Shenzhen Western Corridor and Deep Bay Link







Purpose
1. This paper sets out the current position on the Shenzhen Western
Corridor and Deep Bay Link.

Background

2. Hong Kong has benefited from China’s economic growth enabling herself to perform better than most of the neighbouring places, such as Singapore, Indonesia etc., during the recent economic recession that has occurred in Asia.

3. However, this economic advantage is not without worry since the three existing vehicular boundary crossings at Lok Ma Chau, Man Kam To and Sha Tau Kok are nearly saturated and it is expected that they will exceed their handling capacity within the next five years. In fact, the public has raised concerns on the frequent occurrence of traffic congestion and long waiting times at these crossings.

4. Both the governments of the HKSAR and Shenzhen recognise the need to remove these potential bottle-necks to trade and traffic. However, there are difficulties in expanding the existing three crossings because they are located within the city centre of Shenzhen. Over 80% of the cross-boundary traffic has to go through the main roads within the Shenzhen city centre causing serious traffic congestion and environmental impacts. On account of this, the Shenzhen authority considers the fourth land boundary crossing – Shenzhen Western Corridor should be built as soon as possible.

5. On Hong Kong’s part, the ‘Feasibility Study for Additional Cross-border Links’ also confirmed the need for constructing SWC together with the connecting road, Deep Bay Link for the following reasons:
(a) to alleviate the nearly saturated existing land boundary crossings at Lok Ma Chau, Man Kam To and Sha Tau Kok;
(b) to enhance trade between Hong Kong and South China, to facilitate Hong Kong’s economic development and to enable Hong Kong to become the business hub of the Pearl River Delta area.

6. We have reached agreement with the Shenzhen authority that in accordance with the boundary of Guangdong and Hong Kong, each side will finance and manage its portion of the SWC, while the construction of the bridge will be a joint effort. Both sides have also agreed to implement the project as soon as possible.

7. At the 4th Plenary of the Hong Kong / Guangdong Cooperation Joint Conference held on 25 July 2001, further agreement has been reached on the principle of co-locating the boundary crossing facilities for immigration and customs clearance procedures on the Shenzhen side in planning SWC.

Proposal
Shenzhen Western Corridor


8. We propose to implement Shenzhen Western Corridor, which is a dual 3-lane bridge spanning Deep Bay. The length of the whole bridge is 5.1 km, 3.2 km of which is within the HKSAR and 1.9 km within Shenzhen. The bridge lands at Ngau Hom Shek in Hong Kong, and in Dong Jiao Tou in Shenzhen.

Deep Bay Link

9. We also propose to implement Deep Bay Link, which links up the SWC and our local road network. Deep Bay Link is proposed to be a dual 3-lane road of 5.4 km in length. (A map showing the proposed alignment is at Annex C.) The scope of works include –
(a) a short tunnel in Hung Shui Kiu to reduce environmental impacts;
(b) slip roads linking DBL to the proposed Hung Shui Kiu New Development Area and the local road network in Yuen Long; and
(c) an interchange at Lam Tei linking Yuen Long Highway. The DBL will be linked to the Yuen Long Highway in its initial years of operation.

10. Our traffic forecasts indicate that the existing road network including Yuen Long Highway and Route 3 should be able to cater for the traffic of DBL in the initial stage. In the longer term, Route 10 between Yuen Long Highway and So Kwun Wat will be required. While our current planning is that this section of Route 10 would be completed after 2010, we will closely monitor the traffic situation and continue to review regularly its need and timing.

11. We propose to commence detailed design for the SWC and DBL in early 2002.

Financial Implications

12. The total cost of the section of the SWC within the HKSAR is estimated to be HK$2.8 billion. The cost of the DBL is estimated to be HK$7.723 billion.

Land Acquisition

13. A part of an existing oyster bed may have to be resumed under the SWC project. As to the DBL, it may require resumption and clearance of some private lots and graves, a private batching plant and Hing Tak Public School. In the course of finalising the alignment, we will try to minimise the extent of the area to be affected.

Environmental Implications
Shenzhen Western Corridor


14. The feasibility of the SWC project was established by the Feasibility Study for Additional Cross-border Links. No
insurmountable adverse impact was identified but a further detailed assessment would be necessary to address all the issues thoroughly.

15. We are applying for an environmental impact assessment study brief for the SWC under the EIA Ordinance. Deep Bay is known to be an ecologically sensitive area. We will take due care in choosing an alignment with appropriate structural form and construction methods, which are acceptable from the environmental point of view. Also, we will fulfil the requirements under the EIA Ordinance and devise mitigation measures to minimise impact on the environment.

Deep Bay Link

16. An environmental impact assessment has been carried out under the Feasibility Study for Additional Cross-border Links, which concludes that the DBL will unlikely cause insurmountable adverse impact on the ecological and water quality of the environment. The DBL might have localised impact on individual areas and the issues identified would be assessed in a detailed environmental impact assessment.

17. A more thorough EIA is being carried out. The initial finding is that with proper mitigation measures, impacts on noise, air, visual and water qualities etc. can be abated to acceptable levels. Moreover, we will plant trees to compensate loss during construction. We will also avoid damage to concerned archaeological heritage.

18. We will submit the EIA report for the Director of Environmental Protection’s approval under the EIA Ordinance and will follow the statutory procedures of making the EIA report available for comments by the public and the Advisory Council on the Environment.

19. The DBL is a designated project under Schedule 2 of the EIA Ordinance and an environmental permit is required for the construction and operation of the project. We will incorporate the recommended mitigation measures into the detailed design and shall apply for an environmental permit for the project prior to commencement of construction.

Drainage Impact Assessment

20. A Drainage Impact Assessment for DBL is being undertaken. We will take all necessary precautions and mitigation measures to ensure that the project will not affect the existing local drainage system either during construction or when the road is in service.

Public Consultation

21. We will be consulting the following bodies –
(a) Tuen Mun District Council;
(b) Tuen Mun Rural Committee;
(c) Yuen Long District Council Traffic and Transport Committee;
(d) Ha Tsuen Rural Committee;
(e) Advisory Council on the Environment.

The Way Forward

22. We will seek the approval of the Public Works Sub-Committee of the Finance Committee in November 2001 to upgrade the detailed design works of the SWC and DBL to Category A. The construction programme will be confirmed after commencement of the detailed design and consultation with the Mainland. The Hong Kong and Shenzhen authorities will endeavour to complete the project in 2005.
 

·
Moderator
Joined
·
122,077 Posts
Discussion Starter · #2 ·
西部通道年底竣工

港段工程完成82%
西部通道年底竣工

24/10/2005


【本報訊】連接新界西北及深圳蛇口的深港西部通道香港段工程已完成逾八成,可望年底竣工。路政署發言人表示,涉資二十三億元的西部通道落成後,除每日可額外增加最多八萬架次過境汽車的流量之外,橋上更裝有燈飾,綻放光芒,成為后海灣新地標。另外通道設計上亦特別加入少許彎度,可提高司機警覺之外,亦可讓他們欣賞通道的美態。

初期日行車三萬架次
全長五點五公里的西部通道主要由高架引橋和斜拉橋組成,其中三點五公里位於本港水域,由新界西北鰲磡石,橫跨后海灣至蛇口東角頭新填海區。路政署總工程師李大鈞透露,截至十月中,通道香港段的工程完成度已達八成四,銜接通道的后海灣幹線亦已完成八成二的工程,可望如期在明年配合蛇口的口岸設施落成後通車。預期西部通道啟用初期每天行車量為三萬一千架次,可紓緩落馬洲、文錦渡及沙頭角擠塞的跨境交通。

直彎設計覽大橋景色
李大鈞續稱,西部通道的設計蘊含獨特之處,司機駛上通道時,將發現走線有直有彎,沿途可欣賞大橋景色。通道上兩座斜拉橋橋塔互仰向對方,猶如將連接深港兩地的高架道路互相牽引,帶領兩地居民團結。另外,西部通道將仿照青馬大橋及汀九橋輔以燈飾,配合特別節日慶典綻放光芒,勢必成為后海灣的新地標。

李指出,工程特別照顧具高生態價值的后海灣,署方按照環評報告的措施興建一條長達一點八公里的臨時橋樑運送建材,並改善基圍的沉積情況,為雀鳥提供更理想的棲息地。
 

·
Moderator
Joined
·
122,077 Posts
Discussion Starter · #3 ·
October 23, 2005
Government Press Release
Western Corridor key artery to Mainland







Works on the Western Corridor's Hong Kong section - which is more than 80% complete - have been progressing smoothly, Highways Department Chief Engineer Joseph Lee says.

When it opens in 2006, the new boundary crossing will accommodate 31,000 vehicles daily, becoming a key artery to the Mainland.

The 5.5km-long Western Corridor will be the fourth vehicular boundary crossing between Hong Kong and the Mainland. It starts at the newly reclaimed area for the boundary crossing facilities at Dongjiaotou, Shekou.

More than 80% complete

It will straddle Deep Bay and land at Ngau Hom Shek in the Northwest New Territories. From there it will connect to Yuen Long Highway via the Deep Bay Link.

Both Hong Kong and Shenzhen are building the new boundary crossing, in the form of viaducts and cable-stayed bridges.

Mr Lee tells new.gov.hk about 84% of the works on the 3.5km-long Hong Kong section have been completed. "We are confident that it will, together with the Deep Bay Link, be completed by the end of this year as planned."

Chief Executive Donald Tsang announced in his Policy Address the new road link will open to traffic next year when the control point at Shekou is completed.

Transport Department figures revealed in August, the daily traffic flow of the three existing boundary crossings - Lok Ma Chau, Man Kam To and Sha Tau Kok - reached 32,313, 8,003 and 2,545 vehicles, higher than their total capacity of 42,500 vehicles a day.

On a year-on-year comparison, the daily traffic flow of Lok Ma Chau, Man Kam To and Sha Tau Kok rose 3.6%, 3.1% and 13%.

Cross-boundary traffic capacity to rise

The Western Corridor, upon its opening next year, will offer an additional daily traffic capacity of 80,000 vehicles, raising the overall daily cross-boundary traffic capacity and thereby easing the current congestion.

Mr Lee said cross-boundary vehicles using the Western Corridor may use the Yuen Long Highway, Tuen Mun Road or Route 3 Country Park Section to access other parts of Hong Kong. The capacity of these roads are able to cope with the increased traffic.

Apart from providing a more convenient cross-boundary transport link to boost economic development, particularly in areas of finance, logistics and tourism, the Western Corridor will strengthen Hong Kong's position as the hub of the Pearl River Delta area and enhance trade between the city and South China.

Mr Lee said the new road link also has symbolic and aesthetic functions.

Symbol of synergy

"The towers for the two cable-stayed bridges are inclined towards each other, pulling their approach viaduct towards the boundary. This design symbolises the desire of the two regions to build a synergistic relationship for greater prosperity.

"As the Western Corridor will become a prominent landmark in Deep Bay, architectural lighting will be installed to light up the bridge during festive occasions."

Participating in the project since early 2001, Mr Lee said the project is on a "super fast track".

"For a highway project similar to the Western Corridor Hong Kong section, the planning and construction process usually takes eight years to complete. However, in view of the project's tight programme, we have worked out ways to save time and the project has progressed smoothly, thanks to the co-operation of parties concerned."

Care for the environment

The project has also demonstrated great concern for the environment, Mr Lee noted.

Extensive consultations with the green groups were carried out and their views taken into account. The Advisory Council on the Environment endorsed the Environmental Impact Assessment Report for the Western Corridor Hong Kong section and the Director of Environmental Protection approved it in 2002.

Contractors are implementing all the environmental mitigation measures recommended in the report, to ensure the water quality and the environment in the Deep Bay area will be maintained.

A water channel also connects the gei wais - or shrimp ponds - in Mai Po to Deep Bay. This will improve the water-exchange capacity and enhance the birds' feeding ground.

Temporary steel bridge protects mudflats

Taking into account that Deep Bay is an ecologically important area with extensive inter-tidal mudflats in close proximity to the Mai Po Nature Reserve Area, a temporary steel bridge has been built.

"The 1.8km long, nine-metre wide temporary steel bridge is the largest of its kind in Hong Kong. Built with 12,200 tonnes of steel, the bridge enables the transport of construction materials over mudflats without polluting the area," Mr Lee said.

Works on the Western Corridor Hong Kong section, started in August 2003, will be completed by the end of the year at a cost of about $2.29 billion.
 

·
POUND THE ALARM!!!
Joined
·
397 Posts
I love it!!!
 

·
Moderator
Joined
·
122,077 Posts
Discussion Starter · #7 ·
Corridor may snarl traffic in northwest New Territories

The Hong Kong-Shenzhen Western Corridor, expected to relieve congestion at the Lok Ma Chau, Man Kam To and Sha Tau Kok checkpoints, may result in massive traffic jams in the northwest New Territories, legislators said.

Winnie Chong
Hong Kong Standard
Saturday, January 07, 2006

The Hong Kong-Shenzhen Western Corridor, expected to relieve congestion at the Lok Ma Chau, Man Kam To and Sha Tau Kok checkpoints, may result in massive traffic jams in the northwest New Territories, legislators said.

Five Legislative Council transport panel members came to the conclusion after an inspection of the Hong Kong end of the corridor at Lau Fau Shan.

They said they were generally satisfied with the progress of the bridge construction, with more than 90 percent of the Hong Kong side already completed. Over the next two months, asphalt will be laid on the bridge and the corridor could be opened by year-end.

However, as vehicles could run to the west side of Tuen Mun or the east side of the New Territories by using Route 3, this could increase the traffic in the northwest New Territories, including Yuen Long and Tuen Mun, panel chairman Lau Kong-wah said.

"Many big vehicles may choose to travel to Tuen Mun because of cheaper costs. This could lead to serious traffic jams on Tuen Mun Road," he said. Lau urged the SAR government to utilize Route 3 to divert traffic flow.

Highways Department major works project manager Chow Ying-shun said cars could travel from Shenzhen via Deep Bay Link and Tuen Long Road to Route 3 in 15-20 minutes.
 

·
Moderator
Joined
·
122,077 Posts
Discussion Starter · #8 ·
HK, Shenzhen bridge the gap
21 January 2006
South China Morning Post

After months of uncertainty, the two ends of the Hong Kong-Shenzhen Western Bridge were joined yesterday and it is expected to be open by the end of the year.

The 5.5km bridge spanning Shenzhen Bay will become an important link between the western part of Guangdong and Hong Kong.

Shenzhen Mayor Xu Zongheng , who led the bridge-joining ceremony with Secretary for Environment, Transport and Works Sarah Liao Sau-tung, hailed it as an important step towards economic integration.

The bridge will link Yuen Long with Shekou . Travelling time from Shenzhen Airport to Hong Kong could be cut by at least half an hour when the bridge opens.

It will also help ease traffic congestion in Shenzhen. Vehicles from Guangzhou, Zhuhai and Foshan will be able to travel to Hong Kong via the bridge without entering the crowded Futian and Lowu districts.

The bridge was proposed by the Shenzhen government in 1991 and approved by the central government in 1997. It has been funded by the Hong Kong and Shenzhen governments.

The joining of the two ends yesterday was a relief for authorities on both sides as construction had been hit by difficulties. Foundation work was suspended briefly in 2004 amid accusations of negligence after the contractor ran into a piling problem.

The contractor said it could not drive posts into the ground below the waterline to support the structure because of an unexpected layer of mud and sand deep beneath the seabed.

But a Shenzhen government worker yesterday said they had successfully solved the technical problem, and hailed the construction of the bridge as an engineering achievement.
 

·
Moderator
Joined
·
122,077 Posts
Discussion Starter · #9 ·
Land boost for Hong Kong box storage.
23 February 2006
Lloyd's List

OFFICIALS have expanded the amount of land available for container storage and repairs by nearly a third in Hong Kong’s north-west New Territories, writes Keith Wallis.

The move coincides with the opening of the 5.4 km long Hong Kong-Shenzhen bridge later this year.

Legislator Miriam Lau, who represents the transport industry, was told by government minister Michael Suen that the amount of land for container operations has been increased by 229 ha from 617 ha to 846 ha.

The bridge will provide a fast route between the Shenzhen ports of Shekou and Chiwan and Hong Kong. Industry insiders believe the bridge, which is running about nine months late, will be the main truck route between Hong Kong and central and western Shenzhen.
 

·
Moderator
Joined
·
122,077 Posts
Discussion Starter · #10 ·
LCQ12 : Assessment of vehicles using HK-Shenzhen Western Corridor
Wednesday, March 1, 2006
Government Press Release

Following is a question by the Hon Abraham Shek and a written reply by the Secretary for the Environment, Transport and Works, Dr Sarah Liao, at the Legislative Council meeting today (March 1) :

Question:

It has been reported that the Hong Kong-Shenzhen Western Corridor (the Corridor) is expected to open at the end of this year or early next year. The Government estimates that the Corridor will aggravate the traffic congestion on the already over-loaded Tuen Mun Road. Designed to relieve traffic congestion at the checkpoints in Lok Ma Chau, Sha Tau Kok and Man Kam To, the Corridor will also increase the traffic flow in northwest New Territories, including Yuen Long and Tin Shui Wai. In this connection, will the Government inform this Council:

(a) as the reconstruction of and improvement to Tuen Mun Road will only be completed in 2010-11, how the Transport Department will relieve the traffic congestion in northwest New Territories, which will be aggravated by the opening of the Corridor; and

(b) whether the authorities will work with the operator of Route 3 to make special arrangements for diverting the traffic on Tuen Mun Road to Route 3, thereby reducing the traffic flow on Tuen Mun Road?

Reply:

Madam President,

The Hong Kong section of the Hong Kong-Shenzhen Western Corridor (the Corridor) was completed at the end of last year. Based on the progress of the works that have been carried out thus far, it is estimated that the Shenzhen section of the Corridor and the main works for the boundary-crossing facility at Shekou will be completed in the end of this year. Hong Kong and Shenzhen will continue to work closely together with the objective of opening the Corridor to traffic within the first half of next year.

In the Northwest New Territories Traffic and Infrastructure Review 2004 (the Review), we have examined in detail the traffic implications of the commissioning of the Corridor on the transport infrastructure in northwest New Territories. As we have explained to the Panel on Transport of the Legislative Council when reporting the results of the Review, the existing road networks in northwest New Territories together with road projects that have been planned for the region should be able to cope with the traffic demand, including the additional demand that the Corridor will bring about, up to 2016.

According to our assessment, there will be about 31,000 vehicle trips daily (vtd) using the Corridor when it is open. At that time, there will be a total of around 160,000 vtd using Tuen Mun Road and Route 3, which will be below the total designed capacity of 250,000 vtd of the two major trunk roads in northwest New Territories. We expect that by 2016, there will be about 60,000 vtd using the Corridor, and at that time around 188,000 vtd will be using Tuen Mun Road and Route 3. That level will still be below the total designed capacity of 250,000 vtd of the two trunk roads.

Nevertheless, in order to relieve the traffic pressure on the town centre section of Tuen Mun Road, we have drawn up several short and medium-term traffic improvement plans. Some of those plans have already been implemented, including lengthening of the bus bays along the town centre section of Tuen Mun Road to increase their capacity and reduce obstruction to traffic on the main road; and improving the lanes merging from Tuen Hi Road into the town centre section of Tuen Mun Road. As regards medium-term measures, we will widen the section of Tuen Mun Road near Tsing Tin Interchange from two lanes to three lanes for each direction. We expect the widening works to be completed by mid-2008. We have also commissioned a consultancy study to examine whether it is feasible to introduce further traffic improvement measures at the town centre section of Tuen Mun Road. We expect that the study will be completed by mid-2006.

For the long term, we have drawn up a plan to provide new strategic transport infrastructure to meet the growth in traffic demand in the northwestern part of the New Territories after 2016. Different possible highway packages have been examined in the Review. We have allocated resources for preparatory work for the possible highway packages such as site investigation work and further studies. These will enable us to provide the supporting transport infrastructure to meet the development needs in a more efficient and timely manner in future.

Apart from continuing to encourage the franchisee of Route 3 to offer more concessions to more vehicle types, we are actively exploring with the franchisee other possible measures to rationalise the utilisation of Route 3 and Tuen Mun Road.
 

·
Moderator
Joined
·
122,077 Posts
Discussion Starter · #14 ·
深西通道明年7.1啟用
料胡錦濤主禮 實施一地兩檢

18/08/2006



【專案組記者簡淑明報道】由元朗鰲磡石橫跨后海灣至深圳蛇口的深港西部通道,貫穿中港兩地的首條跨海大橋,港府計劃於明年七月一日香港特區成立十周年,由中央領導人主持落成儀式後才正式啟用。為使本港紀律部隊人員可在通道上執法,實施一地兩檢模式,港府正等候中央授予司法及行政管轄權,並在立法會十月復會後將《香港管區條例草案》提交審議。

候中央授行政司法管轄權
深西通道的落成日期一延再延,外界一度揣測是港深兩地尚未洽妥大橋的管理權及如何分配車輛配額等等問題,為消弭外界的憂慮,行政長官曾蔭權較早前到廣州參加粵港合作聯席會議時亦刻意提及,深西通道的工程已進入最後階段,期望明年七月一日前通車。

政府消息透露,跨海大橋的土建工程年底基本完成,只待安裝配套設施後即可啟用,港府為加強新口岸的清關能力,已展開大規模的招聘行動,當局欲將這條大橋作為明年香港特區政府成立十周年的大禮,估計由國家主席胡錦濤抵港舉行開幕儀式後才正式啟用。

為配合七一通車,兩地必須盡快落實「一地兩檢」模式,由中央賦予香港紀律部隊人員在原屬內地的蛇口範圍執法。政府消息人士指出,港府的相關程序已完成,正等候中央正式授權行政及司法管轄權,同步亦會在立法會十月復會後將相關的《香港管區條例草案》提交立法會審議,草案主要在深西通道實施「一地兩檢」,建立過境設施提供法律依據。據悉,深西通道的旅檢大樓建構大致完成,整個大樓長度二百米,清楚劃分香港在南面、內地在北面。
 

·
Registered
Joined
·
353 Posts
Wow. I'd never heard of this causeway before today. When is the projected completion date?

And when will construction begin on the Lantau to Zhuhai/Macau bridge?
 

·
Moderator
Joined
·
122,077 Posts
Discussion Starter · #16 ·
Cunning Linguist said:
Wow. I'd never heard of this causeway before today. When is the projected completion date?

And when will construction begin on the Lantau to Zhuhai/Macau bridge?
This bridge is almost done. The Zhuhai / Macau bridge is still under discussion so it'll probably take a few more years before it becomes visible.
 