Bibimbaaaaaap
Joined
·
2,503 Posts
Well, what do you want? You want the heavy buses to pass through the rinky-dink temporary steel ramps and counterflow lanes that are barely wide enough for cars?
I know buses are not capable of passing thru the temporary steel ramp, what I mean is their temporary ban for 1.5 months which I consider a burden for those coming from/to South, especially P2P. Hope they'll consider the latter and few city or provincial buses to pass Skyway from Feb 16 to March 30.
 

·
Registered
Joined
·
635 Posts
With Segment 2A delayed because of the fire and collapse girders, any news on getting Segment 3 & 4 open?
From the current video.There are still two or three months decking in the middle of section 4. Plus, they still have to finish section 4 on Sargent Rivera.So no hope on that section until June-July.
 

·
Registered
Joined
·
20,991 Posts

·
Registered
Joined
·
783 Posts
From the current video.There are still two or three months decking in the middle of section 4. Plus, they still have to finish section 4 on Sargent Rivera.So no hope on that section until June-July.
But the whole viaduct is done from Aurora Blvd (whole S3) to Amoranto (part of S4) - will this not be viable to open once off ramps near INC and on ramp at St. Peter is done?
 

·
Registered
Joined
·
20,991 Posts
Pati ba Hillsborough NB on-ramp isasara na rin sa Feb 16?
SB lang ata ngayon, pero in due time need ulit isara NB on-ramp gawa meh 5-6 piers that still needs to be piled and set-up'ed. Giba ang innermost on-ramp lane as well (based sa lane markings).

Is this the same din kaya sa SB, kaya sinara na nila yung buong off-ramp para mahapit na magawa din yung 5-6 piers that needs to be constructed para maconnect sa existing elevated section?
 

·
Registered
Joined
·
437 Posts
^^ Siguro iniiwasan lang nila pagsabay sabayin ung activity sa NB at SB. I already expected this last year pa na magiging one way din ang West Service Road pag nagstart na ang full construction sa SB.
 

·
Registered
Joined
·
2,102 Posts
Beginning next week, is the SB elevated portion going to remain 2-lanes from Hillsborough all the way to steel ramp?? or 1 lane lang at certain times?
 

·
Registered
Joined
·
1,935 Posts
2 southbound lanes of Balintawak to be closed for Skyway Stage 3 construction
By: Consuelo Marquez - Reporter / @CMarquezINQINQUIRER.net / 08:25 PM February 12, 2020

MANILA, Philippines — Two southbound lanes of Balintawak will not be passable to motorists starting Sunday morning (Feb. 16) to make way for the construction of the Skyway Stage 3 project, the Metropolitan Manila Development Authority (MMDA) said Wednesday.

In a press briefing at MMDA’s main office, MMDA General Manager Jojo Garcia said the closure would start at 12 a.m. of Sunday.

Aside from this, Garcia said one lane from A. Bonifacio going to North Luzon Expressway would also be closed from 11 p.m. to 3 a.m. on Saturday (Feb. 15).

Read more: https://newsinfo.inquirer.net/1227985/2-southbound-lanes-of-balintawak-to-close-for-skyway-stage-3-construction#ixzz6Du3UYvLP
 

·
Registered
Joined
·
20,991 Posts
Swivel-type steel vertical clearance barriers for Class 2 temporarily banned this coming Sunday now installed at SB Dela Rosa / Magallanes onramp
 

·
Registered
Joined
·
264 Posts
So, how's Skyway Stage 3 Phase 2-A two weeks after the fire in Pandacan? Were the Skyway parts and the plastic factory demolished as of this moment? It's currently under investigation though.
 

·
Registered
Joined
·
223 Posts
So, how's Skyway Stage 3 Phase 2-A two weeks after the fire in Pandacan? Were the Skyway parts and the plastic factory demolished as of this moment? It's currently under investigation though.
The investigation would probably take a bit longer since this ultimately involves the insurance provider making sure that their exposure to the potential cost of the payout is as small as possible. Afterall, nobody loses out on insurance except for the clients who often have to beg to even get something during the time they need the extra cash.
 

·
Registered
Joined
·
1,301 Posts
The investigation would probably take a bit longer since this ultimately involves the insurance provider making sure that their exposure to the potential cost of the payout is as small as possible. Afterall, nobody loses out on insurance except for the clients who often have to beg to even get something during the time they need the extra cash.
They can resume construction even there is an investigation
 

·
Registered
Joined
·
223 Posts
They can resume construction even there is an investigation
Maybe for the unaffected parts, but not for the areas that they want to claim for insurance. Not unless the insurance provider agrees with this kind of arrangement and would disburse payment after the fact. That rarely happens, though. The insurance provider might be afraid that this could set a bad precedent. Suppose that a company is strapped for cash and wants an insurance payout by causing a fire. It's very much within the realm of possibilities. I don't have a clue of what is actually going on. We're just speculating here.
 

·
Registered
Joined
·
20,991 Posts
S2E SB: And so it Begins

Umabot pa prior to closing of Hillsborough off ramp / South Station / Alabang Exits

---

Alabang Bulletin is at Skyway Slex.
57 mins · Muntinlupa City ·
And so it begins...🎢🎢🎢🎢🎢

FYI, neighbors.

Please tag your friends who might be affected.

Konting pasensya, guys. Wag uminit mga ulo sa daan. Let's go!

#balitasasouth











 

·
Registered
Joined
·
20,991 Posts
Just passed S2E work area, SB lane closure starts at S96 (just after the Sucat Entry acceleration lane)

Heavy equipment on site now demolishing the fence and placing concrete barriers

Let’s see tomorrow how the traffic goes

EDIT: vertical clearance steel barriers with tarpaulin for no entry Class 2 now swiveled into position at SB Magallanes onramp - SOMCO personnel manning the on-ramp so that no C2 vehicles can enter
 