2010
3 Feb 2011
4 Apr 2011
5 Jun 2011

Agree ? the critical part is year 2010 ?
Progress as at 31 January 2010.

Block A - Level 11 (unsold > 10 units)
Block B - Level 7 (unsold = 5 units)
Penthouses (all 4 units) still available.
Show house will be teared down after Feb.

Youzef - Get ready your 15%. Latest by March.

Target completion - on track (May/June 2011)

Last edited by nismoboy; January 31st, 2010 at 05:16 PM. Reason: typo error
nismoboy no está en línea   Reply With Quote
Old February 1st, 2010, 03:19 PM   #91
mah
Registered User
 
Join Date: Jan 2010
Posts: 9
Likes (Received): 0

thanks for the updates on LB
mah no está en línea   Reply With Quote
Old March 4th, 2010, 04:47 PM   #92
youzef
Registered User
 
Join Date: Nov 2009
Posts: 95
Likes (Received): 0

Quote:
Originally Posted by nismoboy View Post
Progress as at 31 January 2010.

Block A - Level 11 (unsold > 10 units)
Block B - Level 7 (unsold = 5 units)
Penthouses (all 4 units) still available.
Show house will be teared down after Feb.

Youzef - Get ready your 15%. Latest by March.

Target completion - on track (May/June 2011)
We are waiting for your frequent update in progress. notice, where will you pay since there is no show room?
youzef no está en línea   Reply With Quote
Old March 7th, 2010, 02:50 PM   #93
nismoboy
Registered User
 
Join Date: Aug 2009
Posts: 42
Likes (Received): 0

Progress as at 7 March 2010

Block A - Foundation works started on Level 13
Block B - Foundation works started on Level 8
nismoboy no está en línea   Reply With Quote
Old March 9th, 2010, 01:49 PM   #94
mah
Registered User
 
Join Date: Jan 2010
Posts: 9
Likes (Received): 0

Do u think there will be a delay with current progress?
Though they told me it is on schedule for May 2011.
The showroom will be thr for another 2 months as i was told last week.
mah no está en línea   Reply With Quote
Old March 9th, 2010, 04:11 PM   #95
youzef
Registered User
 
Join Date: Nov 2009
Posts: 95
Likes (Received): 0

Quote:
Originally Posted by mah View Post
Do u think there will be a delay with current progress?
Though they told me it is on schedule for May 2011.
The showroom will be thr for another 2 months as i was told last week.
The show room will remain due to empty units, but my concern why the big gap

in progress between Block B and A, what is reasons?

Is it the Bank supplier? , is bank in Block B different than Block A?

Is it technical reasons?

Last edited by youzef; March 9th, 2010 at 04:17 PM.
youzef no está en línea   Reply With Quote
Old March 9th, 2010, 05:21 PM   #96
nismoboy
Registered User
 
Join Date: Aug 2009
Posts: 42
Likes (Received): 0

Mah

I would be in the mindset that the project will be completed as per scheduled. At the rate of 1-1.5 level(s) per month (realistically). But I do notice that during public holidays and Sundays, no one is working at the site! IJM Land really treats their workers (not slave drivers).

Youzef

Whether Block A completes first or not, the whole project will need to be completed as a whole before VP or CF could be issued. So dun worry.

As a matter of fact, I prefer it slow and steady... let the cement dries/set more thoroughly. I have just been to The Peak, Cheras to be a busybody for my colleague, many cracks in almost every room. The developer tried to rush to complete it ahead of schedule. But now, the rectification works will take some months. I certainly do not want that. Heart sick for 1/2 million of hard earned future salary!

Have a productive day ahead......
nismoboy no está en línea   Reply With Quote
Old March 19th, 2010, 04:06 AM   #97
nismoboy
Registered User
 
Join Date: Aug 2009
Posts: 42
Likes (Received): 0

nismoboy no está en línea   Reply With Quote
Old April 6th, 2010, 07:20 PM   #98
wahonn
Registered User
 
Join Date: Aug 2009
Posts: 47
Likes (Received): 0

I wondering whether IJM is able to complete the entire condo in the next 1 year? Since they are only at about Level 9 Block B now ...

Anyone here has the site progress update photo ? Appreciate if you share the photo here ...

Thanks
wahonn no está en línea   Reply With Quote
Old April 8th, 2010, 10:10 PM   #99
youzef
Registered User
 
Join Date: Nov 2009
Posts: 95
Likes (Received): 0

i received 2(b) notice for the 9th floor. keep on updating
youzef no está en línea   Reply With Quote
Old April 8th, 2010, 10:13 PM   #100
wahonn
Registered User
 
Join Date: Aug 2009
Posts: 47
Likes (Received): 0

Great ! I am looking forward to receiving the 2(b) for Level 12 !
wahonn no está en línea   Reply With Quote


Reply

Thread Tools
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off



All times are GMT +2. The time now is 10:33 PM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2013, vBulletin Solutions, Inc.
Feedback Buttons provided by Advanced Post Thanks / Like v3.1.2 (Pro) - vBulletin Mods & Addons Copyright © 2013 DragonByte Technologies Ltd.
vBulletin Optimisation provided by vB Optimise (Pro) - vBulletin Mods & Addons Copyright © 2013 DragonByte Technologies Ltd. (Resources saved on this page: MySQL 25.00%)

SkyscraperCity - In Urbanity We Trust

Hosted by Blacksun, dedicated to this site too!
Forum server management by DaiTengu