PVNR Expressway

image hosted on flickr



image hosted on flickr



image hosted on flickr



image hosted on flickr
pvk no está en línea   Reply With Quote

Sponsored Links
 
Old September 1st, 2009, 06:26 AM   #42
shanware
Registered User
 
shanware's Avatar
 
Join Date: Jul 2009
Posts: 1,215
Likes (Received): 1

All hail pvk !! Excellent job again !

Do we know if they're going to be able to stick to the October deadline that was mentioned ? Also, I'm kinda new to this thread. Are they going to open and operate both phases simultaneously ?
shanware no está en línea   Reply With Quote
Old September 1st, 2009, 10:59 AM   #43
ferrari_fan
Forza!
 
ferrari_fan's Avatar
 
Join Date: Jan 2006
Location: Chennai + Hyderabad
Posts: 3,619
Likes (Received): 152

Both phases? I thought it's one continuous expy? How will they inaugurate it in parts?

Cool updates PVK!!

I have a question that one of the HYD forumers could maybe clear for me - Mehdipatnam is where the expy starts right? Is this area considered to be a central part of HYD city or a distant suburb?

Because I found it very busy and crowded which seemed to mean it's a relatively important part of the city.. But at the same time it seemed very chaotic and disorganized and so seemed a little rural.. I was just wondering how native Hyderabadis think of this area..
ferrari_fan no está en línea   Reply With Quote
Old September 1st, 2009, 02:52 PM   #44
bobbie501
World Entertainer.
 
bobbie501's Avatar
 
Join Date: Sep 2007
Location: Hyderabad/Vizag,AP,Chicago,IL
Posts: 1,818
Likes (Received): 15

Quote:
Originally Posted by ferrari_fan View Post
Both phases? I thought it's one continuous expy? How will they inaugurate it in parts?

Cool updates PVK!!

I have a question that one of the HYD forumers could maybe clear for me - Mehdipatnam is where the expy starts right? Is this area considered to be a central part of HYD city or a distant suburb?

Because I found it very busy and crowded which seemed to mean it's a relatively important part of the city.. But at the same time it seemed very chaotic and disorganized and so seemed a little rural.. I was just wondering how native Hyderabadis think of this area..
Mehdipatnam is quite close to Central part of Hyderabad areas like Lakadikapul or even Basheerbagh but this area needs some attention when it comes to sanity since there are lot of engineering colleges situated near Chilkur this area is quite choatic with college goers & Business establishments.
__________________
"When I Don't Make Any Decision,It's Not That I Don't Think About It.I Think About It & Make A Decision Not To Make A Decision"-P.V.N.R

"Time itself is the solution to all problems." -P.V.N.R
bobbie501 no está en línea   Reply With Quote
Old September 1st, 2009, 06:06 PM   #45
viper9999
BANNED
 
Join Date: Jun 2007
Posts: 238
Likes (Received): 1

Quote:
Originally Posted by ferrari_fan View Post
Both phases? I thought it's one continuous expy? How will they inaugurate it in parts?

Cool updates PVK!!

I have a question that one of the HYD forumers could maybe clear for me - Mehdipatnam is where the expy starts right? Is this area considered to be a central part of HYD city or a distant suburb?

Because I found it very busy and crowded which seemed to mean it's a relatively important part of the city.. But at the same time it seemed very chaotic and disorganized and so seemed a little rural.. I was just wondering how native Hyderabadis think of this area..

At one point it was pretty much on the outer edge of the city, but with the city rapidly expanding, theres been quiet a bit of activity around here. The adv is the proximity to some of the central areas in the city. Definitely it doesnot qualify as any central business area or for that matter any prime area. Other than that, its just another area.
viper9999 no está en línea   Reply With Quote
Old September 2nd, 2009, 03:31 AM   #46
Babji
Registered User
 
Join Date: Mar 2006
Posts: 5,708
Likes (Received): 0

Quote:
Originally Posted by pvk View Post
PVNR Expressway
image hosted on flickr
excellent job, @pvk! thanks for sharing!
Babji no está en línea   Reply With Quote
Old September 6th, 2009, 04:50 PM   #47
Hindustani
Registered User
 
Join Date: Jul 2004
Posts: 4,015
Likes (Received): 7

Wink pvnr

Hindustani no está en línea   Reply With Quote
Old September 6th, 2009, 06:01 PM   #48
keshavasiva
CUPIDSTRUKWIDCUPID
 
keshavasiva's Avatar
 
Join Date: May 2007
Location: LAS VEGAS..NEVADA
Posts: 109
Likes (Received): 0

^
Looks perfect, but why do our Hyd planners always comprise for 2x2 lane roads.. Everywhere.. almost everywhere I go in hyd
__________________
ROCK IS DEAD!
keshavasiva no está en línea   Reply With Quote
Old September 6th, 2009, 06:57 PM   #49
Babji
Registered User
 
Join Date: Mar 2006
Posts: 5,708
Likes (Received): 0

Quote:
Originally Posted by keshavasiva View Post
^
Looks perfect, but why do our Hyd planners always comprise for 2x2 lane roads.. Everywhere.. almost everywhere I go in hyd
from 0 to 2X2 is not too bad, given the economic situation...
just to share my thoughts, there are several elevated roads and/or bridges (across rivers) in and around New York and Newark city areas -
some are new, some are old- but majority of them are 2X2 lane ...
Babji no está en línea   Reply With Quote
Old September 10th, 2009, 03:06 AM   #50
nh9
Registered User
 
Join Date: Jul 2009
Posts: 173
Likes (Received): 58

http://www.hindu.com/2009/09/10/stor...1059790300.htm

Major part of elevated expressway completed




Main structure to be ready by Oct. 2, say HMDA officials





--------------------------------------------------------------------------------

3,492 segments of the bridge were pre-cast

Seven girders used for erecting 291 spans


--------------------------------------------------------------------------------

HYDERABAD: Inching towards completion by the deadline of October 2, the last of the span of the P.V. Elevated Expressway was successfully erected here on Monday.

With this, the major super structure work of the entire 11.43 km expressway, longest elevated one in the country, has been completed.

According to the Hyderabad Metropolitan Development Authority (HMDA) officials, the last and the 327th span of the project was erected by launching girder and with that in place and completing the major aspect, other works for readying the expressway offering seamless access towards the airport at Shamshabad from Sarojinie Devi Eye Hospital were on. “The rest of finishing works such as black topping, median kerbing and road signage are in progress,” he said.

Modern techniques


The work was taken up using modern methods of construction and 3,492 segments of the bridge were pre-cast at the casting yards located at Shamshabad, transported to the site in trolleys and erected using launching girders.

Seven such girders were used to erect 291 spans, each span consisting of 12 pre-cast segments, while the balance of 36 spans were done in the conventional cast-in-situ method. While the main structure of the elevated expressway offering express drive from S.D. Eye Hospital to Aramgarh would be ready by October 2, ramps connecting it at different points would take few more months.

Rs.439 crore


Taken up with a contract value of Rs.439 crore, two other components of the project, an underpass at Aramgarh and a Trumpet Interchange were already completed.
nh9 no está en línea   Reply With Quote
Old September 16th, 2009, 03:05 AM   #51
Vara123
Registered User
 
Join Date: Jul 2007
Posts: 486
Likes (Received): 3

Trail Run on PVNR Expressway from September 25th

http://www.eenadu.net/district/distr...s=hyderabad#13

Brief Transalation

Trail Run on PVNR Expressway will begin from September 25th. Inauguration will be on October 2nd. Officials are thinking not to allow two wheelers on it.

This is cool.
Vara123 no está en línea   Reply With Quote
Old September 17th, 2009, 04:01 AM   #52
nh9
Registered User
 
Join Date: Jul 2009
Posts: 173
Likes (Received): 58

Anti Glare System for PVNR Express Way

http://www.andhrajyothy.com/mainshow...st/sep/17hyd10

The expressway will be equipped with latest anti glare system to prevent accidents during night times.
nh9 no está en línea   Reply With Quote
Old September 17th, 2009, 09:27 PM   #53
ferrari_fan
Forza!
 
ferrari_fan's Avatar
 
Join Date: Jan 2006
Location: Chennai + Hyderabad
Posts: 3,619
Likes (Received): 152

Quote:
Originally Posted by Vara123 View Post
http://www.eenadu.net/district/distr...s=hyderabad#13

Brief Transalation

Trail Run on PVNR Expressway will begin from September 25th. Inauguration will be on October 2nd. Officials are thinking not to allow two wheelers on it.

This is cool.
That's awesome!

ferrari_fan no está en línea   Reply With Quote
Old September 18th, 2009, 12:53 AM   #54
raghussc
Registered User
 
Join Date: Oct 2007
Posts: 1,753
Likes (Received): 102

Quote:
Originally Posted by Vara123 View Post
http://www.eenadu.net/district/distr...s=hyderabad#13

Brief Transalation

Trail Run on PVNR Expressway will begin from September 25th. Inauguration will be on October 2nd. Officials are thinking not to allow two wheelers on it.

This is cool.
that link does not work anymore but here is the link that will take u to the article in archives ..

http://www.eenadu.net/archives/archi...s=hyderabad#13
raghussc no está en línea   Reply With Quote
Old September 18th, 2009, 01:00 AM   #55
nh9
Registered User
 
Join Date: Jul 2009
Posts: 173
Likes (Received): 58

Hers is one more update in Hindu paper

http://www.hindu.com/2009/09/18/stor...1857830300.htm



HYDERABAD: With the main structure of the 11.5 km long P.V. Elevated Expressway ready and finishing works being attended to, the Hyderabad Metropolitan Development Authority (HMDA) is planning to allow trial runs from around September 27. The facility is to be formally declared open on October 2. For trial runs, the authorities are against allowing two-wheelers and also heavy vehicles. “The stretch is wide open with couple of sharp curves. Though signage is placed, we are wary of two-wheelers racing around dangerously,” says an official.

At the same time, there are apprehensions over having the heavy vehicles climb the expressway as there are no lay-bys created as of now.

“In case of a breakdown, shifting a heavy vehicle will be an issue as the expressway is 11.5 km long. And in absence of a lay-by, sort of widened section used for emergency parking, the traffic flow could be affected,” he says. The lay-bys could take some time to be in place on the elevated expressway as their design is linked to the ramps. Though the main expressway from S.D. Eye Hospital to Aramgarh Junction is getting ready for October 2 deadline, the work on ramps joining the facility at different points has remained stuck in problems such as shifting of water pipelines and also a place of worship at one place. However, the financial crunch has come to hit the country’s longest elevated expressway even at the stage of finishing works of the main structure. The HMDA has already run into heavy dues to the contractor and bills to the tune of Rs.20 crore are still to be cleared. The work in closing stages could get affected to some extent due to non-payment of bills, officials concede adding that each day, about 60 tonnes of bitumen, each tonne costing around Rs.38,000, is being used for the BT work. This alone comes to around Rs.24 lakh per day and without clearing pending amounts, the HMDA might find it hard to push for faster completion.
nh9 no está en línea   Reply With Quote
Old September 19th, 2009, 06:39 PM   #56
raghussc
Registered User
 
Join Date: Oct 2007
Posts: 1,753
Likes (Received): 102

Seems like PVNR expressway is finally getting ready .... the last segment was put up ..

Source: ExpressBuzz



PV Expressway inches closer to Oct 2 opening


HMDA Metropolitan Commissioner K S Jawahar Reddy inspects the PV Expressway on Thursday.
Hyderabad : 11 Sep 2009 10:42:55 AM IST

HYDERABAD: The HMDA on Thursday erected the last span of the 11.43 km PV Narasimha Rao Elevated Expressway. The late Chief Minister Y S Rajasekhara Reddy had instructed HMDA officials to ensure that the Expressway is thrown open to the public by October 2 i.e Gandhi Jayanti day.
With this, the major part of the super structure work of the country’s flyover has been completed.

The last and 327th Span of the Expressway was erected successfully through a Launching Girder.

Works like black topping, median kerbs, road signage are in progress. The Expressway will offer seamless connectivity from the Sarojini Devi Eye Hospital, Mehdipatnam to the International Airport at Shamshabad.
raghussc no está en línea   Reply With Quote
Old September 21st, 2009, 05:17 AM   #57
nh9
Registered User
 
Join Date: Jul 2009
Posts: 173
Likes (Received): 58

Fencing on PVNR ExpressWay

Hi Guys,
Has anybody been through the trumpet interchange at the airport.
When the airport approach road ends and after that GMR didn't take up the trumpet interchange. It was constructed by HMDA.

You can notice the sudden change in quality of the bridge i.e the trumpet interchange. Really it doesn't match the international quality. You can notice the poor quality of the fencing of the bridge.

My concern is today(9/21) I saw few pics of PVNR expressway on eenadu e-paper and the expressway looks 100% similar to the trumpet interchange bridge that is constructed over NH7. The road fencing doesn't look good. The city flyover fencings are far better than the PVNR expressway and the trumpet interchange bridge.

did anybody notice this before???? Check out the link

nh9 no está en línea   Reply With Quote
Old September 21st, 2009, 07:05 AM   #58
hyderabadnawab
Registered User
 
Join Date: Dec 2006
Location: New York / Hyderabad
Posts: 158
Likes (Received): 0

The whole contract of PV expressway involves the major structure (11.6 KM flyover), underpass at Aramgarh junction (IRR and NH7 Junction) and the trumpet interchange for airport. So, this has been given as a package to one developer. So, i am not surprised that the quality looks the same.

To match GMR's quality takes something. The more i go to the airport, more and more i'm impressed by the work GMR has done. (Not only the airport (external, internal) but also the connecting roads and signages etc..)
hyderabadnawab no está en línea   Reply With Quote
Old September 22nd, 2009, 07:51 PM   #59
Vara123
Registered User
 
Join Date: Jul 2007
Posts: 486
Likes (Received): 3

In some places the Expressway curves are not smooth.
Vara123 no está en línea   Reply With Quote
Old September 23rd, 2009, 02:24 AM   #60
kranthisb
Registered User
 
Join Date: Jul 2007
Posts: 7
Likes (Received): 0

PVNR express way video

this is the latest video of PVNR express way which is getting ready to be inaugurated

kranthisb no está en línea   Reply With Quote


Reply

Tags
hyd pvnr, hyderabad pvnr expressway

Thread Tools
Display Modes Rate This Thread
Rate This Thread:

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off



All times are GMT +2. The time now is 02:25 AM.


Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2013, vBulletin Solutions, Inc.
Feedback Buttons provided by Advanced Post Thanks / Like v3.1.2 (Pro) - vBulletin Mods & Addons Copyright © 2013 DragonByte Technologies Ltd.
vBulletin Optimisation provided by vB Optimise (Pro) - vBulletin Mods & Addons Copyright © 2013 DragonByte Technologies Ltd. (Resources saved on this page: MySQL 25.00%)

SkyscraperCity - In Urbanity We Trust

Hosted by Blacksun, dedicated to this site too!
Forum server management by DaiTengu