SkyscraperCity banner

1 - 20 of 639 Posts

·
Moderator
Joined
·
12,365 Posts
Discussion Starter #1 (Edited)
Update 2014-03-30

-----------------

-----------------

Update 2014-03-09

This is a semi-community project. I will do lots of buildings myself, but once the plot map is released, feel free to propose building concepts.
You can either construct them on your own or let me do that for you
:cheers:
-----------------



-----------------

Credits

Original creators

Bolzeng
B.29 | Sky Condos
B.32 | Bolzeng World Trade Center & Residence
B.39 | Mirage Towers

earthbuilder
A.30 | The Evanescence
A.43 | Corporate Tower
B.19 + B.31 | Metropolitan Trade Center
B.43 | International Business Center
C.?? | River View Hotel
C.?? | Millenium Tower

Evrasia99911
A.44 | Astradamsky Tower
A.78 | The Sea Residence
A.84 | Lake Hotel & Tower
B.15 | International Tower
B.20 | Sky Gardens
B.22 | Euromarine Tower
B.38 | Crown Residence

JMGA196
B.51 - B.52 | Elemental Towers

xdexina
A.28 - A.29 | Institute of Technology
A.39 | House of Architecture
A.46 | Icarus Tower
B.55 - B.60 | Century City Plaza
C.?? - C.?? | Imperial Tower
C.?? | Torre Apple
 

·
Moderator
Joined
·
12,365 Posts
Discussion Starter #4
^^
Thanks! :cheers:

------------

GCI wins contract for $400 million mixed-use development

Today, GCI was awarded with another skyscraper development in phase two of the city's new business district. The client, Bolzeng Group, has said that the project is still in conceptual stage but is scheduled to start construction soon.

 

·
Moderator
Joined
·
12,365 Posts
Discussion Starter #10
Phase I
A.00 | AURORA Lake | -25.00m | U/C

Phase II
B.?? | Euromarine Tower | Prep
B.?? | Bolzeng World Trade Center & Residence | Prep

2014-03-22





 

·
Moderator
Joined
·
12,365 Posts
Discussion Starter #11
Phase I
A.00 | AURORA Lake | -25.00m | U/C

Phase II
B.?? | Euromarine Tower | Piling Level | -25.00m | Gw
B.?? | Independence Tower | Prep
B.?? | Bolzeng World Trade Center & Residence | Prep

2014-03-29









 

·
Registered
Joined
·
6,236 Posts
Hmmmmm....... :/
 

·
Moderator
Joined
·
12,365 Posts
Discussion Starter #16
Honestly, I think it looks to simular. I mean, the buildings should have more differencial in hights, right?
You do realize this is just a mass model with estimated heights, right? :D

----------

Phase I
A.00 | AURORA Lake | -25.00m | U/C
A.40 | The Cube | Prep

Phase II
B.13 | Independence Tower | Prep
B.22 | Euromarine Tower | Piling Level | -72.50m | Gw
B.32 | Bolzeng World Trade Center & Residence | Piling Level | -25.00m | Gw

2014-04-05







 

·
Moderator
Joined
·
12,365 Posts
Discussion Starter #17 (Edited)
Phase I
A.00 | AURORA Lake | -25.00m | U/C
A.40 | The Cube | Excavation Works | -2.50m | Gw
A.84 | Lake Hotel & Tower | Prep

Phase II
B.13 | Independence Tower | Piling Works | -60.00m | Gw
B.22 | Euromarine Tower | Piling Works | -72.50m | Gw
B.32 | Bolzeng World Trade Center & Residence | Piling Works | -60.00m | Gw

2014-04-12





 

·
Moderator
Joined
·
12,365 Posts
Discussion Starter #18
Phase I
A.00 | AURORA Lake | -25.00m | U/C
A.40 | The Cube | Foundation Level | -5.00m | Gw
A.84 | Lake Hotel & Tower | Prep

Phase II
B.13 | Independence Tower | Piling Works | -60.00m | Gw
B.20 | Sky Gardens | Prep
B.22 | Euromarine Tower | Piling Works | -72.50m | Gw
B.32 | Bolzeng World Trade Center & Residence | Piling Works | -60.00m | Gw