Radio Valencia Cadena SER offers them exclusively the image that Juan Roig has presented to the City Council of Valencia to show the pavilion he intends to build together with L'Alqueria del Basket. In addition, we give you all the details of figures and terms

This is the image best kept by Juan Roig until today and the SER runs the curtain so that you can start to see what the future Valencia Arena Basket Pavilion will look like. Because this is what is called in the documentation presented to the City Council by the ERRE architecture offices with the collaboration of HOK . Amparo Roig, daughter of Juan Roig, is a partner of the ERRE office, which also designed L'Alqueria del Basket. Today we can see the image of Juan Roig's project for this pavilion and whose idea was already advanced by SER Deportivos Valencia in its program on February 6th.

The future pavilion is included in the documentation with a capacity of 15,100 spectators and in the development of the project it exhibits different scenarios for different uses : basketball pavilion as main use, but with full foresight for the celebration of great musical concerts, in order that Valencia can enter the circuit of major European and world concerts.

The Arena Valencia Basket project has a parking forecast for 1,800-2,200 parking spaces . The Arena Valencia Basket will be placed on the plot next to the current L'Alqueria del Basket , if Juan Roig has just reached an agreement with the City Council of Valencia on the legal formula for the use of the land on which the pavilion will be based, that is of public use and educational dotacional.

Juan Roig prioritizes the times and start as soon as possible, because he has the conviction that, if it is finished, the Final Four of the Euroleague of 2022 could be celebrated. Conversations has already had in this regard with the head of it, Jordi Bertomeu.
http://cadenaser.com/emisora/2018/04/17/radio_valencia/1523991632_824535.html
 

·
Moderator
Joined
·
20,960 Posts
Discussion Starter · #4 · (Edited)
Juan Roig wants to build a pavilion of 15,000 spectators in Valencia

The City Council would cede to the businessman the plot for fifty years, then it would become municipal property. If the agreement is made, the pavilion would be ready by 2022.


The patrimonial society of the businessman and maximum shareholder of Valencia Basket, Juan Roig , Licampa 1617 SL, presented this Wednesday in the register of entrance of the City of Valencia the project for a multipurpose pavilion, which would have a capacity of 15,000 spectators and a budget of 192 millions of euros.

The installation, which would be ready in 2022 , would be built on a municipal plot that the consistory would cede for fifty years to the employer, who would be responsible for all expenses with its assets, and would remain the ownership and management of the pavilion during that time to later become municipal property.

The company has announced that it has submitted " the documentation and dossier of the project so that, if the Mayor considers it, it will be presented at the Municipal Assembly to obtain the support of the Consistory ".

Roig's proposal includes the annual payment as a fee to the City Council of 2.7 percent of the income generated , and ensures that " if all administrative procedures are developed according to the schedule, and if there are no major setbacks, the Arena could be inaugurated in Valencia in 2022. "

The businessman and the City Council have been working for months on the project, with the formula of a concession for a period of 50 years of a plot of 21,500 square meters, located next to the pavilion of the Fountain of San Luis and L ' Alqueria del Basket, the quarry macro installation that opened the club a few months ago.

According to the project, the pavilion would have 15,000 seats and would be designed "with a high comfort index, and adjustable according to the need of the event, within a total surface area of ​​approximately 40,000 square meters".

The Arena includes 1,458 underground parking spaces and will have a restaurant area and a wide range of VIP boxes and areas.

In addition, the facility will be equipped with the most advanced technology, and the latest technical means for retransmission and monitoring of all types of events.

Likewise, in the plot described, the future headquarters of the Valencia Basket Club will be built, which will include sports services such as an auxiliary track, changing rooms, media area, shop, trophy room and club offices.

Roig's company would be the owner of the installation during that half-century, and would entrust "the management of the entirely private activity to a manager / specialist operator who will be responsible for developing and carrying out an attractive programming", as well as "of the exploitation and management of it with full autonomy".

The idea of ​​the entrepreneur is "to make the future Arena a space with musical, artistic and sporting events of first national and international level".

The joint investment would be 192 million euros that Juan Roig would assume entirely , and would be used " for the construction of the enclosure, the parking lot and other complementary infrastructures".

Roig has also commissioned a report to the Valencian Institute of Economic Research (Ivie), according to which the pavilion "will contribute to generate approximately 300 jobs" and would have "an economic impact (GDP) in the city of Valencia exceeding 10 million of annual euros".
https://www.cope.es/noticias/liga-e...r-pabellon-15000-espectadores-valencia_240571
 

·
Moderator
Joined
·
20,960 Posts
Discussion Starter · #8 · (Edited)






Valencia will have a multi-purpose venue of 18,600 spectators. The installation, which will be the new Valencia Basket pavilion, has expanded its capacity, as announced by the promoter of the complex, Licampa 1617. This is the company that created Juan Roig, owner of the club, to promote the new arena, which will be ready in 2022-2023. The planned investment is more than 220 million euros, exceeding 192 million announced in July 2018.

The idea is that the capacity of the pavilion for basketball games is 15,600 people, a figure that will be expanded to 18,600 locations when concerts are held. This was announced by the company after meeting with the mayor of the city, Joan Ribó, and some members of his government team. The Valencia Arena will be built on public land, whose use will be sports. It is a punctual modification that has been made in the General Urban Planning Plan (Pgou) after being approved in the September plenary session.

The investment will be made by businessman Juan Roig through the equity company Licampa 1617, a company established to promote this project. The works will begin in summer 2020, as long as the company and City Council reach an agreement. Since the initiative was presented, “it has evolved with the sole objective of providing Valencia with a multipurpose enclosure with the requirements to position the city and the Valencian Community as a world reference to host sporting, cultural and entertainment events of first level national and international ”, the company said.
https://www.palco23.com/clubes/zona...et.html?utm_source=dlvr.it&utm_medium=twitter
 

·
Moderator
Joined
·
20,960 Posts
Discussion Starter · #11 ·
The developer wants to finish the work in November 2022, in February 2020 the approval of the modification of the PGOU by the Generalitat is planned and in March the application for the construction license

The scaling of dates, to which this newspaper has had access, projects for June 2020 the official commencement of the works and for November 2022 the delivery of keys of the enclosure.

The main building on a plot of 21,000 square meters will be erected on the land next to Antonio Ferrandis, Ángel Villena and Bomber Ramón Duart, to achieve an area with capacity for 15,600 spectators in basketball games and 18,600 for concerts.
https://www.lasprovincias.es/deportes/valencia-bc/primera-piedra-arena-20200101195259-nt.html
 

·
Moderator
Joined
·
20,960 Posts
Discussion Starter · #13 ·
Mayor gives update on construction projects

Regarding the new arena, Ribó indicated that work on the future home of Valencia Basket should begin in June 2021 and all deadlines will be met.

The EuroLeague team from the third largest city in Spain has played in the Pabellón Fuente de San Luis so far, with a capacity of 9,000 seats, it is one of the smaller arenas in the competition. The arena opened in 1983 will soon be replaced - a new venue for € 220m is to be built by 2023.
https://www.stadionwelt.de/sw_stadi...n&folder=sites&site=news_detail&news_id=20581
 

·
Moderator
Joined
·
20,960 Posts
Discussion Starter · #14 ·
Valencia Arena: the coronavirus does not stop Juan Roig’s plans to open the pavilion in 2023

The coronavirus will not alter Juan Roig’s plans for the construction of the Valencia Arena, the new sports and cultural pavilion in the Quatre Carreres neighborhood with capacity for more than 18,000 spectators and with a budget of 220 million euros, entirely paid for by the owner. from Mercaddona.

Sources from Licampa 1617 – the company created by Roig exclusively to carry out this project and the only one that was submitted to the public competition – confirm to ABC that the schedule of performances remains intact despite the crisis caused by Covid-19. The works will start this summer to inaugurate the new multipurpose venue in 2023.

 

·
Registered
Joined
·
93 Posts
New step ahead. Yesterday, Town Council (Joan Ribó) and Licampa 1617 (Juan Roig) signed the agreement to lend the plot for the new Arena.

 

·
Moderator
Joined
·
20,960 Posts
Discussion Starter · #16 ·
Work on-site is expected to commence this summer, with a view to completing the arena in 2023.

The arena will be privately financed by Licampa, which was founded by Juan Roig, the billionaire businessman behind the Mercadona supermarket chain and owner of Valencia Basket. The arena will have a seated capacity of 15,600, which will extend to 18,600 with standing room.

Roig added: “My commitment to the development of this project is a source of pride, because it will also help to reactivate the city’s economy, while at the same time helping to raise the notoriety and reputation of Valencia and the Valencian community.”

 

·
Moderator
Joined
·
20,960 Posts
Discussion Starter · #20 ·


The esplanade , which previously served as a parking lot for users of the Fonteta and L'Alqueria, now has a frenzied activity with more than a dozen excavating and drilling machines that are shaping the foundation that a work requires that will support a structure of 47,000 square built for an enclosure that will have a capacity for 15,600 spectators at basketball games and 18,600 for concerts and shows.

The first phase of the work , which is being carried out in the month and a half since the first stone was laid on Monday, June 29, is currently focused on the containment of the land and the foundation of the Arena. The main action in August will be the excavation of the plot to a depth of approximately seven meters to make said foundation and the execution of the screen walls around the perimeter to protect this segment of work. It is an important part since the level of the main court, where Valencia Basket will play its matches, will be 4.5 meters below street level .

In this first phase, other tasks that are being planned include from the execution of deep foundations using piles and foundation slab, the electrical installation of the equipotential earth network, the drainage network of the foundation slab or the execution of ventilated slab and ventilation system of the same. Technical works for which the knowledge of the terrain has been key since the end of 2019 , when the geotechnical study was carried out. Taking into account that three months after that tasting the country was paralyzed due to the pandemic, if it had not had the results of the phreatic level that are key to designing the type of foundations necessary in the work, it would not have been in time to start the work within the established deadlines.

With the work shifts already established, where Ismael Padilla is the general coordinator of the construction and Víctor Ferré is the technical director, the forecast until the end of 2020 is of 26 million investment in the work . For the rest, Juan Roig has already supplied Licampa 1617 of the 220 million that will be necessary to complete the work as a whole , where 183 are those that will go to the main enclosure, 15 for the underground parking, 8 for the parking at height , 4 for the 20,000 square meter park to be built on the site that will be left by the current Les Arts school after its demolition, 8 for the construction of the new educational center and 2 for the urbanization.

 