Discussion Starter · #1 · (Edited)


Beirut, Lebanon







A Remarkable Art of Living

Discrete, elegant in its modern facades, Saifi Pearl nurtures with an enthusiasm of a true softness of living.
Inserted well in its prominent environment, this new residential program offers the attraction of unit to voluntarily human size.
Arising naturally on Georges Haddad Street in Saifi district, it offers to its residents a quality and a very attractive framework of life, close to schools and colleges, and few steps away from the hub of the city, shopping center, embassies, restaurants…

Saifi Pearl offers the functionality of a modern architecture, the approval of materials and quality in services are guaranteed by one of the leaders name in the construction Mouawad Investment Group.

The project is being developed on 1,620m2 of land for a total build-up area of 12,000m2 to include apartments with private gardens and terraces on the ground floor with areas that vary between 170m2 and 330m2, typical apartments of various dimensions on the 10 upper floors with sizes that vary from 140m2 to 600m2, and a penthouse on the 12th floor of 900m2.

Saifi Pearl embraces:​
  • 2 garden apartments on the ground floor (1 to 3 bedrooms, gardens and terraces…) from 160 to 210 m2, and a duplex of 380 m2 on the ground and 1st floors (3 bedrooms, living area, garden and terraces…)
  • 3 studios found on the first floor with areas that vary from 40 to 60 m2.
  • 41 typical apartments from the 1st to the 11th floor (2, 3 & 4 bedrooms, living area, gardens and terraces) with areas that vary from 140 m2 to 600 m2.
  • A Penthouse on the 12th floor (5 bedrooms, living areas, gardens and terraces…) of 920 m2.
  • Parking spaces and cellars found on the 1st, 2nd, 3rd & 4th basement floors.
 

·
Registered
Joined
·
4,957 Posts
Do you know the exact location of this Beirut!??? All these saifi projects compliment each other, they are well made
 

·
Moderator
Joined
·
4,373 Posts
Discussion Starter · #5 ·
Latest Update:


+ The building is divided into 2 sides, one on the back and one on the front.


Back side:
+ The Ground floor slab has been poured.

Front side:
+ The 1st basement slab has been completed.

+ The Ground floor slab is expected to be completed by week 43.
 

·
Moderator
Joined
·
4,373 Posts
Discussion Starter · #6 ·
Lastest Update:



+ Concrete works reached the third floor.

+ Concrete works expected to be completed by end of October 2008.

+ Masonry works are almost completed in the basements and ground floors, and have started in first floor.
 

·
Moderator
Joined
·
4,373 Posts
Discussion Starter · #7 ·
Latest Update (Sept. 18 2008):

+ Concrete works have reached the 12th floor.
+ Concrete works are expected to be completed by end of November 2008.
+ Masonry works are completed basement floors and have reached the 9th floor.
+ Electro-mechanical works are in progress in all apartments.
+ Cladding is expected to start by the end of October 2008.
+ Tiling in all apartments is expected to start early October 2008.
+ Installation of metallic sub frames for aluminum has started.
 

·
Moderator
Joined
·
4,373 Posts
Discussion Starter · #8 ·
+ Concrete works are completed.
+ Masonry works completed, except on the 12th floor, where completion date is expected by week 49.
+ By the end of November 2009, all common areas and main entrance will be completed.
+ Cladding is completed at all facades.
+ All scaffolding will be dismantled by end of November 2009.
 