SkyscraperCity Forum banner

UYO | Akwa Ibom International Airport | Under Construction

145072 Views 320 Replies 54 Participants Last post by  Jakepor
9
PROJECT DATA
[info updated May 3rd, 2007]

Project Title: Akwa Ibom (Uyo) International Airport
Location: Uyo, Akwa Ibom, Nigeria
Project Owners: Akwa Ibom State + DynCorp International (USA)

Project Budget: $300,000,000
Year Construction start: 2006
Design Consultants: LPA Group (USA)
Contractors: N/A
Promoter: Akwa Ibom State Nigeria
Designers/Architects: N/A
Features: Initial phase for the new airport will include a 3,600 meter runway with a CAT II approach, navigational aids, a four-gate terminal building, and a maintenance / repair / overhaul (MRO) facility capable of accomodating 2 Boeing 747-400 wide-body aircraft simultaneously. The construction cost of the initial phase is expected to exceed $125 million. This portion of the project is scheduled to be open for operations in 2007. The final phase will include a permanent passenger terminal and cargo facility which will result in total project costs in excess of $200 million.






CONSTRUCTION PHOTOS TAKEN IN EARLY 2007:

Above: Stone base installation on Runway looking south from Station 12+960

Above: Preparation for stone base on Runway

Above: Clearing Mobilization area for new Subcontractors

Above: On-site Borrow Pit operations

Above: Stone base installation on Runway looking south

--------------------------------------------------------------------

The following description was culled from the project website http://www.akianigeria.com/akwaibom/home/index

AKIA development will be undertaken in two phases. Phase 1, which started in November 2005, is scheduled to be completed for beneficial occupancy in the First Quarter of 2008 and consists of the following:

Airside facilities including a 3600 meter runway, aprons, an Air Traffic Control Tower (ATCT), fuel storage facility, and an Airfield Rescue and Fire Fighting Facility (ARFF).
Landside support including roads, utilities, and an interim passenger terminal.
National Hangar MRO Center.
Phase 2 construction will include expanded airside facilities (taxiway and aprons), an international passenger terminal, air cargo facilities, Administration Building, expanded terminal parking, fuel storage facilities, and access roads

Substantial progress has been made on the design, structure, supplies, and equipment for the MRO. In addition, works on the MRO are being coordinated with works on the airfield, since it is a prerequisite that the airfield be operational at the time that MRO construction is completed.

Structural Frame and Foundations-the design of the structural frame foundations and architectural finishes of the MRO Center is complete. The 4,500 ton structural package for the MRO Center is being fabricated in China with deliveries to the jobsite expected to occur in June – December 2007. The erection subcontract has been awarded and foundation work will commence in March 2007 with a substantial completion date in November. The massive double set of sliding hangar doors will be completed in early January 2008.
Crushed stone base is currently being installed on the runway in preparation for the cement-treated base and asphalt surface to follow.
A subcontract for construction of the ATCT, ARFF, Interim Terminal, and Lighting Vault has been awarded and construction will commence in March 2007.
Designs for the water, sewer and storm drainage packages are 95 percent complete. Electrical infrastructure design is in progress.
The design of the parallel taxiway that will connect the international terminal and cargo facilities to the runway is 100 percent complete and will be constructed as part of the Phase 2 facilities.
A subcontract has been issued for landside paving, and parking, and work has commenced.
Hangar Support Equipment (for work stands, tools, testing, and hydraulic equipment) has been identified and a request for proposals has been issued.
Computer Operations Systems have been tendered and proposals for supply, installation and training are being evaluated.
NAVAIDS, ATCT Communication equipment, and Weather Stations have been tendered and award of the subcontract for supply, installation, training, and site-acceptance testing will occur in March 2007.
Emergency vehicles for the ARFF have been ordered with delivery anticipated in November 2007.
See less See more
1 - 20 of 321 Posts
Im not a big fan of the design of the airport, at this day and age we need more innovation!!
Im not a big fan of the design of the airport, at this day and age we need more innovation!!
I agree. The terminal building does not look contemporary nor African. It looks retarded, plain and simple! Nigeria should look at other low-cost airports in South Africa, North Africa, and elsewhere, and learn how to build low-cost yet visually attractive airports. In any case i hope that this project will at least give Uyo a functional, safe airport conforming to the highest specifications. Aesthetics is a secondary issue here...
I hope that this is not one of those white elephant projects. Does Uyo has the economic clout to adequately utilise an International airport of that size, moreso, when you already have one at calabar and Port Harcourt? The Government should rethink of a more value adding project like the Tinapa.
I hope that this is not one of those white elephant projects. Does Uyo has the economic clout to adequately utilise an International airport of that size, moreso, when you already have one at calabar and Port Harcourt? The Government should rethink of a more value adding project like the Tinapa.
despite the fact that we have both the portharcourt and calabar airport the uyo one is unique in the sense that a to d checks can be performed here on all types of aircraft including the airbus A380. it will also be the largest maintainance hangar in africa therefore being the new national hangar. in short we will no longer have to fly abroad to repair our planes plus it will bring more money into the economy in that other airlines in the region and the continent will fly to nigeria to maintain their planes as it is cheaper to do it here than abroad
I would agree the design in very great but it is the economic benefits to Nigeria that impress me . A maintenance airport form Nigeria with a FAA rating is going to provide some very good jobs to local people and that is the key to developing Nigeria beyond the petrochemical industries. This is huge money into Nigera and if executed well it could be the start on many other similair investments from foreign countries.

Communication Satellites, Dynacorp Aerospace Parks , developments in real estate and tourism, the bank sector expanding privately, government owned companies being bought with private capital it is all very good for Nigeria.
  • Like
Reactions: 1
6
Construction Photos taken June 2007





See less See more
i also dont get the need for an airport in Uyo with Calabar 1 hour away. with good roads calabar even gets closer. Perhaps with calabar expanding to accommodate international flights it will leave more local business to uyo. additionally the repair component of uyo is very attractive.

who know, with those cities so close to each other, a very large metro area may emerge in the future and these two airports will be overwhelmed.
The UYO Airport is being built mainly to service Aircrafts that will normally be done in Europe
Lawmakers threaten showdown over A’Ibom airport
By Chukwudi Akasike
Published: Sunday, 12 Aug 2007
The Akwa Ibom State caucus in the National Assembly may be on a collision course with Dyncorp; the contractor handling the state‘s international airport project.

The caucus, which comprises all members of the House of Representatives and the Senate from the state, is dissatisfied with the stalled airport project.

The Chairman of the Caucus, Mr. Benard Udo said during a tour of the project on Friday that work on the project, which began in 2005 had unduly been delayed for so long to the detriment of the people of the state.

He expressed surprise that only 20 percent of the total work had been carried out at the airport site as no part of the runway had been tarred.

Udo explained that the contractors handling the airport project had been unfair to the people of the state.

He said despite the fact that the contractor had been at the site for 18 months, only 20 percent work had been done.

Udo, who is a member representing Ikot Abasi/Mkpat Enin/Eastern Obolo Federal Constituency became more angry when the Site Manager, Mr. Mike Cofilini could not state the amount that had been received so far for the project.

According to him, since the site manager failed to give account of what had been spent so far, the tour to the airport site by members of the caucus was not necessary.

Responding, Cofilini said he was only a technical man and could not ascertain how much had gone into the project so far.

The site manager, however, explained that the reason work on the project had been stalled was as a result of lack of funds.

He said though, the duration of the project was two years, Dyncorp would execute the remaining 80 percent work within six months if funds were provided by the state government.

A member representing Ini/Ikono Federal Constituency in the state, Dr. Ini Udoka told the site manager that the people of the state were angry over the slow pace of work on the project.

”It is unacceptable that the runway has not been tarred in a project that will last for two years and 18 months had already been spent,” he said.

Competent sources said that over N4 billion had already been spent on the project which will cost the state about N5 billion.
See less See more
This airport is being built because Uyo has no existing airport.
Noooo.....REALLY? :lol:

The question is: Does Uyo need an airport or more hospitals?
oh come of it...the airportis gonna be vital to the economy of the state...the state doesnt have hospital problems and i know cos i'm 4rm that state
I'm mostly interested in the engineering aspect of this project.

Iluvnaija, it's going to take much more than your sentance to convince me that Uyo and Akwa Ibom "need" an airport, given Calabr is only 45 km away, while PHC is a mere 120 km away. I just can't see why this project was given priority instead of building power stations and competitive industries in the state! Bottom line: an economy feeds airport business, not the other way.

I'm not saying I'm against the project, only believe that this project costs waaay too much for what the state will get. It remains to be seen whether Attah and his DynCorp gang will account for their expenditure so far, yet the runway is not even paved yet...

On a similar note, I was astonished to learn that Osun State is also building an airport! This time reactivating an old project, for the sake of promoting a free trade zone. Geopolitics and rivalry between Nigerian states is truly petty, because I think much more can be accomplished if a wholistic air transport masterplan is drafted at a national level whereby states would cooperate and share FUNCTIONAL+SAFE airports. This would contrast with the current situation where the endless state governments build dysfunctional+unviable airport in each of Nigeria's 40+ state capitals.

My 2 cents...
See less See more
yeahv but it'll be the only one in west africa and maybe the second in africa tht can offer full maintainance for all kinds of palnes..tell me when a whole lot of planes are coming from all over africa to fix they planes in your state it aint good...plus currently all nigerian airlines take their planes to europe to get fixed but now they can do it in the country enhancing the countries air safety and promoting airline growth by lowering the cost of maintainance
yeahv but it'll be the only one in west africa and maybe the second in africa tht can offer full maintainance for all kinds of palnes..tell me when a whole lot of planes are coming from all over africa to fix they planes in your state it aint good...plus currently all nigerian airlines take their planes to europe to get fixed but now they can do it in the country enhancing the countries air safety and promoting airline growth by lowering the cost of maintainance
is that the sole purpose of the airport or will it also handle commercial flights
2
Update

Substantial progress continues to be made despite continuing rains and funding delays associated with the transition of a new State government. The construction of temporary and permanent drainage systems, upgrading of temporary access roads, and the use of sand embankment has been implemented to allow most construction activities to resume quickly, even after torrential down-pours.

* The 3,500 ton structural package for the MRO Center is being fabricated to specifications by Atlantic Projects Company (HK) Ltd in China with deliveries to the jobsite expected to occur in November – December 2007.
* The 1,000 ton structural package for the ATCT, ARFF, Interim Terminal, MRO Pump House, and Lighting Vault is also being fabricated by Atlantic Projects Company (HK). The first two shipments have docked at Onne Port and are currently in customs clearance. Another six ships are currently at sea containing the balance of the steel for these buildings.
* Crushed stone base is currently being installed on the runway in preparation for the cement-treated base and asphalt surface to follow. Over 50% of the runway surface is now covered with stone base.
* The subcontract for construction of the ATCT, ARFF, Interim Terminal, and Lighting Vault has been awarded and construction commenced in June 2007. Footing excavation and blinding concrete has commenced on all buildings and column anchor bolts have been delivered. Placement of footings will begin in September.
* Designs for the water, sewer and storm drainage packages are complete. The Invitations For Bid will be issued after receipt of Customer approval of the Bidder's List. Electrical infrastructure design is in progress and nearing completion.
* The Substation site has been selected and cleared for mobilization of Cub Three, a subcontractor to Power Holdings Company of Nigeria for supply and installation of the 33/15 MVA Substation.
* The design of the parallel taxiway that will connect the international terminal and cargo facilities to the runway is 100 percent complete and will be constructed as part of the Phase 2 facilities.
* A subcontract has been issued for landside paving and parking, and work is progressing. Most of the 4.2 km of roads have received stone base and preparations to begin asphalt paving in early November (with the on-set of the dry season) are continuing. With Customer approval, the roads subcontractor (Marlum Nigeria Ltd) will also install the road and parking lighting system.
* NAVAIDS, ATCT Communication Equipment, ATCT Cabin, Approach Lighting, and Weather Stations have been tendered and award of the subcontract for supply, installation, training, and site-acceptance testing will occur after receipt of Customer approval.
* Three Titan 6x6 P-111 emergency vehicles for the ARFF 2007 were factory tested by E-One on 24 August in Ocala, Florida. The successful testing was witnessed by Customer and DynCorp representatives. The vehicles are scheduled to ship on 31 August for site delivery in late October.
* Security system infrastructure design drawings were issued for review by The LPA Group and prequalification of bidders for installation has commenced.


See less See more
Akwa Ibom releases N4.6 billion for aiport project, micro financing

ABOUT N3 billion was released to contractors handling the construction of Ibom International Airport in Akwa Ibom State.

The state government also released N1.6 billion on micro credit financing and provision of fishing facilities for rural areas.

Governor Godswill Akpabio disclosed this recently in Uyo during an interactive session with journalists.

"The airport project is on course and by April 2008, the airport's 3,600-metre runway will be ready," he said.

The governor also disclosed that about 500 youths in the state had been provided employment in the skilled and semi-skilled construction phases of the project.

"The airport project at its operational phase will also provide more jobs," he said.

The News Agency of Nigeria (NAN) recalls that the airport project, conceived by the Governor Victor Attah administration in 2001 has three main components.

These are airport maintenance, repairs and overhaul, cargo and passenger operations with a completion deadline of December 2007.

Akpabio added that the airport, when operational would fast track the development of the state's economy in many sub-sectors.
well its past april is the runway finished
1 - 20 of 321 Posts
Top