I don't know if you know or not but this terminal is under construction right now.

Welcome to new Dalalman airport...

These are only decent pix I could find.














it is so strange that Airport will be open soon and there is not any construction photo on the internet yet :sleepy:

It will be openned before Izmir and Ankara... There are some information but no photo
 

·
re re re ra ra ra
Joined
·
4,745 Posts
Excellent! Airports are vital to the commercial success of a city. :eek:kay:
 

·
Registered
Joined
·
4,077 Posts
System_Halted said:
What will happen to the current airport of Dalaman?
most probably, it will be used for domestic flights
 

·
Super Member
Joined
·
9,190 Posts
Shopping Center – The Grand Bazaar at Dalaman Airport

A shopping center covering an area of 5.000 m2 is designed to be built under the New Terminal Building. The shopping center to be constructed at the International Terminal will bear the concept of the Grand Bazaar. The shopping center, where the unique and authentic products of Turkey will be sold at carpet, leather and jewelry shops, will create the Grand Bazaar’s atmosphere at Dalaman Airport with its indoor design as well as the animations to be organized.

Terminal Features

The Domestic and International Terminals at the current airport in Dalaman cover an area of 35.000 m2. When the Dalaman Airport Project is completed in 2006, the new International Terminal covering an area of 95.000 m2 will be three times bigger than the current terminal. Within the framework of the project, in addition to the International Terminal, an additional apron of 210.000 m2 and a parking lot covering 14.000 m2 with a capacity 950 vehicles, CIP and VIP buildings are being constructed.

When the terminal is started to operate, passenger capacity per annum will rise up to 10.000.000 people. Together with the additional aprons to be constructed, 14 new parking places for airplanes are planned. There are 8 passenger bridges and 6 distant plane passenger boarding gates. By means of the 400 Hz system and PCA system, which are available at the passenger bridges, necessary energy and ventilation, air-conditioning and utility water supplies will be provided.

In the building that is designed as 4-storey, there will be 22 escalators and 21 elevators, which will ensure fast and comfortable connection between the floors. In the new terminal building, the basement and 1st floors are allocated for arriving passengers, while the 2nd and 3rd floors are allocated for departures. At the terminal building, being equipped with high technology, everything is planned for the comfort of passengers.

At the New International Terminal, there will be 60 check-in counters, all of which are designed as CUTE stations, with a capacity of 4000 passengers and 5000 baggage per hour. Besides, necessary infrastructure is being prepared for early check-in of the passengers at their hotels. Therefore passengers will save time for taking the advantages of the services offered to them at the terminal without waiting in long queues.

At the International Terminal of Dalaman Airport, for arriving passengers on the 1st floor, and for departing passengers on the 2nd floor, there are Duty Free Shops, where you can find the famous brands of Turkey and the world, and shopping areas where you can buy products that are unique for Turkey, and entertainment and resting places for a pleasant time. Our passengers will have the chance to taste different dishes from the Turkish and the world cuisine at the restaurants and cafés on the mezzanine floor while watching the take-offs and landings.

Services such as ticket sales, banks and exchange offices, post office, emergency care clinic, baby rooms and children play grounds, pharmacy, newspaper stall, car rent, hotel reservations, florist, checkroom for luggage, restrooms etc. are offered to our passengers and there is necessary guidance for the passengers to ensure practical and fast access to the those services. There are also a small Mosque, Chapel and Synagogue for prayers at Dalaman International Terminal.

Technical Features and Technology

Within the framework of the terminal operation, the passenger and the baggage services, the land-side and air-side security and the financial management are supported by high-tech electronic and automation systems. Terminal operations systems are designed to work within a network as an integrated database. Moreover, the systems that are critical in terms of operation can also function independently.

Some of the technology based systems used at the terminal are as follows:

Automatic Check-in Service: The check-in service is provided by means of 60 check-in counters automatically via DCS software.
Baggage Services: Baggage Handling System allows the baggage to be monitored from the check-in point until they are loaded in the plane and the passenger-baggage reconcelliation is made automatically with the help of Baggage Reconcelliation software.
Flight Info Display System: Flight information including real time take-off and landings together with check-in counters, boarding gates and baggage reclaim belts allocation can be monitored with the help of the FIDS system via the number of monitors placed in many points on the arrival and departure floors of the terminal.
Docking and Guidance System: Docking and Guidance System used to ensure that the plane is safely approached and parked in correct position at the passenger bridges.
Building Management Systems: SCADA, intercom, telephone, building automation system, fire alarm system, and data cable network (internet etc.), automatic air-conditioning and Central Clock system.
Data Transfer Network: Data transfer is performed through a high speed, Ethernet backbone structure, with a structural cable architecture and star topology fiber optic and CAT6 UTP cable network. In order to obtain an uninterrupted high service level in terms of operation, all the information services have redundancy back-ups and they are offered by means of active network systems.
Uninterrupted Power Source and Backup Generators: Inside the terminal there is a unit for number of uninterrupted power sources supporting all the systems. A generator system that is turned on when the network electricity is cut off and provides back up for a 100% of critical operational systems and 50% of illumination and air-conditioning systems.
Waste Water and Solid Waste Treatment: Water treatment, solid and sanitary waste treatment facilities are available among the mechanical systems of the building.
Security Systems: For the security of the building, x-ray devices and metal detectors are located at all entrance-exit gates of the terminal and transit points between the units. Furthermore, the passenger baggage are inspected through an in line detection system including a number of x-rays and explosive detecting devices (EDS/EDDS) from the check-in until they reach their plane. At the terminal building, the most advanced technology are used in terms of building and aviation security, all areas are monitored by CCTVs.
The car park are controlled with the help of an automatic tolling system and that region’s security is ensured by the CCTVs located in that area and the security officers.
dalaman-airport.com
 

·
Strange User
Joined
·
19,706 Posts
Discussion Starter · #14 ·
old pix from the contruction








General Directorate of State Airports Administration (DHMI) called a privatization tender in the year 2003 for Dalaman Airport on the basis of Build-Operate-Transfer model. Being awarded the contract, ATM Airport Construction and Management Co. assumed the financing, construction and operation of Dalaman Airport International Terminal and its extensions.
ATM Airport Construction and Management Co. is a consortium formed by Aksa and their partners Turkuaz and Manas companies. YDA-AKSA, the big partner of the consortium, is the flag ship of YDA Group, which is based in Ankara. YDA Group has YDA, AKSA, intas, YDA-AKSA - Joint Venture and Turkuaz-YDA-Stroy partnerships in Kazakhstan in the construction sector; MAYDA in Mining and Energy sector; MEYDA and DIOMEYDA in health sector, TUYDA in tourism and YDA Sigorta in insurance sector. YDA has first entered this sector with Zonguldak flour factory, the construction of which was started in 1976 and completed in 1979 and performed so many public and commercial construction projects in Turkey and Central Asia since its establishment; and is now celebrating its 30th anniversary with the big project of Dalaman Airport.

With an investment of USD 130.000.000, Dalaman Airport is one of the most significant projects in the sector. The project is funded by the German Hypo-Vereinsbank together with an important amount of YDA-AKSA equities. Consultancy and audit of this international project are executed by Scott Wilson (U.K.) and Obermeyer Gmbh (Germany).

Dalaman Airport project is performed with great diligence and pace in accordance with the concession contract signed with the General Directorate of State Airports Administration on June 24th, 2004. 125 architects and engineers and 2100 foremen and workers are involved in the project, and the construction goes on 24 hours a day without interruption. After the construction is completed in April 2006, ATM Airport Construction and Management Co. will handle the operation of Dalaman Airport for 6, 5 years (this period will be extended to 9 years together with the additional investments planned) with the same diligence and quality.

Serving for areas such as; Marmaris, Datga, Fethiye, Koycegiz, Dalyan, Gocek, Sangerme etc. Dalaman Airport has been insufficient due to the increasing number of passengers and airplanes in line with the development of tourism in Turkey. Within the framework of Dalaman Airport project, which aims at relieving the traffic of international and domestic flights, there will be an International Terminal Building, and additional Apron, CIP and VIP buildings and a car park to be built at the current airport area
 

·
Super Member
Joined
·
9,190 Posts
ATM'den Dalaman'a çevreci havalimanı

Ankaralı YDA Grup bünyesindeki ATM Havaalanı İşletme tarafından yapımı gerçekleştirilen Dalaman yeni dış hatlar terminali, mimari yapısıyla alışılmış havalimanlarının dışına çıkıyor. Yoğun olarak İngiliz turistlerin kullanacağı yeni terminalde, inşa edilen hareketli güneş korucu sistem sayesinde, yüzde 40 daha az klima enerjisi kullanılarak çevrenin daha az kirletileceğini söyleyen projenin mimarı Emre Arolat, 'Yeni Dalaman Dış Hatlar Terminali ile alışılmış havalimanlarının dışına çıktık' dedi. İç dekorasyonda Dalaman bölgesinin bitki örtüsünü de kullanacaklarını söyleyen Arolat, şöyle dedi: 'Havalimanının mimarisinde ilk kez doğal ahşap kullandık. Betonları örtmedik. Yüzde 40 daha az klima kullanarak, dünyayı daha az kirleteceğiz.'

BRITISH AIRWAYS DİREKT UÇACAK

Dalaman yeni dış hatlar terminali, aynı zamanda 3 milyon yerine 10 milyon turiste hizmet verebilecek şekilde tasarlandı. British Airway gibi İngiltere'nin en büyük havayolu şirketlerinin Dalaman'a direkt sefer koyacaklarını söyleyen ATM Havaalanı İşletme Yönetim Kurulu Başkanı Hüseyin Arslan, 'Bugünkü yolcu kapasitesinin 3 katından fazla yolcuya kolaylıkla hizmet verecek şekilde tasarlanan yeni terminal, yabancıların ülkemiz hakkındaki görüşlerine de olumlu katkı yapacak. Kaş'tan Marmaris-Datça'ya kadar uzun bir kıyı şeridine hizmet verecek. Bölgenin turizm kapasitesini artıracak' dedi.

ANTALYA'YI YAKALAYACAĞIZ

Arslan şöyle devam etti: 'Bu bölge, Kaş, Kalkan, Fethiye, Göcek, Sarıgerme, Marmaris, Gökova ve Datça gibi, Türkiye'nin en çok bilinen uluslararası turizm destinasyonlarını kapsıyor. Yörenin mevcut 220 bin olan belgeli yatak kapasitesinin, 35 bin yataklı 'Dalaman Turizm City' gibi projelerle yakın bir zamanda 300 bini aşacağı düşünülüyor. Antalya ise Türkiye'de en yüksek sayıda turist çeken turistik destinasyon olarak lider konumda ve 2005 yılında 7.5 milyon turist ağırladı. Dalaman'ın da yakın zamanda Antalya'ya yetişeceğini öngörüyoruz.''

EN BÜYÜK ÜÇÜNCÜ HAVALİMANI

Planlanan tarihten 8 ay önce tamamlanan Dalaman Havaalanı yeni dış hatlar terminali haziran ayında hizmete açılacak. Arslan, yeni terminalin Antalya ve İstanbul'daki dış hatlar terminallerinden sonra Türkiye'nin yolcu sayısı bakımından en büyük üçüncü terminali olma özelliğini taşıdığını söyledi.

Ciro hedefi 500 milyon $

ATM Havaalanı'nın da dahil olduğu YDA Grup, bu yıl 500 milyon dolar ciro hedefliyor. 7 farklı sektörde faaliyet gösteren ATM'nin Yönetim Kurulu Başkanı Arslan, 'Dalaman ve Kazakistan'daki yatırımlarımızla hedefi gerçekleştireceğiz' dedi.


Dalaman'da turist sayısında azalma yok

ATM Yönetim Kurulu Başkanı Hüseyin Arslan, her geçen gün Dalaman Havalimanı'na gelen turist sayısının arttığını söyledi. Türkiye'ye gelen turist sayısında yüzde 10 ile 12 arasında bir düşüş yaşandığını söyleyen Arslan, 'Halbuki Dalaman'a gelen turist sayısı geçen yıla göre yüzde 17.5 oranında arttı. Türkiye'ye gelen turist sayısı azalırken, bu bölgeye gelen turist sayısı artıyor' dedi. Dalaman'a havayoluyla gelen yabancı turistlerin arasında yüzde 70 ile İngilizler ilk sırada yer alıyor. İngilizleri, Alman, Hollandalı ve Rus turistler izliyor.
Aksam

8 ay erken bitirilen Dalaman açılıyor

Türkiye'nin en önemli turizm kapılarından biri olan yeni Dalaman Dış Hatlar terminalinin yapım çalışmaları tamamladı. Planlanan tarihten 8 ay önce yapımı biten Dalaman yeni dış hatlar terminali Haziran'da ilk misafirlerini ağırlayacak

Türkiye'nin en önemli turizm kapılarından biri olan yeni Dalaman Dış Hatlar terminalinin yapım çalışmaları tamamladı. Planlanan tarihten 8 ay önce yapımı biten Dalaman yeni dış hatlar terminali Haziran'da ilk misafirlerini ağırlayacak. 150 milyon dolara mal olan ve yolcu kapasitesi 3 milyondan 10 milyona çıkarılan yeni terminal, yolcu sayısı bakımından Türkiye'nin en büyük 3. dış hat terminali. Dış Hatlar terminalini Yap-İşlet-Devret modeli ile hayata geçiren ATM Havaalanı İşletme Başkanı Hüseyin Aslan, "Yeni terminal, yabancıların ülkemiz hakkındaki görüşlerine de olumlu katkı yapacak" dedi. ATM Genel Müdürü Hamdi Güvenç ise "15 Şubat 2007'ye kadar süremiz varken, bu tarihten 8 ay önce terminali dünya standartlarında bitirdik" diye konuştu.

Londra'ya üç sefer

Dalaman'dan giriş yapan yabancı turistlerin yüzde 40'ını İngilizler oluşturuyor. British Airways Londra-Dalaman arası üç gün direkt sefer yapacak.
Vatan

Completed 8 months earlier than planned and opening in June
 

·
Banned
Joined
·
2,505 Posts
The capacity is 10 million so it will be Turkey's 3th bigeest airport with Ankara.