Completion Date:
31/07/2010

Region:
Western Cape

Description:
The design of Phase 4 of this pristine development will mirror the architecture of the first three buildings. The 5 storey building features approximately 3,000 square meters of office space with a penthouse apartment featured at the top of the building.

Programme:
The fourth phase of the Waterview Park development will commence this year and expected completion will be approximately ten months from the time of tenant confirmation.

Features:
Office units of various sizes are available for tenant occupation with plenty of available parking. The Waterview precinct is ideally located on Century Boulevard close to Canal Walk and various other amenities, as well as the N1 and other major transport routes. For further information regarding this prime development, please contact Michael Van Schoor on 021 4611033 or 0828514078.
 

·
Moderator
Joined
·
23,361 Posts
Discussion Starter · #2 ·
After construction initially started years ago, the site's been "boarded" up with the pieces of a crane and a bunch of derelict construction equipment in a bit of a hole. It seems it's once again alive, with JT Ross listing completion as 30 November 2013 :)

I'm glad this bit of a blight will finally be covered up!
 

·
Moderator
Joined
·
23,361 Posts
Discussion Starter · #4 ·
Location: Century City - Cape Town
Client: JT Ross
Contract Value: R57,6 million
Project Duration: 11 months
Completion Date: July 2014
Total area size: 12,360m²

Construction of a multi-storey office block with basement parking

NMC was awarded the fourth phase of the Waterview Office Development in Century City.

The R57,6 million project has a gross building area of 12,360m² and comprises of six levels; with four levels (ground to third floor) being parking levels and levels four to five will accommodate 3,000m² of lettable office space. The remaining sixth slab will be a roof slab.

The design ties in with that of the first three buildings.

Source: NMC

 

·
Moderator
Joined
·
23,361 Posts
Discussion Starter · #6 ·
Waterview Office Development



Construction of Phase IV of the Century City based Waterview Office Development, comprising a multi-storey office block with basement parking, is on programme for an August 2014 completion.

The R57,6 million project has a gross building area of 12 360m² and comprises of six levels; with four levels (ground to third floor) being parking levels and levels four to five will accommodate 3 000m² of lettable office space. The remaining sixth slab will be a roof slab for future extension.

Source: NMC Construction
 