Gurgaon Metro | Rapid Metro Rail Gurgaon (RMRG)


Official Website

Gurgaon's 5.1 km long rapid metro system was opened on November 2013.

System Info:


Route Maps:




Rolling Stock:

- built by CSR Zhuzhou ELW for Siemens mobility

Phase II of the system in which the line will be extended further south is currently U/C will open sometime in 2015.

Phase II Map:
Click to view large



Stub on Wikipedia:
http://en.wikipedia.org/wiki/Gurgaon_Metro
__________________
Vaguely heretical thoughts on travel technology at Gyrovague | Map and share your flights at OpenFlights

n20 liked this post

Last edited by IU; November 15th, 2013 at 09:51 PM.
jpatokal no está en línea   Reply With Quote

Sponsored Links
 
Old July 16th, 2009, 08:36 AM   #2
todscreen
Registered User
 
Join Date: Jun 2007
Location: Mumbai/ Atlanta
Posts: 1,600
Likes (Received): 8

are yaar, ye saabh kya hey?

mods, pls merge this back into the delhi metro thread. Having a separate thread for the same metro and its subsidiaries will become a clutter later on.
__________________
K O L K A T A

Bengali Review: First ever user-generated review site for Bengali movies, restaurants, and events.
todscreen no está en línea   Reply With Quote
Old July 16th, 2009, 09:23 AM   #3
Abhishek901
Registered User
 
Abhishek901's Avatar
 
Join Date: May 2009
Posts: 10,316
Likes (Received): 372

Gurgaon metro link to be completed in 30 months

Quote:
GURGAON: A year after floating tenders, the Haryana government gave the go-ahead to India's first entirely private Metro rail network that will connect Gurgaon to Delhi Metro's Sikanderpur station. The rail network, which involves an investment of Rs 900 crore, would be complete in 30 months from the date of award of the project. A major portion of the 6.1km elevated stretch would have a single track providing one-way movement.

The network to be called Gurgaon Metro Rail Link (GMRL) will benefit an estimated 1 lakh commuters, particularly the daily workforce. According to the design, the rail line takes off and terminates at Sikanderpur covering both residential and commercial areas of DLF-II, DLF-III and Cyber City. The approximately 1.2km stretch between Sikanderpur Metro station and DLF-II would have double tracks, while the rest would have a single track. So, a train will start from Sikanderpur station and terminate at the same after covering the entire stretch. The trains would draw power from the third rail running underneath. The GMRL would be connected to the station through a 90m-long walkway.

Originally, Haryana Urban Development Authority (HUDA) had floated a tender for a 3.2km-long Metro link between Sikanderpur and NH-8 worth Rs 500 crore. Though realty major DLF had envisaged the project in 2007 to provide connectivity to Cyber City, Haryana government had objected to the idea of a private player using public transport for profit making. DLF owns most part of Cyber City and a majority of the land on this stretch.

Now, according to the modified proposal, the 6.1km elevated corridor will have six stations Sikanderpur, DLF-II, Belvedere Tower, DLF-III, Gateway Tower touching NH-8 and Mall of India which government officials claim would serve the "real purpose of the new mode of public transport''.

All the platforms will have special screen doors and even dead-ends of the platforms would have glass screens. These doors will separate the platform from the track to prevent accidents and also permit higher arrival and departure speeds for trains. Besides, it would also increase the service frequency significantly.

The initial frequency of trains with three coaches would be three minutes and each coach would have a capacity of 300 passengers. While the average speed would be 30kmph, the maximum speed is 80kmph. The design of the train is yet to be decided, but sources said it would be a medium Metro. A standard fare of Rs 10 has been fixed for the entire stretch.

Haryana government sources said the consortium would pay Rs 765 crore to HUDA as connectivity charges over the next 35 years. It will also pay a certain percentage in the range of 5-10% of the revenue earnings from advertisement rights and property development to HUDA. The government is yet to hand over the letter of intent to the consortium.
Source: Times of India
Abhishek901 no está en línea   Reply With Quote
Old July 16th, 2009, 10:18 AM   #4
Kewl Batty
When it rains, it pours!
 
Join Date: Sep 2008
Location: Amsterdam
Posts: 2,695
Likes (Received): 11

Finally!!
Kewl Batty no está en línea   Reply With Quote
Old July 16th, 2009, 04:57 PM   #5
numb.soul
Registered User
 
numb.soul's Avatar
 
Join Date: May 2008
Location: gurgaon
Posts: 1,958
Likes (Received): 33

Gurgaon Metro Link To Be Completed In 30 Months

A year after floating tenders, the Haryana government gave the go-ahead to India's first entirely private Metro rail network that will connect Gurgaon to Delhi Metro's Sikanderpur station. The rail network, which involves an investment of Rs 900 crore, would be complete in 30 months from the date of award of the project. A major portion of the 6.1km elevated stretch would have a single track providing one-way movement.


The network to be called Gurgaon Metro Rail Link (GMRL) will benefit an estimated 1 lakh commuters, particularly the daily workforce. According to the design, the rail line takes off and terminates at Sikanderpur covering both residential and commercial areas of DLF-II, DLF-III and Cyber City. The approximately 1.2km stretch between Sikanderpur Metro station and DLF-II would have double tracks, while the rest would have a single track. So, a train will start from Sikanderpur station and terminate at the same after covering the entire stretch. The trains would draw power from the third rail running underneath. The GMRL would be connected to the station through a 90m-long walkway.
Originally, Haryana Urban Development Authority (HUDA) had floated a tender for a 3.2km-long Metro link between Sikanderpur and NH-8 worth Rs 500 crore. Though realty major DLF had envisaged the project in 2007 to provide connectivity to Cyber City, Haryana government had objected to the idea of a private player using public transport for profit making. DLF owns most part of Cyber City and a majority of the land on this stretch.

Source: Times Of India
__________________
Time will Tell

Last edited by numb.soul; July 16th, 2009 at 05:59 PM.
numb.soul no está en línea   Reply With Quote
Old July 16th, 2009, 07:25 PM   #6
bains1971
ताज़ा समाचार
 
bains1971's Avatar
 
Join Date: Sep 2008
Posts: 634
Likes (Received): 5

This is not a part of Delhi metro or is it ?
Will it be linked to the Delhi Metro ?
__________________
The Athletes' Village for the Commonwealth Games in New Delhi has been officially opened and described as "better than the Beijing Olympics" by Craig Hunter, the Chef de Mission for England's team.
The dates for the Games are 3 - 14 October 2010, inclusive of the Opening and Closing Ceremonies. Weather wise the city experiences an October mean temperature of a minimum 17.2 degrees centigrade and maximum 31.3 degrees centigrade with humidity ranging from 31 to 78% for the October and November months.
Punjab Aviation in India
bains1971 no está en línea   Reply With Quote
Old July 16th, 2009, 07:33 PM   #7
Kewl Batty
When it rains, it pours!
 
Join Date: Sep 2008
Location: Amsterdam
Posts: 2,695
Likes (Received): 11

They may integrate it with Delhi Metro but dont think it'll be connected to Delhi Metro.. Coz the technology is different.. Delhi Metro uses over head cables and this one uses third rail.
Kewl Batty no está en línea   Reply With Quote
Old July 17th, 2009, 02:04 AM   #8
IU
->
 
IU's Avatar
 
Join Date: Apr 2006
Location: Hanooz Dilli dur ast
Posts: 10,492

Good to see the project finally taking off. DLF wanted to start building it in 2007 but the babus in Chandigarh weren't in favor of the revenue sharing model and in general money being made by a private firm and not a govt body.

btw CBK Rao is the head of this network. He used to be #2 at Delhi metro until 2007.
IU no está en línea   Reply With Quote
Old July 17th, 2009, 03:37 AM   #9
european
Registered User
 
european's Avatar
 
Join Date: Oct 2005
Posts: 1,483
Likes (Received): 17

i say privatise the whole of NCR atleast ehn we would have one city in india upto good standards.
european no está en línea   Reply With Quote
Old August 11th, 2009, 11:48 AM   #10
ajithv
BANNED
 
Join Date: Jan 2007
Location: Thiruvananthapuram
Posts: 10,628
Likes (Received): 328

DLF, IL&FS consortium plans to raise Rs7bn for metro rail project

DLF Ltd has announced a metro rail project for its townships in Gurgaon with a project cost of Rs 9bn, according to a report.

A consortium of India' DLF Ltd and IL&FS plans to raise Rs7bn to part fund the construction of a metro rail system in New Delhi suburbs.

The 'DLF MetroRail, Gurgaon' project has been bagged on concession by the consortium for a period of 99 years to build and operate the metro sytem, report stated.

The report stated that the mode of fund raising would be decided later. The 6.1 km metro link with standard gauge line would be completed within the next 30 months.

Source
ajithv no está en línea   Reply With Quote
Old August 11th, 2009, 11:59 PM   #11
Abhishek901
Registered User
 
Abhishek901's Avatar
 
Join Date: May 2009
Posts: 10,316
Likes (Received): 372

Wink Coming back to the topic of Gurgaon metro

Quote:
Foundation laid for DLF Metro

That the millennium city's public transport is in a mess is anybody's guess. But finally it came from Haryana chief minister Bhoopinder Singh Hooda on Tuesday. So, what made the CM admit the `nightmare', especially when elections are round the corner?

Perhaps, a sign that things are improving. Hooda on Tuesday laid the foundation stone of India's first privately-owned public transport network, the Gurgaon Metro Rail Project (GMRP), which seeks to serve as a feeder network to Delhi Metro's Central Secretariat-Gurgaon. "The DLF Metro and Delhi Metro will change the way the city travels,'' said Hooda.

GMRP executive director CBK Rao said that the 6.1km-long stretch will be integrated with DMRC's central secretariat-Gurgaon line at Sikandarpur. "The two stations will be connected through an elevated walkway 90metre-long and 9metre-wide. Passengers should be able to interchange between the lines without having to go on the road,'' said Rao, adding that the timing of the two networks will be synchronized so that passengers have enough time on their hands for switch-over. Rao added that that there will be common ticketing system for both the Metro systems. It's expected to benefit 1 lakh commuters everyday, especially the workforce in DLF cyber city.

The DLF Metro to be constructed at an estimated cost of Rs 900crore will include six stations Sikanderpur, DLF Phase-II, DLF Phase-III, DLF Cyber City, Mall of India and DLF Gateway Tower. At one point in Sikanderpur, the Metro track will go above the DLF line. "There will be gap of 4 meters at that point,'' Rao said.

The loop-like rail line takes off and terminates at Sikanderpur covering both residential and commercial areas of DLF-II, DLF-III and Cyber City. The approximately 1.2km stretch between Sikanderpur Metro station and DLF-II would have double tracks, while the rest would be single track.

The trains would draw power from the third rail that will run underneath the tracks. All the platforms will have special screen doors and even dead-ends of the platforms would have glass screens. These doors will separate the platform from the track to prevent accidents and also permit higher arrival and departure speeds for trains.

The initial frequency of trains with three coaches would be three minutes and each coach would have a capacity of 300 passengers. While the average speed would be 30kmph, the maximum will be 80kmph. The design of the train is yet to be decided, but sources said it would be a medium Metro. A standard fare of Rs 10 has been fixed for the entire stretch.

Though all six stations will have drinking water and public convenience facilities, there is no provision for parking in station area. But 250 sq feet area will be given for commercial activities at each station, said Rao.
Times of India
Abhishek901 no está en línea   Reply With Quote
Old August 14th, 2009, 05:29 AM   #12
jpatokal
Registered User
 
Join Date: Jan 2005
Posts: 388
Likes (Received): 8

Foundation stone laid

And getting back on topic

__________________
Vaguely heretical thoughts on travel technology at Gyrovague | Map and share your flights at OpenFlights
jpatokal no está en línea   Reply With Quote
Old August 19th, 2009, 02:51 PM   #13
Euromast
Mast Malang
 
Euromast's Avatar
 
Join Date: Apr 2007
Location: Raania da pind
Posts: 5,620
Likes (Received): 452

Euromast está en línea ahora   Reply With Quote
Old September 16th, 2009, 06:35 AM   #14
jpatokal
Registered User
 
Join Date: Jan 2005
Posts: 388
Likes (Received): 8

__________________
Vaguely heretical thoughts on travel technology at Gyrovague | Map and share your flights at OpenFlights
jpatokal no está en línea   Reply With Quote
Old October 26th, 2009, 01:26 AM   #15
IchimaruGin1
BANNED
 
Join Date: Jul 2009
Posts: 3,105
Likes (Received): 1

lol this thread is fun to say the least

the poll hurdle is bit of a non issue. the project will still go along as planned. Probably 2-3 months behind

plus my question is this,

honestly wont a tram service or monorail be better suited for this than a metro?
IchimaruGin1 no está en línea   Reply With Quote
Old October 27th, 2009, 05:18 AM   #16
jpatokal
Registered User
 
Join Date: Jan 2005
Posts: 388
Likes (Received): 8

Quote:
Originally Posted by IchimaruGin1 View Post
honestly wont a tram service or monorail be better suited for this than a metro?
Obviously the technology hasn't been announced yet, but it's not going to be a "real" metro, more like an LRT. The specs say 75m platforms and 3-car trains with a total capacity of 300, vs 300 pax in a single car of the Delhi Metro, so you're probably looking at something like Crystal Mover or Bombardier CX-100/Innovia:



Both of those take around 100 people per car, so 3 x 100 = 300 as required.
__________________
Vaguely heretical thoughts on travel technology at Gyrovague | Map and share your flights at OpenFlights
jpatokal no está en línea   Reply With Quote
Old November 13th, 2009, 01:11 PM   #17
Abhishek901
Registered User
 
Abhishek901's Avatar
 
Join Date: May 2009
Posts: 10,316
Likes (Received): 372



Hindustan Times
Abhishek901 no está en línea   Reply With Quote
Old November 13th, 2009, 02:56 PM   #18
Abhishek901
Registered User
 
Abhishek901's Avatar
 
Join Date: May 2009
Posts: 10,316
Likes (Received): 372

Quote:
Originally Posted by jpatokal View Post
Obviously the technology hasn't been announced yet, but it's not going to be a "real" metro, more like an LRT. The specs say 75m platforms and 3-car trains with a total capacity of 300, vs 300 pax in a single car of the Delhi Metro, so you're probably looking at something like Crystal Mover or Bombardier CX-100/Innovia:



Both of those take around 100 people per car, so 3 x 100 = 300 as required.
According to above article, capacity of each coach is 300, so total capacity is 900. It won't be like a people mover.
Abhishek901 no está en línea   Reply With Quote
Old November 13th, 2009, 06:45 PM   #19
Advait
Registered User
 
Join Date: Jul 2009
Posts: 191
Likes (Received): 0

Quote:
Originally Posted by jpatokal View Post
Obviously the technology hasn't been announced yet, but it's not going to be a "real" metro, more like an LRT. The specs say 75m platforms and 3-car trains with a total capacity of 300, vs 300 pax in a single car of the Delhi Metro, so you're probably looking at something like Crystal Mover or Bombardier CX-100/Innovia:



Both of those take around 100 people per car, so 3 x 100 = 300 as required.
100 people per coach is highly doubtful claim if it is like the pictures shown above. Coaches like the one above have people mostly standing and it is similar to a inter-terminal shuttle you find on large airports. The LRT on the right is used in Singapore as a feeder to two metro stations and thereafter not used elsewhere. Their experience is mixed itseems as it has been reported to break-down often. It's basically a bus with a gripper underneath to confine the bus to move along a rail at the centre. And it is slow and unmanned. Might as well put a bus on elevated feeder busway at closely spaced intervals.
Advait no está en línea   Reply With Quote
Old November 14th, 2009, 10:18 AM   #20
jpatokal
Registered User
 
Join Date: Jan 2005
Posts: 388
Likes (Received): 8

Quote:
Originally Posted by Advait View Post
The LRT on the right is used in Singapore as a feeder to two metro stations and thereafter not used elsewhere. Their experience is mixed itseems as it has been reported to break-down often. It's basically a bus with a gripper underneath to confine the bus to move along a rail at the centre. And it is slow and unmanned. Might as well put a bus on elevated feeder busway at closely spaced intervals.
Singapore's Bukit Panjang LRT (right pic above) was indeed a failure for the reasons you list, but the Japanese-built Sengkang, Punggol and Changi Airport LRTs have been quite reliable.

But this is all speculation and the media always muddles up its figures, let's see what the actual tenders say...
__________________
Vaguely heretical thoughts on travel technology at Gyrovague | Map and share your flights at OpenFlights
jpatokal no está en línea   Reply With Quote


Reply

Thread Tools
Rate This Thread
Rate This Thread:

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off



All times are GMT +2. The time now is 09:29 AM.


Powered by vBulletin® Version 3.8.8 Beta 1
Copyright ©2000 - 2014, vBulletin Solutions, Inc.
Feedback Buttons provided by Advanced Post Thanks / Like v3.2.5 (Pro) - vBulletin Mods & Addons Copyright © 2014 DragonByte Technologies Ltd.

vBulletin Optimisation provided by vB Optimise (Pro) - vBulletin Mods & Addons Copyright © 2014 DragonByte Technologies Ltd.

SkyscraperCity ☆ In Urbanity We trust ☆ about us | privacy policy | DMCA policy

Hosted by Blacksun, dedicated to this site too!
Forum server management by DaiTengu