My reply is below.
I've recently moved to Navi Mumbai and have been driving to Nariman Point on a daily basis via the BPT road, where MMRDA & Simplex are building the Eastern Freeway. I've been seeing the progress on a daily basis and had some questions regarding the process, if any one in the field could help me out, I'd appreciate it.
So as far as I know:
-They dig I big square hole This is the foundation.and 4 circular hole near each corner This are Piles. They are doing pile foundations.
-Shove some bars in the middle of the square and first make a 1-2 foot concrete skirting for the bars (first layer of concrete)
-Then they put up the mould around the bare steel bars and pour in some more concrete and voila the pillar is done.
Correct?
There are a whole load of pillars along the road which are stuck around the 2nd point. With the concrete skirting done, but the mould not being put. Why? Is it necessary to wait for the concrete to set Yes, after the concrete is poured, they need to wait for the concrete to gain strength. , or is it lack of funds etc? Is it possible to carry on working during the monsoons? Work can be carried all round year. I've always heard in the negative, but the way work is going on, it doesn't seem so. Bridge building is not a instant noodle. I suggest you google for words like, pile foundation, piers, pilecap, segmental bridges. Read these topics so that you get a rough idea. If you have spare time, then stop at the site when a major activity goes on, speak to a engineer, I am sure he will explain and clear your doubts.
Thanks
Have attached my brief, yet spectacular, rendition of the pillar
![]()
I've recently moved to Navi Mumbai and have been driving to Nariman Point on a daily basis via the BPT road, where MMRDA & Simplex are building the Eastern Freeway. I've been seeing the progress on a daily basis and had some questions regarding the process, if any one in the field could help me out, I'd appreciate it.
So as far as I know:
-They dig I big square hole This is the foundation.and 4 circular hole near each corner This are Piles. They are doing pile foundations.
-Shove some bars in the middle of the square and first make a 1-2 foot concrete skirting for the bars (first layer of concrete)
-Then they put up the mould around the bare steel bars and pour in some more concrete and voila the pillar is done.
Correct?
There are a whole load of pillars along the road which are stuck around the 2nd point. With the concrete skirting done, but the mould not being put. Why? Is it necessary to wait for the concrete to set Yes, after the concrete is poured, they need to wait for the concrete to gain strength. , or is it lack of funds etc? Is it possible to carry on working during the monsoons? Work can be carried all round year. I've always heard in the negative, but the way work is going on, it doesn't seem so. Bridge building is not a instant noodle. I suggest you google for words like, pile foundation, piers, pilecap, segmental bridges. Read these topics so that you get a rough idea. If you have spare time, then stop at the site when a major activity goes on, speak to a engineer, I am sure he will explain and clear your doubts.
Thanks
Have attached my brief, yet spectacular, rendition of the pillar
![]()
