What is the current situation on A7 Lorentzweiler – Waldhaff,the section which is U/C ?
Two weeks ago it looked almost finished. The variable overhead signs are installed both between Waldhaff and tunnel Stafelter and in the cut near Stafelter. Currently work is going on at the provisional end of A7 at Waldhaff to connect the new stretch and adapt the exit. I guess ground markings are also not yet painted. But looks good for an opening early next year as planned.
 

·
Moderator
Joined
·
52,591 Posts
Discussion Starter · #125 ·
They will finally begin construction there very soon. It was held up by a farmer who didn't want to sell its land, and apparently couldn't be expropriated easily.
 

·
Banned
Joined
·
5,848 Posts
It's a funny bit of road. Coming from Germany there is a matrix sign stating perpanently in German that the motorway is about to end. Staugefahr! But there is never any traffic.
 

·
Moderator
Joined
·
52,591 Posts
Discussion Starter · #127 ·
The 'aire de Berchem' along A3 is the highest volume fuel station in the world. They sell over 300 million liters of fuel every year (80% diesel). That amounts to more than 40 tanker shipments per day. I wonder if these fuel stations have a private pipeline to supply them. Shipping that amount by truck is impractical. Especially because the 'aire de Capellen' along A6 likely has a similar volume of fuel.
 

·
Moderator
Joined
·
52,591 Posts
Discussion Starter · #128 ·

·
Moderator
Joined
·
52,591 Posts
Discussion Starter · #129 ·
2015-2018 construction programme

The following projects have been included in the 2015-2018 construction programme of Luxembourg.

* widening A3 to 2x3 lanes in 4 phases: 1) Berchem - Gasperich, 2) Dudelange-Centre, 3) Bettembourg - Berchem, 4) Bettembourg interchange. Cost: € 159 million

* connection Micheville, which will connect A4 with France. Cost: € 354 million

* Bus lane on A4 in various phases. First phase Leudelange - Pontpierre. Cost € 4 million

* N3 Hesperange bypass. Cost € 74 million.

* Completion A7 'Nordstrooss'. Opens September 2015

* reconstruction Hellange interchange (A13 missing link) Cost: 35 million

* reconstruction Burange interchange (A13) Cost: 36.5 million


http://www.tageblatt.lu/nachrichten/luxemburg/story/13174208
 

·
Registered
Joined
·
7,292 Posts
A13 Hellange bypass

The news article from June 2013 says that the costs are up to 30 million €. Completion in spring 2016.

http://www.tageblatt.lu/nachrichten/story/12564622 (10th July 2014)

The parliament accepted to begin the construction. The construction should begin in September 2014. The works will last 2 years and will cost 34 million €.
Preliminary works have been started on 20th October 2014. A temporary roundabout is u/c. No info about the "real" construction begin. Source (13th November 2014).
 

·
Registered
Joined
·
7,292 Posts

·
Registered
Joined
·
7,292 Posts

·
Moderator
Joined
·
52,591 Posts
Discussion Starter · #138 ·
A7 Nordstrooss

The missing link of A7 around Luxembourg (city) opens to traffic tomorrow. This is really a game-changer in regional mobility. North-south traffic can now bypass the urban area of Luxembourg. The current routes to A7 are circuitous and run across city streets not meant for so much traffic.

 

·