Old May 3rd, 2019, 01:38 AM   #1241
Bob Loblaw
Registered User
 
Join Date: Oct 2017
Posts: 37
Likes (Received): 55

Got the following email today:

ALIA Insider,

With spring here and the sun making more frequent appearances, we would like to share a project update with you. Since our celebratory launch event in mid-December, the response to ALIA has been tremendous. We have heard loud and clear over the past five years that Minneapolis is eager for a for-sale condominium of ALIA’s caliber at a preeminent location, and we are excited to be bringing that to the market.

As many of you know, our team is committed to and has a reputation for developing incredibly high quality buildings. In alignment with this commitment, we recently secured a fully executed term sheet with a new financing partner whose values will support us in delivering the best possible homes to our buyers. This is incredibly important and our diligence in assembling the correct team will be apparent by the extraordinary building that results.

Our site preparation is complete and our pre-development and construction planning efforts are continuing. We will be breaking ground as soon as we have completed the construction documents and finalized subcontractors for the project.

Thank you,

ALIA’s Development Team
Bob Loblaw no está en línea   Reply With Quote
Sponsored Links
Advertisement
 
Old May 3rd, 2019, 03:17 AM   #1242
go4guy
Registered User
 
Join Date: Mar 2014
Posts: 145
Likes (Received): 122

Quote:
Originally Posted by mspguy View Post
Why did they wait so long to get a better financing deal if they knew there was high interest in December!? That was six months ago. It could take several more months before we have any clarity on the status of this project.

We were a week away from the groundbreaking. Very disappointing.
Interest rates were still pretty high then. Much lower now and maybe at a point where it was worth finding a new financing package.

Also, an underwriter is going to be able to allow much more favorable terms with proof of reservations higher than they expected.
go4guy no está en línea   Reply With Quote
Old May 3rd, 2019, 04:29 PM   #1243
beykite
Registered User
 
beykite's Avatar
 
Join Date: Nov 2012
Location: Minneapolis
Posts: 60
Likes (Received): 123

Engineering CD's are still under development, and I know prelim bids for precast on the podium have gone out. Not sure on the status of architectural CD's. I know that doesn't add a ton of new info but thought I'd share.
__________________

Scott16475, TCMPLS liked this post
beykite no está en línea   Reply With Quote
Old May 3rd, 2019, 04:47 PM   #1244
RedDutch
Registered User
 
RedDutch's Avatar
 
Join Date: Oct 2014
Location: Minneapolis
Posts: 328
Likes (Received): 389

Quote:
Originally Posted by Bob Loblaw View Post
Got the following email today:

ALIA Insider,

With spring here and the sun making more frequent appearances, we would like to share a project update with you. Since our celebratory launch event in mid-December, the response to ALIA has been tremendous. We have heard loud and clear over the past five years that Minneapolis is eager for a for-sale condominium of ALIA’s caliber at a preeminent location, and we are excited to be bringing that to the market.

As many of you know, our team is committed to and has a reputation for developing incredibly high quality buildings. In alignment with this commitment, we recently secured a fully executed term sheet with a new financing partner whose values will support us in delivering the best possible homes to our buyers. This is incredibly important and our diligence in assembling the correct team will be apparent by the extraordinary building that results.

Our site preparation is complete and our pre-development and construction planning efforts are continuing. We will be breaking ground as soon as we have completed the construction documents and finalized subcontractors for the project.

Thank you,

ALIA’s Development Team
That is the update I received as well.
RedDutch no está en línea   Reply With Quote
Old May 7th, 2019, 07:15 PM   #1245
TCMPLS
Registered User
 
TCMPLS's Avatar
 
Join Date: Apr 2014
Posts: 860
Likes (Received): 756

Quote:
Originally Posted by Bob Loblaw View Post
Got the following email today:

ALIA Insider,

With spring here and the sun making more frequent appearances, we would like to share a project update with you. Since our celebratory launch event in mid-December, the response to ALIA has been tremendous. We have heard loud and clear over the past five years that Minneapolis is eager for a for-sale condominium of ALIA’s caliber at a preeminent location, and we are excited to be bringing that to the market.

As many of you know, our team is committed to and has a reputation for developing incredibly high quality buildings. In alignment with this commitment, we recently secured a fully executed term sheet with a new financing partner whose values will support us in delivering the best possible homes to our buyers. This is incredibly important and our diligence in assembling the correct team will be apparent by the extraordinary building that results.

Our site preparation is complete and our pre-development and construction planning efforts are continuing. We will be breaking ground as soon as we have completed the construction documents and finalized subcontractors for the project.

Thank you,

ALIA’s Development Team
Quote:
Originally Posted by RedDutch View Post
That is the update I received as well.


Looks like you too might be neighbors! Thank you both for sharing, it's nice to have some inside knowledge from those looking to buy here!


My hope is that Alia can get up and off the ground close to the same time as our other big two going up. Three tower cranes for these three projects are going to look great amongst the skyline
TCMPLS no está en línea   Reply With Quote
Old May 8th, 2019, 03:14 PM   #1246
Bob Loblaw
Registered User
 
Join Date: Oct 2017
Posts: 37
Likes (Received): 55

Quote:
Originally Posted by TCMPLS View Post
Looks like you too might be neighbors! Thank you both for sharing, it's nice to have some inside knowledge from those looking to buy here!


My hope is that Alia can get up and off the ground close to the same time as our other big two going up. Three tower cranes for these three projects are going to look great amongst the skyline
I simply wanted updates on the project so I signed up for their mailer. A high rise condo with an 8 month old doesn't really excite me.
Bob Loblaw no está en línea   Reply With Quote
Sponsored Links
Advertisement
 


Reply

Tags
alatus, bob lux, esg, high rise, minneapolis, northeast, tcnortheast

Thread Tools

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off



All times are GMT +2. The time now is 06:01 PM.


Powered by vBulletin® Version 3.8.11 Beta 4
Copyright ©2000 - 2019, vBulletin Solutions Inc.
vBulletin Security provided by vBSecurity v2.2.2 (Pro) - vBulletin Mods & Addons Copyright © 2019 DragonByte Technologies Ltd.
Feedback Buttons provided by Advanced Post Thanks / Like (Pro) - vBulletin Mods & Addons Copyright © 2019 DragonByte Technologies Ltd.

SkyscraperCity ☆ In Urbanity We trust ☆ about us