a recent reply to my email regarding progress in these towers...


Good morning!

Further to your e-mail below, please be informed that we haven’t stopped construction on any of our projects. The December payments for Sedrawan have been deferred till June but the management still has to make a decision on the payment plan. As far as RT3-C2 and Marina Bay are concerned, the construction is going on and hasn’t stopped. Please find attached the construction reports for RT3-C2 and Marina Bay.

FGB and Aseel are providing finance upto 80% to clients for our projects.

Should you need any further assistance please do not hesitate to contact me.

Best regards,
 

·
banglaboy
Joined
·
455 Posts
Discussion Starter · #4 ·
Called GEP in abu dhabi....

Security got the phone and said staff do not work Fridays, Saturdays and Sundays! Strange or have they got nothing to do as nothing to sell...
 

·
Registered
Joined
·
156 Posts
And you know you want to take that finance!

How about interest free since its your bank ya buggers!
That´s surprisingly astute dbxdude..Have a cigar!

First Gulf Bank, Al Dar Properties, Surouh Real Estate,
And Reem Investments are the shareholders in GEP which means that the Bani Fatima are in control.
 

·
Rrrraaaaaahhhhhhh!!!!!!!
Joined
·
9,583 Posts
Any pictures, details etc?
Please make sure to post a render, details of heights, floors, usage and all that sort of stuff if available. Make a new thread then with the right stuff at the beginning.
 

·
Registered
Joined
·
14 Posts
Is this the last page?
I am wondering how construction is going in the Green Emirates Pearl Bay..still no contracts... going slowly.
 

·
Registered
Joined
·
10,939 Posts
Aug/2009

Site Progress

Foundations: casting completed on Aug 28
Construction of Basement 3 retaining walls and columns
in progress
3 out of proposed 10 Tower Cranes erected

To #UNDER C




 

·
Registered
Joined
·
3 Posts
any Contact to present our Solutions in

(LVS, system integrations ,IBS (intelligent building system , BMS (building management System), ITS (intelligent transportation system ) , LED light
 

·
Registered
Joined
·
1,272 Posts
Construction Update - October 2009

Site Progress

- C2 Tower: B2 Slab & B2-B1 Retaining Wall, Core Wall &
Columns completed; B1 Slab, B1-GF Core Wall &
Column in progress
- C3 Tower: B2-B1 Slab & B1-GF Retaining Wall, Core Wall &
Columns completed; GF Slab in progress



 