I had yet another walk along the Trafford Park Line yesterday to view progress. As I said last time things have slowed down in terms of big changes but there is a lot of what might be termed detailing work in progress along the route.
Starting as usual at Pomona where they are still working on the new viaduct although it wasn't easy to make out what was going on.
P1360155 by Steve Hyde, on Flickr
P1360157 by Steve Hyde, on Flickr
Down below the viaduct the paving and fencing work has moved on.
P1360161 by Steve Hyde, on Flickr
P1360171 by Steve Hyde, on Flickr
P1360172 by Steve Hyde, on Flickr
It looked to me as though the end of the path from Wharfside was visible. At present this path is only surfaced in crushed stone but I would hope it is to be finished with slabs.
P1360163a by Steve Hyde, on Flickr
Reinstating the original handrailing where it was removed during construction.
P1360165 by Steve Hyde, on Flickr
I can't make out exactly where the canal side fence is in relation to the edge of the viaduct.
P1360171 by Steve Hyde, on Flickr
There are now TMS VECOM loops in place on the ramp.
P1360178 by Steve Hyde, on Flickr
The substation compound is now fenced off and it is clear that the concrete steps down to trackside are only for staff access as there is no public access at the top.
P1360179 by Steve Hyde, on Flickr
P1360180 by Steve Hyde, on Flickr
From Trafford Road the access arrangements for staff seem to be clearer and also visible on the track in the distance is derailment containment between the rails. From the close up version of the photograph it looks as though the path runs between the canal side railings and the green fence under the viaduct. green fence under the viaduct
P1360184 by Steve Hyde, on Flickr
P1360184a by Steve Hyde, on Flickr
The footpath still awaits final paving (hopefully).
P1360186 by Steve Hyde, on Flickr
A view towards Wharfside and beyond from Trafford Road.
P1050423 by Steve Hyde, on Flickr
P1050426 by Steve Hyde, on Flickr
There were a couple of guts grouting rail baseplates at Wharf End.
P1050431 by Steve Hyde, on Flickr
The parallel feeder link cables all seem to be connected to the contact wires along here now.
P1050433 by Steve Hyde, on Flickr
The footway along Wharf End has now been moved over to the retaining wall side presumably leaving the other side to the contractors working on the new tower blocks.
P1050435 by Steve Hyde, on Flickr
This gives some new views along the track.
P1050438 by Steve Hyde, on Flickr
P1050442 by Steve Hyde, on Flickr
Speed signs are starting to appear and the Wharfside 'emergency' crossover has gained position indicators which is unusual for an emergency crossover.
P1050444 by Steve Hyde, on Flickr
P1050447 by Steve Hyde, on Flickr
Not much else has changed at Wharfside. Perhaps other than the lamp posts have been finally fix vertical.
P1360193 by Steve Hyde, on Flickr
Looking west from Wharfside.
P1360196 by Steve Hyde, on Flickr
P1360197 by Steve Hyde, on Flickr
Electrical switching cubicles behind the MPT compound.
P1360203 by Steve Hyde, on Flickr
The HERAS fencing along Trafford Wharf Road seems to be disappearing. I wonder whether they are getting ready to re-open the west bound side.
P1360206 by Steve Hyde, on Flickr
P1360210 by Steve Hyde, on Flickr
The crossing they were starting to lay last time is now complete and provides access to the footway behind the stop and also to the platform.
P1360213 by Steve Hyde, on Flickr
P1360218 by Steve Hyde, on Flickr
P1360219 by Steve Hyde, on Flickr
P1360225 by Steve Hyde, on Flickr
A quick diversion behind Quay West.
P1360234 by Steve Hyde, on Flickr
P1360237 by Steve Hyde, on Flickr
Ceremonial unveiling of the No entry Except Trams signs.
P1360242 by Steve Hyde, on Flickr
30 mph along Trafford wharf Road.
P1360243 by Steve Hyde, on Flickr
P1360248 by Steve Hyde, on Flickr
10 mph round the curve into Warren Bruce Road.
P1360251 by Steve Hyde, on Flickr
P1360254 by Steve Hyde, on Flickr
This short section of track awaiting embedding is the location of the special friction modifier equipment for the inbound curve. There is a similar section on Trafford Wharf Road for the outbound line.
P1360257 by Steve Hyde, on Flickr
I got lucky here whilst chatting to one of the MPT guys. He offered to get me some photographs of the equipment installed so far. There are two separate systems installed. Apparently one is a fairly normal track lubricator and the other is a fluid water based system.
P1360260 by Steve Hyde, on Flickr
P1360261 by Steve Hyde, on Flickr
P1360263 by Steve Hyde, on Flickr
P1360264 by Steve Hyde, on Flickr
Fingers crossed it all works as it is supposed to.
Feeder cables connected.
P1360267 by Steve Hyde, on Flickr
P1360269 by Steve Hyde, on Flickr
P1360271 by Steve Hyde, on Flickr
10 mph entry into the turnback.
P1360274 by Steve Hyde, on Flickr
The PPI is there now for the entrance points and the final bit of concrete embedding is awaited.
P1360276 by Steve Hyde, on Flickr
P1360278 by Steve Hyde, on Flickr
Part 2 Village Circle to Parkway Circle will follow later today along with Part 3......
Starting as usual at Pomona where they are still working on the new viaduct although it wasn't easy to make out what was going on.


Down below the viaduct the paving and fencing work has moved on.



It looked to me as though the end of the path from Wharfside was visible. At present this path is only surfaced in crushed stone but I would hope it is to be finished with slabs.

Reinstating the original handrailing where it was removed during construction.

I can't make out exactly where the canal side fence is in relation to the edge of the viaduct.

There are now TMS VECOM loops in place on the ramp.

The substation compound is now fenced off and it is clear that the concrete steps down to trackside are only for staff access as there is no public access at the top.


From Trafford Road the access arrangements for staff seem to be clearer and also visible on the track in the distance is derailment containment between the rails. From the close up version of the photograph it looks as though the path runs between the canal side railings and the green fence under the viaduct. green fence under the viaduct


The footpath still awaits final paving (hopefully).

A view towards Wharfside and beyond from Trafford Road.


There were a couple of guts grouting rail baseplates at Wharf End.

The parallel feeder link cables all seem to be connected to the contact wires along here now.

The footway along Wharf End has now been moved over to the retaining wall side presumably leaving the other side to the contractors working on the new tower blocks.

This gives some new views along the track.


Speed signs are starting to appear and the Wharfside 'emergency' crossover has gained position indicators which is unusual for an emergency crossover.


Not much else has changed at Wharfside. Perhaps other than the lamp posts have been finally fix vertical.

Looking west from Wharfside.


Electrical switching cubicles behind the MPT compound.

The HERAS fencing along Trafford Wharf Road seems to be disappearing. I wonder whether they are getting ready to re-open the west bound side.


The crossing they were starting to lay last time is now complete and provides access to the footway behind the stop and also to the platform.




A quick diversion behind Quay West.


Ceremonial unveiling of the No entry Except Trams signs.

30 mph along Trafford wharf Road.


10 mph round the curve into Warren Bruce Road.


This short section of track awaiting embedding is the location of the special friction modifier equipment for the inbound curve. There is a similar section on Trafford Wharf Road for the outbound line.

I got lucky here whilst chatting to one of the MPT guys. He offered to get me some photographs of the equipment installed so far. There are two separate systems installed. Apparently one is a fairly normal track lubricator and the other is a fluid water based system.




Fingers crossed it all works as it is supposed to.
Feeder cables connected.



10 mph entry into the turnback.

The PPI is there now for the entrance points and the final bit of concrete embedding is awaited.


Part 2 Village Circle to Parkway Circle will follow later today along with Part 3......