Discussion Starter · #3 ·
This project has just started ground work ! No pix coz i lost my phone battery ;(
 

·
Registered
Joined
·
882 Posts
Preparation ongoing for Ground floor. Columns are already casted.



On 7th Feb, most of the formworks and rebars are done for GF.



It took them approximately a month to go from P1 to GF, meaning that if they continue at the same pace, it may take 9-10 more month to complete the structure.
 

·
Registered
Joined
·
882 Posts
Works ongoing for level 2.



The slab of Level 2 was casted on 17th April
The slab of Level 3 on 30th April.
If they continues with the same speed (1 floor every 2 weeks), they could completed the 9 floors + roof by the end of August, taking into account that the midday summer ban and Ramadan are making things slower.
 

·
Registered
Joined
·
882 Posts
They have accelarated the works, the slab of level 5 was poured on 21st May.
If they continue like that, the main structure could be completed by the end of July.

 

·
Registered
Joined
·
882 Posts
Level 9 is completed - works ongoing for the roof which is probably the lift machine room - progress in the block works




Paint done at level 1 in the center column

 