Well, the Pre-app meeting was interesting, DLA and a representative of the developer was in attendance to address the presentation. To be fair, the panel raised some reasonable points and seemed fairly balanced overall (with one or two exceptions), I think they are learning and evolving, perhaps listening to external commentators
The main points:
- The panel was generally in favour of the scheme, and in acceptance of the mix of uses and the general massing of the scheme
- They had issues with the layout of the public outdoor space (which makes up 55% of the overall area), in particular the access through the site to link with the footbridge, and the pathway that runs alongside the A58M
- The architect stated they are working up the documents for a full planning application to be lodged in the next few weeks, with the aim to gain full approval by late summer, in order to start phase 1 this autumn, although they did state this was perhaps an optimistic outlook, but are wanting to start as soon as they can
- Phase 1 would include everything apart from the office building (the office plot would constitute the site compound area during the phase 1 build period)
- In addition, the developer stated they had operators lined up for the BTR, the Aparthotel and the Student accommodation (everything but the office)