Here is a larger version of the rendering. Sigma 1 and 2 have the exact same floorplans. These will be ready in 2011 about 6 months to a year after Hydra Avenue and Phase 1 of the City of Lights.

I have some listings in this project so contact me if you are interested. Google my name to find me.

-Gerald

 

·
Registered
Joined
·
10,939 Posts


-------------------------------------------------------------------------

Construction Update March/2009

Please Change title to #Ground Work: SOLARIS TOWERS (SIGMA I+OMEGA +SIGMA II) , 28F Res +35F Com+28F Res ( City Of Lights )




Source
http://www.gep.ae
 

·
Registered
Joined
·
275 Posts
Piling complete, main contractor now on board - 2011 completion is a little optimistic...expect early 2012
 

·
Registered
Joined
·
1,272 Posts
Construction Update - August 2009

Site Progress

- Raft Foundation: casting completed on Aug 26
- Construction of Basement 3 retaining walls and columns in progress
- 3 out of proposed 10 Tower Cranes erected
 

·
Registered
Joined
·
3 Posts
ِAny Contact to present our Solutions in

(LVS, system integrations ,IBS (intelligent building system , BMS (building management System), ITS (intelligent transportation system ) , LED light
 

·
Registered
Joined
·
1,272 Posts
Another construction update - October 2009

Site Progress

- Towers C10/C11: B2 Slab, B3-B1 Retaining Wall, Core Wall &
Columns completed; B1 Slab in progress
- Tower C10a: B2-B1 Slab, B1-GF Core Wall, B3-B1 Retaining Wall &
Columns completed; B1-GF Retaining Wall & Columns in progress



 

·