Old August 21st, 2008, 12:15 PM   #1
RawLee
Registered User
 
RawLee's Avatar
 
Join Date: Jul 2007
Location: Budapest
Posts: 9,458
Likes (Received): 1158

[Szeged] Villamos | Tram project

Since this big project already started(Debrecen will start in september),and we have a good source of infos and pics, I think it would be a good idea to start a separate thread for it!


The project is composed of the following:

-reconstruction of lines 1,3,3F,4
-extension of network for line 2
-extension of trolley network for lines 8,10
-reconstruction of squares Kossuth-Rókus roads,Anna-well-,Indóház-,Glattfeld squares
-Bertalan bridge bridgeheads reconstruction
-reconstruction of tram and trolley depots
-reconstruction of electrical substations
-new trams and trolleys
-bicycle routes and containers
-stations and platforms
-on-board electronics

The project started in 2008,and should be finished in 2011.

This is the current network of trolleys and trams:

(greens are trolleys,browns are trams)

And this will be the route of line 2:


Here's a map which includes both the plans for the trolleys and the trams:

Dark red is what is planned to be new trolley-routes,"dark" yellow is what will be reconstructed of the tramlines,and blue is new tramline.

Last edited by RawLee; August 21st, 2008 at 01:04 PM.
RawLee no está en línea   Reply With Quote
Sponsored Links
Advertisement
 
Old August 21st, 2008, 12:16 PM   #2
RawLee
Registered User
 
RawLee's Avatar
 
Join Date: Jul 2007
Location: Budapest
Posts: 9,458
Likes (Received): 1158

March 23rd, 2008
Quote:
Originally Posted by Qtya View Post
Beside the new tram line, Szeged will recieve two new (one reopened) trolley bus lines too...

RawLee no está en línea   Reply With Quote
Old August 21st, 2008, 12:17 PM   #3
RawLee
Registered User
 
RawLee's Avatar
 
Join Date: Jul 2007
Location: Budapest
Posts: 9,458
Likes (Received): 1158

Old May 29th, 2008
Quote:
Originally Posted by RawLee View Post
Some pics from the tramline projects in the city(pics are from http://www.ujpalyan.hu)

Junction plan of Rókus ringroad



Junction plan at Kálvária boulevard and Boross József street

Render of Indóház square

Stations at Anna-well, Glattfelder square and Szent György square





The plan of the bridgehead at Újszeged

Renders of the reconstructed tram depot




RawLee no está en línea   Reply With Quote
Sponsored Links
Advertisement
 
Old August 21st, 2008, 12:20 PM   #4
RawLee
Registered User
 
RawLee's Avatar
 
Join Date: Jul 2007
Location: Budapest
Posts: 9,458
Likes (Received): 1158

June 11th, 2008
Quote:
Originally Posted by RawLee View Post
3 weeks and the tram project will kick-off in Szeged!

http://www.delmagyar.hu/szeged_hirek...troli/2059800/

The article is dedicated to the history of public transport in the city



RawLee no está en línea   Reply With Quote
Old August 21st, 2008, 12:20 PM   #5
RawLee
Registered User
 
RawLee's Avatar
 
Join Date: Jul 2007
Location: Budapest
Posts: 9,458
Likes (Received): 1158

May 29th, 2008
Quote:
Originally Posted by RawLee View Post
2 other stations at the square of the Martyrs of Arad and Széchenyi square


RawLee no está en línea   Reply With Quote
Old August 21st, 2008, 12:24 PM   #6
RawLee
Registered User
 
RawLee's Avatar
 
Join Date: Jul 2007
Location: Budapest
Posts: 9,458
Likes (Received): 1158

July 18th, 2008
Quote:
Originally Posted by Fricy View Post
The tram reconstruction work started on 15th of July.



More pictures here:
http://www.indohaz.hu/rovatok/hir/hv...annakut080717/
The more pics:












RawLee no está en línea   Reply With Quote
Old August 21st, 2008, 12:27 PM   #7
RawLee
Registered User
 
RawLee's Avatar
 
Join Date: Jul 2007
Location: Budapest
Posts: 9,458
Likes (Received): 1158

August 9th, 2008
Quote:
Originally Posted by Fricy View Post
New photos about the construction of tram tracks:



http://www.indohaz.hu/rovatok/hir/hv...nna-kut080805/
More pics from that source:











RawLee no está en línea   Reply With Quote
Old August 21st, 2008, 12:28 PM   #8
RawLee
Registered User
 
RawLee's Avatar
 
Join Date: Jul 2007
Location: Budapest
Posts: 9,458
Likes (Received): 1158

August 13th, 2008
Quote:
Originally Posted by RawLee View Post
Anna-well:state of works

http://www.delmagyar.hu/szeged_hirek...godor/2064955/

Szeged - Egy hete startolt el a villamosprojekt, a 2011-ben befejeződő, közel 30 milliárd forintos beruházás. A kivitelezők mára érnek a bontási munkálatok végére, az Anna-kútnál jelenleg egy nagy gödör tátong.



















Delays at Anna-well

http://www.delmagyar.hu/szeged_hirek...pitok/2066659/

Szeged - Lassan halad az Anna-kúti építkezés. Adminisztrációs csúszás után az előkészítésnél is adódtak problémák. A hosszadalmas bontás után most az építők próbálják behozni a késést – mától túlórával, majd vasárnapi munkával. Szeptember 19-ére várhatjuk a villamosforgalom újraindítását.

RawLee no está en línea   Reply With Quote
Old August 21st, 2008, 12:30 PM   #9
RawLee
Registered User
 
RawLee's Avatar
 
Join Date: Jul 2007
Location: Budapest
Posts: 9,458
Likes (Received): 1158

Works continued even on the 20th of August

http://www.delmagyar.hu/szeged_hirek...oztak/2067807/

Szeged - Az Anna-kút építői dolgoztak az ünnepen, hogy tartsák a határidőt, máskülönben napi 15 millió forintos kötbért fizethetnek. A Szabadkai úti körforgalomban viszont csend volt tegnap, pihenőnapot kaptak a munkások.




Anna-well:if constructor behind schedule,15 million/day is the fine

http://www.delmagyar.hu/szeged_hirek...otber/2067351/

Szeged - Új határidőkben állapodott meg a városvezetés az Anna-kúti csomópont felújítását végző generálkivitelezővel. A villamosok szeptember 23-ától, az autók és a buszok október 21-étől használhatják ismét a kereszteződést.













RawLee no está en línea   Reply With Quote
Old September 3rd, 2008, 09:03 PM   #10
RawLee
Registered User
 
RawLee's Avatar
 
Join Date: Jul 2007
Location: Budapest
Posts: 9,458
Likes (Received): 1158

From Webrádió:
























RawLee no está en línea   Reply With Quote
Old September 3rd, 2008, 09:44 PM   #11
Kontúr
Hajrá Magyarország!
 
Kontúr's Avatar
 
Join Date: Mar 2008
Location: Budapest
Posts: 959
Likes (Received): 13

Do you know anything about the new tram tender?
Kontúr no está en línea   Reply With Quote
Old September 3rd, 2008, 09:47 PM   #12
RawLee
Registered User
 
RawLee's Avatar
 
Join Date: Jul 2007
Location: Budapest
Posts: 9,458
Likes (Received): 1158

Quote:
Originally Posted by Kontúr View Post
Do you know anything about the new tram tender?
They will have to be ordered in a year,if I get it right:

http://www.ujpalyan.hu/index.php?opt...d=47&Itemid=58

Típusengedély
Villamos elvi előzetes típusengedély

Engedélyező hatóság: Nemzeti Közlekedési Hatóság, Kiemelt Ügyek Igazgatósága
Engedély száma: KU/VF/1729/1/2007
Engedély dátuma: 2007.november 5.
Engedély érvényessége: 2009.november 5.
RawLee no está en línea   Reply With Quote
Old September 3rd, 2008, 09:57 PM   #13
Kontúr
Hajrá Magyarország!
 
Kontúr's Avatar
 
Join Date: Mar 2008
Location: Budapest
Posts: 959
Likes (Received): 13

Hát ez nekem sem túl egyértelmű.
Kontúr no está en línea   Reply With Quote
Old September 3rd, 2008, 10:37 PM   #14
RawLee
Registered User
 
RawLee's Avatar
 
Join Date: Jul 2007
Location: Budapest
Posts: 9,458
Likes (Received): 1158

Quote:
Originally Posted by Kontúr View Post
Hát ez nekem sem túl egyértelmű.
Hát a típusengedély ugye az,amit egy meglévő járműre adnak. Az előzetes ugye annyit tesz,hogy előre adják. Az elvi,meg hogy ugye "oké,legyen". Szerintem ez annyit tesz,hogy egy ismeretlen típusra adtak egy engedélyt,hogy azt be lehessen szerezni.
RawLee no está en línea   Reply With Quote
Old September 3rd, 2008, 10:44 PM   #15
Kontúr
Hajrá Magyarország!
 
Kontúr's Avatar
 
Join Date: Mar 2008
Location: Budapest
Posts: 959
Likes (Received): 13

Ez eddig OK, de igazából az érdekelne, hogy mikor írják ki a tendert, mikor zárul le, stb. Ahogy Debrecenben ez világos és egyértelmű itt ezt nem látom.
Kontúr no está en línea   Reply With Quote
Old September 3rd, 2008, 11:22 PM   #16
RawLee
Registered User
 
RawLee's Avatar
 
Join Date: Jul 2007
Location: Budapest
Posts: 9,458
Likes (Received): 1158

Quote:
Originally Posted by Kontúr View Post
Ez eddig OK, de igazából az érdekelne, hogy mikor írják ki a tendert, mikor zárul le, stb. Ahogy Debrecenben ez világos és egyértelmű itt ezt nem látom.
Itt építéssel kezdődött a projekt,ott rendeléssel. Szerintem hamarosan kiírják,hiszen rengeteg villamosról van szó.
RawLee no está en línea   Reply With Quote
Old September 4th, 2008, 10:53 AM   #17
Qtya
sensational
 
Qtya's Avatar
 
Join Date: Aug 2006
Location: Budapest - Brussels
Posts: 16,321
Likes (Received): 11557

Quote:
Originally Posted by RawLee View Post
Itt építéssel kezdődött a projekt,ott rendeléssel. Szerintem hamarosan kiírják,hiszen rengeteg villamosról van szó.
Ez egyenlőre csak egy kereszteződés, amelyet a valós projecten kívül is már tíz éve meg kellett volna csinálni...

A tényleges beruházás még nem indult el. Vegyük ezt egy 0. elemnek...
__________________
„A nemzet csak akkor remélhet egy jobb jövőben, ha polgárai képesek közös erőfeszítéssel felelősséget vállalni a közjóért.”

II. János Pál pápa
Qtya no está en línea   Reply With Quote
Old September 4th, 2008, 11:03 AM   #18
RawLee
Registered User
 
RawLee's Avatar
 
Join Date: Jul 2007
Location: Budapest
Posts: 9,458
Likes (Received): 1158

Quote:
Originally Posted by Qtya View Post
Ez egyenlőre csak egy kereszteződés, amelyet a valós projecten kívül is már tíz éve meg kellett volna csinálni...

A tényleges beruházás még nem indult el. Vegyük ezt egy 0. elemnek...
Szerintem valami olyasmi menete lesz ennek az egésznek,hogy először felújítják a meglévő vonalakat,és amikor az 1esen eljutnak a jövőbeli elválási pontig,akkor kezdik el építeni a 2es vonalát.
RawLee no está en línea   Reply With Quote
Old September 4th, 2008, 11:05 AM   #19
Qtya
sensational
 
Qtya's Avatar
 
Join Date: Aug 2006
Location: Budapest - Brussels
Posts: 16,321
Likes (Received): 11557

Quote:
Originally Posted by RawLee View Post
Szerintem valami olyasmi menete lesz ennek az egésznek,hogy először felújítják a meglévő vonalakat,és amikor az 1esen eljutnak a jövőbeli elválási pontig,akkor kezdik el építeni a 2es vonalát.
Ez a kereszteződés a 4-es és az 1-es vonalán van. Valahol középtávon. A 4-es körúti szakaszát már felújították, eddig a kereszteződésig. Az 1-est még nem. Ez egy teljesen különböző project. Még a tendereztetés is hamarabb volt. Nem hiába kezdték már most el a felújítást, jóval azelőtt, hogy Brüsszel döntött volna. Az 1-es, felújítása csak majd ez után következik... Valamikor... Reméljük minél hamarabb.
__________________
„A nemzet csak akkor remélhet egy jobb jövőben, ha polgárai képesek közös erőfeszítéssel felelősséget vállalni a közjóért.”

II. János Pál pápa
Qtya no está en línea   Reply With Quote
Old September 4th, 2008, 12:05 PM   #20
RawLee
Registered User
 
RawLee's Avatar
 
Join Date: Jul 2007
Location: Budapest
Posts: 9,458
Likes (Received): 1158

Quote:
Originally Posted by Qtya View Post
Ez a kereszteződés a 4-es és az 1-es vonalán van. Valahol középtávon. A 4-es körúti szakaszát már felújították, eddig a kereszteződésig. Az 1-est még nem. Ez egy teljesen különböző project. Még a tendereztetés is hamarabb volt. Nem hiába kezdték már most el a felújítást, jóval azelőtt, hogy Brüsszel döntött volna. Az 1-es, felújítása csak majd ez után következik... Valamikor... Reméljük minél hamarabb.
Amennyire én látom a térképen,az összes vonal átjön it (szegedi Deák tér...),és mivel a 2es az 1es szárnyvonala lesz...

Amenniben ez a térkép valós,úgy a tértől északra/keletre eső szakaszt fogják felújítani a 3,3F,4-es vonlán,illetve a 3,3F-én egy a körút után egy szakaszt,illetve a teljes 1-est. Szerintem nagyonis része ez a teljes projektnek,csak szerintem ezt megcsinálják a saját forrásból,és ha mégsem kapnak pénzt(amit én erősen kétlek),akkor max a többit nem csinálják meg.
RawLee no está en línea   Reply With Quote
Sponsored Links
Advertisement
 


Reply

Tags
szeged, tram

Thread Tools
Rate This Thread
Rate This Thread:

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off



All times are GMT +2. The time now is 03:13 PM.


Powered by vBulletin® Version 3.8.11 Beta 4
Copyright ©2000 - 2019, vBulletin Solutions Inc.
vBulletin Security provided by vBSecurity v2.2.2 (Pro) - vBulletin Mods & Addons Copyright © 2019 DragonByte Technologies Ltd.
Feedback Buttons provided by Advanced Post Thanks / Like (Pro) - vBulletin Mods & Addons Copyright © 2019 DragonByte Technologies Ltd.

SkyscraperCity ☆ In Urbanity We trust ☆ about us