Plenty of interesting info in the Construction Phase plan. It's another precast build so should fly up once foundations are laid. I think the dates below are target completion dates opposed to start dates so the demolition of the garage and site prep should be imminent.

Detailed Description of the Project and Programme Details including Key Dates:

The New Cross Project consists of two blocks, A and B, of Private Rental Apartments of 8 and 10 storeys respectively. Both blocks have semi basement car parking. The foundations will consist of a mix of driven steel sheet piles as retention and bored piles supporting foundation loads.

The frame and facade of the buildings are formed using precast internal walls, floor slabs and external cladding sandwich panels. The external precast cladding will also have a high proportion of windows and doors prefixed to them off site.

Groundworks and piling – 08/05/18
Foundation – 11/07/18
Precast building (tower cranes) – 29/10/18
Fit out – 07/02/19

Watertight dates –

Block A – 11/10/19
Block B – 31/10/19

MEP – 07/03/19
Roofing – 03/07/19
Furniture – 10/01/20
Hard landscaping – 13/02/20
We can expect two more tower cranes with this one.

 