Old July 7th, 2018, 06:42 AM   #1
SSCwarrior
Registered User
 
Join Date: Aug 2016
Posts: 2,080
Likes (Received): 5254

Mumbai Trans-Harbour Bridge (MTHL) project

The Mumbai Trans Harbour Link (MTHL), also known as the Sewri-Nhava Sheva Trans Harbour Link, is an under-construction 21.8 km, freeway grade road bridge connecting the Indian city of Mumbai with Navi Mumbai, its satellite city. When completed, it would be the longest sea bridge in India.[1] The bridge will begin in Sewri, South Mumbai and cross Thane Creek north of Elephanta Island and will terminate at Chirle village, near Nhava Sheva. The road will be linked to the Mumbai Pune Expressway in the east, and to the proposed Western Freeway in the west.

The project is estimated to cost ₹14,262 crore (US$2.1 billion). The MMRDA awarded contracts for the project in November 2017; construction began in April 2018, and is scheduled to complete within four-and-a-half years.




__________________

Zaz965, KB335ci2, BadHatter liked this post
SSCwarrior no está en línea   Reply With Quote
Sponsored Links
Advertisement
 
Old July 7th, 2018, 06:46 AM   #2
SSCwarrior
Registered User
 
Join Date: Aug 2016
Posts: 2,080
Likes (Received): 5254

The longest sea crossing bridge in India is under way in Mumbai


India is increasing its focus on new infrastructure to support the country’s significant economic growth rates. The Mumbai Trans Harbour Link, a new 22.8 km sea crossing bridge, is an important part of this development.

The bridge will provide a crucial upgrade of the infrastructure connecting south Mumbai with Navi Mumbai and is expected to cut travel time by an hour.
Furthermore, the link will connect to to Nhava Sheva Port, Mumbai-Goa Highway, Mumbai-Pune Expressway and the upcoming Navi Mumbai International Airport. The link is an economic gateway and expected to boost the economic activity in the entire region.

The bridge will traverse through Sewri mudflats, Pir Pau Jetty and also Thane Creek channels. In a first for India, this project will also include an orthotropic steel deck crossing several obligatory navigation channels.

LONG-TIME WISH


The harbour link has been underway since the seventies and several suggestions for bridges have been made. The contracts are now signed and the works are expected to start this month with an estimated construction time around 4.5 years.

During 2016 and 2017 COWI provided the tender design for a contractor joint venture consisting of Larsen & Toubro Ltd (L&T) from India and IHI from Japan. The L&T-IHI JV was late 2017 awarded the Design-Build contract for package 1 of the project which with a length of more than 10km is the longest of the 3 packages. COWI has subsequently signed the contract for detailed design of package 1.

The design work will be a global COWI collaboration mobilising a strong team from Gurgaon in India, Copenhagen and London.

Project Director Lars Thornfeldt Sørensen has been heading the tender process.

”We had an excellent collaboration with the L&T-IHI JV during the tender stages and I am confident that this will continue in the detailed design phase. We have a great team and will deliver this fantastic bridge project.”

https://www.cowi.com/about/news-and-...-way-in-mumbai



Key facts
  • The Mumbai Trans Harbour Link (MHTL ) will connect Mumbai and Navi Mumbai and will have a total length of 22.8 km.

  • The more than 10km long Package 1 part of the project consists of an interchange connecting to the existing Eastern Highway in Mumbai and a combination of concrete box girder bridges and orthotropic steel box girder bridges. Construction cost for package 1 alone is approximately 1 billion Euro.

  • The Owner for MTHL is Mumbai Metropolitan Region Development Authority (MMRDA)

  • MMRDA has awarded contracts to a consortium of Larsen and Toubro (L&T) and Japan's IHI Corporation, a consortium of Daweoo and Tata Projects Limited (TPL), and L&T to construct the Sewri side of sea bridge (Package 1), the Navi Mumbai side of sea bridge (Package 2), and the bridge portion on land towards Chirle (Package 3), respectively.

  • Construction of the MTHL is expected to begin later this year and complete within four-and-a-half years.

__________________

Zaz965, SLASH_2, roaddor liked this post
SSCwarrior no está en línea   Reply With Quote
Old July 7th, 2018, 06:47 AM   #3
SSCwarrior
Registered User
 
Join Date: Aug 2016
Posts: 2,080
Likes (Received): 5254

L&T conducting soil testing throughout the route. Soil testing started in March and have almost been completed
cc Girish Jambekar





On sewri side.
Floating Piling deck is u/c. Casting yard is being set up next it on an abandoned port land



__________________
SSCwarrior no está en línea   Reply With Quote
Sponsored Links
Advertisement
 
Old July 7th, 2018, 09:56 PM   #4
Zaz965
Je suis kanonirsss
 
Zaz965's Avatar
 
Join Date: Jan 2015
Location: CCCP
Posts: 4,080
Likes (Received): 36561

thanks for posting
__________________

djole13 liked this post
Zaz965 no está en línea   Reply With Quote
Old October 20th, 2018, 05:03 AM   #5
SSCwarrior
Registered User
 
Join Date: Aug 2016
Posts: 2,080
Likes (Received): 5254

Portable piling rig has moved into the sea at Sewri side
PC: Sukhvinder Singh





L&T's RCD machine has been now been placed over casing. A small pooja was done on Tuesday to commence drilling.



How the drilling works



TATA projects-Daewoo executing package 2 of MTHL
PC: A R logistics


__________________
SSCwarrior no está en línea   Reply With Quote
Old December 11th, 2018, 01:10 PM   #6
SSCwarrior
Registered User
 
Join Date: Aug 2016
Posts: 2,080
Likes (Received): 5254

Quote:
Mumbai Trans harbour link is truly in u/c phase now. concrete poured for 1st permanent pile at Sewri
PC: MG Alkesh

image upload

other pics







PC: Ratishkumar nair
__________________

firoz bharmal, DJaCoNdA, SLASH_2, ENJINEER liked this post
SSCwarrior no está en línea   Reply With Quote
Old January 27th, 2019, 04:01 AM   #7
SSCwarrior
Registered User
 
Join Date: Aug 2016
Posts: 2,080
Likes (Received): 5254

Quote:
Originally Posted by Coolguyz View Post
TATA's casting yard on either side of Belapur creek.
Its concrete batch plant on barge can be seen marked in red circle

picture upload

best free image hosting no registration
MTHL on sewri side.
PC: Sukhvinder Singh
__________________

DJaCoNdA, Zaz965 liked this post
SSCwarrior no está en línea   Reply With Quote
Old February 28th, 2019, 08:07 AM   #8
SSCwarrior
Registered User
 
Join Date: Aug 2016
Posts: 2,080
Likes (Received): 5254

PC: @cowigroup











The flamingos seem happy!
__________________
SSCwarrior no está en línea   Reply With Quote
Old March 2nd, 2019, 01:29 AM   #9
Zaz965
Je suis kanonirsss
 
Zaz965's Avatar
 
Join Date: Jan 2015
Location: CCCP
Posts: 4,080
Likes (Received): 36561

good progress
__________________

djole13 liked this post
Zaz965 no está en línea   Reply With Quote
Old May 18th, 2019, 03:40 PM   #10
SSCwarrior
Registered User
 
Join Date: Aug 2016
Posts: 2,080
Likes (Received): 5254

April update









credits: Shailesh H
__________________

DJaCoNdA, BadHatter, ollo liked this post
SSCwarrior no está en línea   Reply With Quote
Old December 25th, 2019, 02:01 PM   #11
SSCwarrior
Registered User
 
Join Date: Aug 2016
Posts: 2,080
Likes (Received): 5254

Quote:
Worli- Sweri Connector which will connects MTHL and coastal road.This 4.5 km long elevated corridor in tender C stage








MTHL work progress as of Nov end





1)From Mumbai side
2)Navi Mumbai side

__________________
SSCwarrior no está en línea   Reply With Quote
Old January 14th, 2020, 02:45 PM   #12
SSCwarrior
Registered User
 
Join Date: Aug 2016
Posts: 2,080
Likes (Received): 5254

Sewri mudflats



PC: shahidkhan82
__________________

SLASH_2, Augustão d2 liked this post
SSCwarrior no está en línea   Reply With Quote
Sponsored Links
Advertisement
 


Reply

Thread Tools

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off



All times are GMT +2. The time now is 04:17 AM.


Powered by vBulletin® Version 3.8.11 Beta 4
Copyright ©2000 - 2020, vBulletin Solutions Inc.
vBulletin Security provided by vBSecurity v2.2.2 (Pro) - vBulletin Mods & Addons Copyright © 2020 DragonByte Technologies Ltd.
Feedback Buttons provided by Advanced Post Thanks / Like (Pro) - vBulletin Mods & Addons Copyright © 2020 DragonByte Technologies Ltd.

SkyscraperCity ☆ In Urbanity We trust ☆ about us